state why Somerset Levels was prone to flooding
below sea level
overrun with artificial drainage
lack of river dredging
vastly high tidal range
increased extreme weather - more rainfall and winds
explain why Somerset Levels being below sea level made the area prone to flooding
Somerset Levels spans 250 square miles
majority of this area is below sea level
this made the land vulnerable to tidal and land-based flooding
the maximum attitude in this area is only 8m above sea level
explain why Somerset Levels being overrun with artificial drainage made the area prone to flooding
thousands of years ago, the area was covered by sea
however today, it’s a landscape of rivers and wetlands
which are artificially drained, irrigated and modified to allow productive farming
explain why Somerset Levels lacking river dredging made the area prone to flooding
the River Tone and the River Parrett run through Somerset Levels
neither river has been dredged properly in 20 years
this left farmland and homes without proper defence from floods
as the non-dredged sediment washes downstream
the accumulation of sediment downstream raises the river bed and reduces the river capacity
state the definition of dredging
act of removing silt and other material
from the bottom of bodies of water
which increases river depth and capacity
explain why Somerset Levels having a vastly high tidal range made the area prone to flooding
the Severn Estuary (Bristol Channel) has the second highest tidal range in the world
explain why Somerset Levels experiencing increased extreme weather made the area prone to flooding
early 2014 - UK was hit by the worst storms for 20 years
a succession of storms developed over the Atlantic, tropical and polar maritime air masses also blew in
this caused high wind speeds due to the pressure differences between the two air masses
this resulted in the Somerset Levels receiving 200-250% of its usual winter rainfall
state the human causes of the 2014 flooding in the Somerset Levels
building has developed on the floodplain, much of which is below sea level
thousands of years ago, the are was covered by sea, but today it’s a landscape of rivers and wetlands which are artificially drained, irrigated and modified to allow productive farming
farming practices have changed and become more intensive which means land is less able to retain water
the Rivers Tone and Parrett which run through the Levels had not been dredged properly for 20 years
the River Parrett in particular was blocked an in desperate need of dredging
the dredging process used to happen every 5 years (costing £4 million)
state the physical causes of the 2014 flooding in the Somerset Levels
prolonged rain, hurricane-forced wind speeds and tidal surges caused widespread flooding
the storms were caused by a powerful jet stream driving low pressure systems and their storms across the Atlantic Ocean
from mid-December 2013 to mid-February 2014 there were 12 major storms
the Severn Estuary has the second highest tidal range in the world and when it is high tide floodwater doesn’t travel out to sea as quickly
the majority of this area is below sea level, making the land vulnerable to tidal and land-based flooding - maximum altitude of the Levels is only 8m above sea level
at 193% of average rainfall, it was the wettest January in England since 1910
state the social consequences of the Somerset Levels flood, 2014
people had to move - impacted transport to work/school
hard to access homes due to flooding
the mental health of local residents was harmed largely by the flood
165 homes were affected by the flood
state the economic consequences of the Somerset Levels flood, 2014
people not be able to get insurance coverage for flooding in Somerset Levels
insurance premiums had also increased vastly
total cost of damage to properties is approx. £16 million
house values depreciated in the flooded areas
houses were being sold at 2/3 of their price
houses were flooded and damaged - this caused people to have to pay to move
state the environmental consequences of the Somerset Levels flood, 2014
local fauna had no food to eat and were drowning in the flood waters
this led to loss of biodiversity in Somerset
state the social short term impacts of the Somerset Level flood, 2014
81 road closures
this meant residents in Muchelney (village) could only leave the island by boat, which left every 2 hours
hundreds of people had to evacuate
people were reluctant to leave their homes dur to fears of looting
trains disrupted Bristol line between Bridgwater and Taunton
many residents had to seek temporary accommodation elsewhere
high opportunity for thieves
900L of fuel was stolen from pumping stations in Westonzoyland
state the economic short term impacts of the Somerset Level flood, 2014
tourism industry lost £200 million
50% of businesses impacted by flooding
86% of businesses impacted by road closures
costs of necessary goods started to rise
emergency fuel pumps used to reduce water levels during flooding cost £200,000 per week
local businesses reported over £1 million losses
cost the county’s tourism industry £200 million
state the environmental short term impacts of the Somerset Level flood, 2014
fluctuations in wildlife numbers, breeding patterns and locations for some species
maximum area of land on the Levels covered by winter floods 65 km²
state the social long term impacts of the Somerset Level flood, 2014
lack of trust in government from local communities due to mis-handling of floods pre and post the event
loss of livelihoods from permanent damage to farmland
emotional devastation and heartbreak from losing homes
more than 600 homes were flooded
state the economic long term impacts of the Somerset Level flood, 2014
insurance prices increased - went up five fold after flooding and will were set to triple as a result
government had to invest in long-term flood defence engineering to protect areas at risk
dredging, tidal barrage and extra permanent pumping sites cost £100 million
8km dredging of the Rivers Parrett and Tone cost £6 million
state the environmental long term impacts of the Somerset Level flood, 2014
soil was damaged after being under millions of tonnes of water for months
it took 2 years for soil in the Levels to recover
6880 Ha of farm land was flooded
state the local stakeholders in the Somerset Levels flooding, 2014
FLAG (residents)
Somerset County Council
state the regional stakeholder in the Somerset Levels flooding, 2014
Environment Agency (EA)
state the national stakeholders in the Somerset Levels flooding, 2014
Royal Marines
government (including David Cameron)
state the local management strategies of the Somerset Levels flooding, 2014
Thorney village put in a £180,000 earth embankment built to help protect 10 houses
section of A372, between Aller and Othery (which had been flooded), reopened after 11 weeks of flood prevention work
this work included installing a temporary bridge
the finishing of this prevention work marked the first phase of flood protection at Beer Wall
28 miles of flood-affected roads were repaired and resurfaced
FLAG formed to help support local residents affected by the floods and pressure the government to do more
state the regional management strategies of the Somerset Levels flooding, 2014
there was a Somerset County Council plan to fund a new ‘Somerset Rivers Authority’
this was initially funded by the national government (£2 million was paid), but future funds rely on enhanced maintenance of river channels and flood banks in order to help reduce the risk of flooding
two councils - Somerset County and Sedgemoor District - declared a ‘major incident’ in a bid to mobilise extra support
they raised £1.5 million towards repairs
a list of 10 trigger points on the Somerset Levels have been drawn up which allow additional pumps to be switched on to remove water from a given area
state the national management strategies of the Somerset Levels flooding, 2014
a ‘Somerset Levels and Moors Action Plan’ was formed
it was a 20 year, £100 million plan commissioned by Environment Secretary Owen Paterson
David Cameron said ‘money is no object’ - national government announced the funding of £10.5 million to the project
the Department of Transport is backing it with £10 million
the Somerset Rivers Authority is working with Sedgemoor District Council and the EA on plans to create a £100 million tidal barrier across the River Parrett by 2027
it will protect ~13,000 homes and 1,500 businesses from coastal changes
Royal Marines were deployed to help villagers cut off by the floodwater
the EA installed 62 pumps, working 24/7 to remove 1.5 million tonnes of water
state embankments definition
raised banks along the river
increase the capacity of the river by making it deeper
increased capacity increases the volume of water able to flow
this prevents the water from bursting the river’s banks and flooding
state sluices definition
artificial channel for carrying water
contains an opening at one end to control the flow of water
sluice gates can reduce water flow downstream by preventing water from flowing any further
this decreases water volume downstream, preventing the water from bursting the river banks
this prevents flooding downstream, where there may be settlements