New cards

In the code of ethical conduct, the architect's duty to not render professional services without a professional service agreement falls under which article?

The architect's responsibility in relation to their colleagues and subordinates

2
New cards

In the code of ethical conduct, the architect's duty to carry out their professional work without undue delay and within an agreed reasonable time limit falls under which article?

The architect's responsibility in relation to their clients

3
New cards

The licensed professional who shall prepare and submit a certificate of completion of the project stating its conformity to the code including the approved plans and specifications:

Architect in charge of construction

4
New cards

Single-attached or duplex building/structure of from one storey up to three storeys in height and with each unit for separate use as single-family dwellings

Basic R-2

5
New cards

ISA + USA = ?

TOSL

6
New cards

PSO + ISA = ?

MACA

7
New cards

To build his single-attached home, Mr. ABC acquired a 336 square meter rectangular lot in an R-2 basic zone, with a 12 meter frontage facing a 12 meter RROW. What is the maximum length of firewall allowed for this development?

22.40m

8
New cards

PSO + TOSL = ?

TLA

9
New cards

AMBF / TLA = ?

PSO

10
New cards

Abutment of one side is allowed for any R-1 lot type or location.

True

11
New cards

Which of the following uses are not allowed on public easement?

Both A and b

12
New cards

The minimum and allowable width of temporary walkway in case there is no sidewalk in front of the building site during construction:

1200mm

13
New cards

Which is the correct statement?

Both are correct

14
New cards

A continuous and unobstructed route of exit from one point in a building/structure/facility to a public way consisting of 3 distinct parts:

Means of egress

15
New cards

For how many years will Ar. JKL be held civilly liable for the architectural plans she signed?

15 years

16
New cards

Which of the following is/are within the scope of SPP Doc 204-A?

Evaluation of construction works

17
New cards

Which of the following is/are within the scope of SPP Doc 204-A?

Both a and b

18
New cards

Which of the following is/are within the scope of SPP Doc 204-A?

Filing of documents

19
New cards

Which of the following is/are within the scope of SPP 204-B?

Cost and time control

20
New cards

Which of the following is/are within the scope of SPP 204-B?

Both a and b

21
New cards

Which of the following is/are within the scope of SPP 204-B?

Both a and b

22
New cards

The recommended professional fee (RPF) for an — DBS by administration shall be ___% of the Project Construction Cost, exclusive of the Architect's Fee for the Regular Design Services.

7%

23
New cards

Mr. and Mrs. LMN engage Ar. OPQ to design their dream home to be situated on an R-1 zone. Assuming the PCC is Php 1,500,000, how much should Ar. OPQ charge as RPF for DAEDS?

150,000

24
New cards

In the code of ethical conduct, the architect's duty to respect and help conserve the systems of values with the natural, historic, and cultural heritage of the community in which they create architecture falls under which article?

The architect's responsibility in relation to the people

25
New cards

The powers and functions of the Board of Architecture include:

Supervise the registration, licensure, and practice of architects

26
New cards

The qualifications of an applicant for the board exam for architects include:

None of the above

27
New cards

Mr. ABC got a grade of 85% in History and Theory, Principles of Planning and Architectural Practice; 81% in Structural Design, Building Materials, and Architectural Specifications and Methods of Construction and Utilities; 48% in Urban Design and Architectural Interiors; and 91% in Architectural Design and Site Planning. Given these grades, which statement is correct?

Mr ABC failed the ALE

28
New cards

Mr. ABC got a grade of 81% in History and Theory, Principles of Planning and Architectural Practice; 89% in Structural Design, Building Materials, and Architectural Specifications and Methods of Construction and Utilities; 58% in Urban Design and Architectural Interiors; and 91% in Architectural Design and Site Planning. Given these grades, which statement is correct?

Mr ABC passed the ALE

29
New cards

Mr. DEF, while waiting for the oathtaking ceremony, was convicted of a political offense. Given this situation, which is correct?

Mr. DEF cannot be refused the issuance of their COR and PIC

30
New cards

Mr. DEF, while waiting for the oathtaking ceremony, was convicted of a criminal offense. Given this situation, which is correct?

Mr. DEF can be refused the issuance of their COR and PIC

31
New cards

Mr. GHI, a graduate of BA Architecture from a prestigious university in Switzerland, is currently in the process of having his degree recognized by CHED to qualify for the ALE. Despite this, he claims on his professional social media pages that he is an architect. Which provision of RA 9266 is violated?

25

32
New cards

Mr. GHI then gained a client. Since he cannot sign and seal the documents yet, he asked Ar. JKL to sign the architectural documents on his behalf. What section of RA 9266 is this violating?

32

33
New cards

The architect registered and licensed under RA No. 9266, who is directly and professionally responsible for the total design of the project for the client and who shall assume the civil liability for the plans, specifications, and contract documents he/she has signed and sealed:

Architect of record

34
New cards

The architect registered and licensed or permitted to practice under RA No 9266, who is professionally and academically qualified and with exceptional or recognized expertise or specialization in any branch of architecture:

Consulting architect

35
New cards

Scope of practice of architecture includes:

Both a and b

36
New cards

The existing official national organization of all architects of the Philippines in which all registered Filipino architects shall be members without prejudice to membership in other voluntary professional associations:

Integrated and Accredited Professional Organization

37
New cards

A document embodied in the architects national code, which defines all aspects of professional service, prescribes minimum basic fees, and establishes the rights and obligations of both the architect and the client:

Standards of professional practice

38
New cards

Door openings in means of egress shall not be less than ___ mm in clear width.

710

39
New cards

Maximum slope of an accessible ramp with a rise of 650mm:

1:15

40
New cards

Maximum slope of an accessible ramp with a rise of 550mm:

1:15

41
New cards

Maximum slope of an accessible ramp with a rise of 750mm:

1:20

42
New cards

Accessible handrails shall be installed at mm and mm above ramps and stairs.

900 and 700

43
New cards

Accessible parking slots shall have a dimension of:

4.00m x 5.00m

44
New cards

All accessible doors shall have a minimum door width of __ mm?

900

45
New cards

Turnabout spaces shall also be provided at or within __ mm of every dead end corridor.

3500

46
New cards

Accessible elevators shall be located not more __ meters from the entrance and shall be easy to locate with the aid of directional signs.

30

47
New cards

Workstations designed for accessibility shall ensure each desk counter is a minimum of __ mm wide to provide sufficient space for individuals using wheelchairs or mobility aids.

900

48
New cards

To build his single-attached home, Mr. ABC acquired a 336 square meter rectangular lot in an R-2 basic zone, with a 12 meter frontage facing a 12 meter RROW. How many square meters will be left after applying the maximum allowable setback requirements to maximize the lot?

230 sqm

49
New cards

Given the maximum allowable PSO of 60 for R-2 basic with firewall, what is the area of the TOSL (Total Open Space within Lot)?

134.40 sqm

50
New cards

Given the maximum allowable ISA of 30 for R-2 basic with firewall, compute for MACA

302.40 sqm

51
New cards

Compute for the minimum USA (Unpaved Surface Area).

33.60 sqm

52
New cards

A document which forms part of the architects national code which contains the norms and principles governing the practice of the profession of architecture:

Code of ethical conduct

53
New cards

A certificate bearing a registration number, issued to an individual, by the Professional Regulation Commission through the Board of Architecture, signifying that the individual has successfully passed the Licensure Examination and is registered to practice their profession as architect:

COR

54
New cards

Architectural drawings, specifications, and other outputs of an architect that only an architect can sign and seal consisting, among others, vicinity maps, SDPs, architectural program, perspective drawings, floor plans, elevations, sections, ceiling plans, schedules, detailed drawings, technical specifications and cost estimates, and other instruments of service in any form:

Architectural documents

55
New cards

Refers to the intellectual proprietary rights retained by an architect over any architectural documents or work that he/she prepares unless there is a written stipulation to the contrary:

Copyright

56
New cards

Means a detailed planning and design of the indoor/enclosed areas of any proposed building/structure, including retrofit or renovation work and which shall cover all architectural and utility aspects, including the architectural layouting of all building engineering systems found therein:

Architectural interior

57
New cards

Refers to the proprietary rights to an architectural work such as plans, designs and other documents by a person/ juridical entity who commissions the Architect:

Ownership

58
New cards

Refers to the author or authors of a set of architectural plans or specifications who are in charge of their preparation whether made by them personally or under their immediate supervision:

Authorship

59
New cards

Refers to physical planning at site, community or urban level by an Architect

Planning

60
New cards

The detailed planning of land or property on which vertical structures such as buildings, monuments and/or structures and horizontal developments such as rights-of-way, open spaces and recreational/ sports/ establishments/ tourism and related facilities are to be proposed:

Physical Planning

61
New cards

The detailed planning of all areas surrounding a building/structure and/or a group of buildings/structures but only within the property limits of the land on which such buildings/structures are to be erected:

Site Planning

62
New cards

Physical and systemic design undertaken by an Architect on a community and urban plane, more comprehensive than, and an extension of the architecture of buildings, spaces between buildings, entourage, utilities and movement systems

Urban Design

63
New cards

The act of conceiving, choosing and developing the type, disposition, arrangement and proportioning of the structural elements of an architectural work giving due consideration to safety, cost-effectiveness, functionality and aesthetics

Structural Conceptualization

64
New cards

A duly notarized written contract or equivalent public instrument stipulating the scope of services and guaranteeing compensation of such services to be rendered by an architect registered and licensed under R.A. No. 9266

Service Agreement

65
New cards

Are the documents attached to the agreement including all additions, deletions and modifications incorporated therein. These generally include the following documents: a) Special Provisions or conditions b) General Conditions c) Drawings d) Specifications e) Other Bid Documents

Contract Documents

66
New cards

A document bearing the registration number, date of issuance with an expiry date, due for periodic renewal, duly signed by the Chairperson of the PRC to a registered Architect upon payment of the annual registration fees for three (3) years

PIC

67
New cards

Mr. DFE passed the board exam while waiting for his COR and PIC was convicted of an offense, but in the opinion of the board—the offense is not valid. Can the board disqualify or refuse to give his COR?

Mr. DFE cannot be refused of by the board his COR

68
New cards

The powers and functions of the board of architecture include

Supervise the registration, licensure and practice of architects

69
New cards

The recommended professional fee for an DBS by guaranteed maximum cost shall be _____% of the project construction cost

10%

70
New cards

Mr. ABF engage Ar. CFG to design their dream home to be situated in an R1 zone. Assuming PCC is PHP 10,000,000 what is the architects RPF for DADS?

600,000

71
New cards

Mr. QWE is a graduate of architecture in switzerland, he failed to get a temporary/ special permit that would allow him to practice architecture in the Philippines. Despite this he still advertised his services as an architect. Which provision of RA9266 did he violated?

Section 29

72
New cards

Mr. QWE then gained a client. Since he cannot sign and seal the documents yet, he asked Ar. LBC to sign the architectural documents on his behalf. What section of RA9266 is this violating?

Section 32

73
New cards

In the code of ethical conduct, the architect shall not use paid advertisement, nor use self-laudatory, exaggerated, or misleading publicity falls under which article?

The architect's responsibility in relation to the people

74
New cards

In the code of ethical conduct, the architect shall give the Contractor every reasonable assistance to enable him/her to fully understand the contents of the Contract Documents by furnishing clear, definite, and consistent information in all pertinent contract documents to avoid unnecessary mistakes that may involve extra costs to either the Contractor or the Client falls under which article?

The architect's responsibility in relation to the contractor

75
New cards

In the code of ethical conduct, the architect' shall not solicit free professional engineering/allied design or other technical services from manufacturers or suppliers of building materials or equipment when these are accompanied by an obligation detrimental to the best interest of the Client, or which may adversely affect the Architect's professional opinion falls under which article?

The architect's responsibility in relation to manufacturers, dealers, and agents

76
New cards

In the code of ethical conduct, the architect shall abide by the Basic Minimum Fee prescribed under the "Standards of Professional Practice" falls under which article?

The architect's responsibility in relation to their colleagues and subordinates

77
New cards

Refers to a sustaining and progressive learning process that maintains, enhances, or increases the knowledge and continuing ability of architects

Continuing Professional Development

78
New cards

Entities, agencies, organizations and the like that have been accredited/registered with the Board of Architecture of the Professional Regulation Commission to deliver seminars, lectures, and other continuing professional education modules for architects

CPD Providers

79
New cards

Which is true about accessible parking?

Accessible parking slot shall be located nearest to accessible main entrances.

80
New cards

Which of the following complies with BP344

Turnabout spaces shall be provided at or within 3500 mm of every dead-end corridor with a minimum clear dimension of 1.8m x 1.8m

81
New cards

For a ramp with a rise of 600mm what is the minimum length?

9m

82
New cards

Low-density residential zone, characterized mainly by single-family, single detached dwellings with the usual community ancillary uses on a neighborhood scale, such as executive subdivisions and relatively exclusive residential communities which are not subdivisions

Residential R-1

83
New cards

Low-rise multi-level building/structure of from three (3) up to five (5) storeys in height and for use as multiple family dwellings

Maximum R-2

84
New cards

Rowhouse building/structure of from one storey up to three storeys in height and with each unit for separate use as single-family dwellings

Basic R-3

85
New cards

Medium-rise multi-level building/ structure of from six up to twelve storeys in height and for use as multiple family dwellings

Maximum R-3

86
New cards

A medium to high-density residential use or occupancy, characterized mainly as a low-rise townhouse building/ structure for exclusive use as multiple family dwellings.

Residential R-4

87
New cards

A very high-density residential use or occupancy, characterized mainly as a medium-rise or high-rise condominium building/structure for exclusive use as multiple family dwelling

Residential R-5

88
New cards

Setbacks for 10.00 (and below) to 19.00 meters RROW (Front, Side, Rear)

5, 2, 2

89
New cards

Setbacks for 20.00 to 24.00 meters RROW (Front, Side, Rear)

5, 3, 3

90
New cards

Setbacks for 25.00 to 29.00 meters RROW (Front, Side, Rear)

6, 3, 3

91
New cards

Setbacks for 30.00 meters (and above) RROW (Front, Side, Rear)

8, 5, 5

92
New cards

What are the setbacks for a 7.00m RROW? (Front, Side, Rear)

5, 2, 2

93
New cards

What are the setbacks for a 17.00m RROW? (Front, Side, Rear)

5, 2, 2

94
New cards

What are the setbacks for a 21.00m RROW? (Front, Side, Rear)

5, 3, 3

95
New cards

What are the setbacks for a 28.00m RROW? (Front, Side, Rear)

6, 3, 3

96
New cards

What are the setbacks for a 35.00m RROW? (Front, Side, Rear)

8, 5, 5