Project Management

0.0(0)
studied byStudied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/20

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 4:22 PM on 10/17/24
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

21 Terms

1
New cards

Project Management

The application of knowledge, skills, tools and techniques to project activities to meet the project requirements

2
New cards

Project management scheduling techniques

PERT Charts, Critical Path Method, Gantt Charts

3
New cards

Organizations that undervalue Project management report

50% project failure

4
New cards

Does project management ensure that projects are completed n time?

Yes, within budget and with high quality.

5
New cards

Project management is crucial as it provides…

structured approach to achieving organizational goals

6
New cards

What are the 3 phases of project management?

Planning, Scheduling, Controlling

7
New cards

What is WBS

Work Breakdown Structures

8
New cards

Work Breakdown structures (WBS)

A project broken down into smaller, manageable pieces

9
New cards

Why Use a work breakdown structure?

Define dependencies, categoeize work, establish timeline, produce a statement of work (SOW), assign roles, estimate cost

10
New cards

Scheduling techniques

PERT, CPM, PERT + CPM, Gantt Charts

11
New cards

PERT (Program Evaluation Review Technique)

A method of analyzing a project’s tasks, focusing on the time needed to complete each task

12
New cards

PERT uses _ _____ estimates to define __

3 time estimates to define an expected time estimate

13
New cards

3 time estimates (OMP)

Optimisitc, Most-Likely, Pessimistic

14
New cards

E.T Formula

A + n m + b / avg # of components you’re adding up (6 would come from A + B and then n so if n was 4 then 6

15
New cards

PERT Scheduling shows

IF tasks must be completed in order or if they can be completed simultaneously

16
New cards

Is PERT frequently combiend with Critical Path Method?

Yes

17
New cards

Critical Path Method

Scheduling technique to map the sequence of scheduled activities that determines the duration of the project (critical path)

18
New cards

Critical Path is the ____ path taken

longest

19
New cards

Total project duration is the

sum of the individual duration of the critical path activities

20
New cards

T OR F: More tasks in a path does not necessarily mean its the critical path

True

21