1/44
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
What is risk in project management?
An anticipatable uncertainty that may cause problems if not addressed early.
T/F: A risk is often viewed as a problem waiting to happen.
TRUE
A risk is often viewed as a problem waiting to [blank].
happen
What is the probability range of a risk?
Between 0% and 100%, but never 100%.
T/F: The probability of a risk would be between 0% – 100% but never 100%.
TRUE
The probability of a risk is between [blank]% and [blank]%, but never 100%.
0; 100
Why must risks be anticipated during planning?
To address uncertainties and avoid negative effects on project outcomes.
T/F: A project manager must anticipate and address risks as early as possible during project planning.
TRUE
A project manager must anticipate and address risks during [blank] planning.
project
What is the most probable risk in software projects?
Schedule overrun.
T/F: The most probable risk is schedule overrun.
TRUE
The most probable risk in software projects is [blank] overrun.
schedule
List some common risks in software projects.
Technology availability assumptions, new methodology misunderstandings, constraints miscalculation, requirement changes, incompetence, unrealistic expectations.
T/F: Misunderstanding requirements or constant change of requirements are common risks.
TRUE
Common risks include misunderstanding or constant change of [blank].
requirements
How should project managers build an initial risk list?
List unclear deliverables, unresolved task issues, and resource risks.
T/F: The first step in risk identification is to create a list of those “unclear” items for each deliverable.
TRUE
Risk identification starts with listing [blank] items for each deliverable.
unclear
What is risk prioritization?
Ordering risks based on importance, tolerability, or potential damage.
T/F: Risk prioritization is ordering risks based on set criteria.
TRUE
Risk prioritization orders risks based on set [blank].
criteria
What is recovery cost in risk analysis?
Effort or financial cost to solve a problem if a risk occurs.
T/F: Measuring recovery cost is assigning risks into ordered categories such as low, medium, or high.
TRUE
Recovery cost categories may be [blank], [blank], or [blank].
low; medium; high
What alternative to low/medium/high categorization exists?
Numerical scale (e.g., 1–10) dividing recovery cost into increments.
T/F: Recovery cost can also be assigned a numerical category, such as 1 to 10.
TRUE
Recovery cost numerical scheme divides cost into [blank] equal increments.
10
What is risk mitigation?
Planning activities to reduce, minimize, or avoid risks.
T/F: Risk mitigation may reduce, minimize or totally avoid a given risk.
TRUE
Risk [blank] may reduce, minimize, or totally avoid a risk.
mitigation
What are examples of risk mitigation strategies?
Hiring extra staff, offering incentives, using alternative integration methods.
T/F: Hiring an extra person for backup is an example of risk mitigation.
TRUE
Hiring an extra [blank] for backup is an example of risk mitigation.
person
What factors influence mitigation decision-making?
Ease of mitigation, probability of success, cost of mitigation.
T/F: The cost of each mitigation alternative is just an estimate and carries risk.
TRUE
Mitigation decision-making includes ease, probability of success, and [blank].
cost
What is mitigation value cost?
A combined metric of success probability and dollar cost of a mitigation option.
T/F: Mitigation value cost includes estimated probability of success and actual dollar cost.
TRUE
Mitigation value cost includes success probability and [blank] cost.
dollar
Why must a risk plan include target dates?
To ensure risks are removed after mitigation or dependency changes.
T/F: A risk plan would be of limited utility if it did not include target dates by which the risks were to be eliminated.
TRUE
A risk plan must include [blank] dates by which risks are eliminated.
target
When is a risk item removed from the risk list?
After mitigation success or change in dependency factors.
T/F: A risk item may be removed from the list after successful mitigation or a change in dependency factor.
TRUE
A risk item may be removed after successful [blank] or dependency factor change.
mitigation