1/50
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No analytics yet
Send a link to your students to track their progress
Which of the following is the logical sequence of the schedule processes?
Define Activities, Develop Schedule, Sequence Activities, Estimate Activity Durations | |
Define Activities, Estimate Activity Durations, Sequence Activities, Develop Schedule | |
Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Durations | |
Define Activities, Sequence Activities, Estimate Activity Durations Develop Schedule |
Define Activities, Sequence Activities, Estimate Activity Durations Develop Schedule
Who is the best person or group to select and implement the most appropriate scheduling method and model?
Stakeholders | |
Project Manager | |
Scheduler | |
Project Team |
Project Team
What is the key output after the project schedule is developed and approved?
Schedule Baseline | |
Activity List | |
Milestone List | |
Project Schedule |
Schedule Baseline
Which of the following planning techniques is an example of progressive elaboration?
Activity List Planning | |
Precedence Diagraming Method | |
Rolling Wave Planning | |
Decomposition Planning |
Rolling Wave Planning
Which of the following schedule performance measurements rules is the most common, yet very subjective?
Percent Complete | |
Earned Value | |
Milestone Technique | |
Planned Value |
Percent Complete
The project team is beginning the process of developing their schedule and they need to define activities and create an activity list. Which project document is the best one to identify activities?
Work Breakdown Structure | |
Control Accounts | |
Stakeholder Register | |
Project Management Plan |
Work Breakdown Structure
In adaptive projects, the following activity is directly related to the time required to produce deliverables.
Iterations | |
Increments | |
Product Backlog | |
Task Backlog |
Iterations
Why is the Work Breakdown Structure (WBS) so important in developing project schedules and cost estimates?
Question 8 options:
The WBS dictionary is written to address 100% of the scope | |
The WBS work package is decomposed to identify schedule activities | |
Starting with the WBS results in integrated cost and schedule baselines | |
All the above |
All the above
The reason for breaking work packages down into small activities is to:
Question 9 options:
More effective schedule management | |
Better see what is being planned | |
Make cost estimating easier | |
Collect cost at a better level |
More effective schedule management
Milestones can be any significant event and usually is either at the beginning or end of activities that result in a deliverable. What is the average duration of milestones?
Question 10 options:
> 1 month | |
0 days | |
5 days | |
1 week |
0
Once a schedule has been developed which of the following techniques can be used to create a more realistic schedule?
Question 11 options:
Adding Leads | |
Adding Project Buffers | |
Adding Feeding Buffers | |
All the above |
all
Which of the following techniques shortens, accelerates or decompresses a schedule?
Question 12 options:
Adding Leads | |
Adding Project Buffers | |
Adding Feeding Buffers | |
All the above |
Adding Leads
One of the most common precedence diagraming methods to define activity relationships is:
Question 13 options:
Time Logic Diagram | |
Milestone Chart | |
Gantt Chart | |
Activity on Node (AON) Diagram |
AON
Which activity relationship would you most likely choose if 2 activities should be worked in parallel?
Question 14 options:
Finish-to-Start | |
Start-to-Start | |
Start-to-Finish | |
None of the above |
Start-to-Start
The most common schedule activity relationship is:
Question 15 options:
Start-to-Start | |
Start-to-Finish | |
Finish-to-Finish | |
Finish-to-Start |
Finish-to-Start
Which of the following estimating techniques uses a unit rate to estimate durations?
Question 16 options:
Bottom-ups | |
3-Point | |
Parametric | |
Analogous |
Parametric
There are two types of 3-point estimating: simple and PERT. One doesn't weight the Most Likely amount the other one does. The one that does, weights the Most Likely amount by how much?
Question 17 options:
5 | |
4 | |
6 | |
3 |
4
If a key stakeholder wants a quick estimate and is comfortable with a fairly large range, which estimating technique would be the best one to use?
Question 18 options:
Analogous | |
Parametric | |
3-Point | |
Bottom-ups |
Analogous
There are many types of reserves used in both scheduling and cost estimates. What is the name of the reserve type that is included in the project baseline and under control of the project team?
Question 19 options:
Management Reserve | |
Contingency Reserve | |
Baseline Reserve | |
Project Reserve |
Contingency Reserve
Looking at a schedule precedence diagram, how would the project team identify the critical path?
Question 20 options:
Select the one with the longest duration | |
Select the one with the most critical resources | |
Select the one with the most important activities | |
Select one with very little float |
Select the one with the longest duration
What is the name of the type of float that equals the amount of time that an activity can be delayed without delaying the project finish date?
Question 21 options:
Free Float | |
Feeding Float | |
Project Float | |
Total Float |
Total Float
If the project team is using the Critical Chain scheduling method to account for constrained resources, what types of buffers can the team use to address the constraints?
Question 22 options:
Feeding Buffers | |
Project Buffers | |
Float | |
Both a and b |
Both Feeding and Project
Which resource optimization technique is used to balance resources and does not affect the critical path or the project completion date?
Question 23 options:
Fast-Tracking | |
Smoothing | |
Leveling | |
Crashing |
Smoothing
Which of the following combination of scheduling techniques accelerates the schedule without increasing resources?
Question 24 options:
Fast Tracking and Lags | |
Crashing and Lags | |
Crashing and Leads | |
Fast Tracking and Leads |
Fast Tracking and Leads
The project is behind schedule, over budget and used all its cost reserves and the team does not want to go to management and ask to extend the project end date. Which of the following schedule compression techniques should the project team use?
Question 25 options:
Crashing | |
Adding Lags | |
Reduce Scope | |
Fast Tracking |
Fast Tracking
Which of the following documents and artifacts is used to record and track schedule actual performance in an adaptive project?
Question 26 options:
Task Backlog | |
Burndown Chart | |
Project Schedule | |
Schedule Baseline |
Burndown Chart
An excellent tool for identifying and creating requirements that uses a model of the expected product is called?
Question 27 options:
Benchmarking | |
Mind mapping | |
Context diagrams | |
Protoyping |
Protoyping
Your project is currently in the Execution phase and your cost performance is spiraling out of control. To determine if any action needs to be taken, you create and issue a change request. What process is being used to accomplish this?
Question 28 options:
Validate Scope | |
Control Scope | |
Create WBS | |
Define Scope |
Control Scope
Where would you capture information to "ensure" the WBS met the 100% Rule?
Question 29 options:
Product Scope | |
Project Scope | |
WBS | |
WBS Dictionary |
WBS Dictionary
What is the name of the WBS element that has been selected for the purpose of scope, budget and schedule performance management?
Question 30 options:
Planning Package | |
Work Package | |
Control Account | |
Code of Account |
Control Account
The following process uses tools and techniques to ensure that deliverables meet the acceptance criteria and are ready to transition to the project owner?
Question 31 options:
Control Scope | |
Control Quality | |
Close Project or Phase | |
Validate Scope |
Validate Scope
What is the major output created when all the scope planning processes have been completed?
Question 32 options:
Scope Management Plan | |
Scope Baseline | |
Requirements Management Plan | |
Configuration Management Plan |
Scope Baseline
As the project manager, you've decided that the physical composition of a deliverable needs to be changed. Which of the following change systems should you use?
Question 33 options:
Configuration Management System | |
Project Management Information System (PMIS) | |
Change Management System | |
Product Scope Change System |
Configuration Management System
The key output for Validate Scope process is?
Question 34 options:
Accepted deliverables | |
Transferable deliverables | |
Verified deliverables | |
Approved deliverables |
Accepted deliverables
For monitoring and controlling processes, which of the following is always and output?
Question 35 options:
OPAs | |
Approved change requests | |
EEFs | |
Change requests |
Change requests
A characteristic of a good work package is:
Question 36 options:
Concise title | |
Small enough to adequately collect costs | |
One responsible individual or organization | |
Detailed description in the WBS Dictionary |
One responsible individual or organization
There are two types of work breakdown structures. Pick one of the two types.
Question 37 options:
Work Package Based | |
Phase Based | |
Planning Package Based | |
Control Account Based |
Phase Based
An example of progressive elaboration is:
Question 38 options:
Work packages | |
Scope creep | |
Assumption log | |
Rolling Wave Planning |
Rolling Wave Planning
A good input for identifying and collecting requirements is:
Question 39 options:
Requirement Breakdown Structure | |
Requirement Traceability Matrix | |
Lesson-Learned Register | |
Work Breakdown Structure |
Lesson-Learned Register
Which is the project document used to describe the project requirements, deliverables, and the acceptance criteria?
Question 40 options:
Product Scope | |
Project Charter | |
Scope Statement | |
Work Breakdown Structure |
Scope Statement
Requirements are very important. They have their own management plan. They also have a tool developed to define and track them throughout the entire project lifecycle. What is the name of that tool?
Question 41 options:
Requirements Management Tool | |
Requirements Traceability Matrix | |
Configuration Management System | |
Product scope |
Requirements Traceability Matrix
Which of the following project products are used to define scope in adaptive projects?
Question 42 options:
Iteration Backlog | |
Burndown Chart | |
Product Backlog | |
Kanban Board |
Product Backlog
Which of the following is not part of the scope baseline?
Question 43 options:
Scope Statement | |
Scope Management Plan | |
WBS | |
WBS Dictionary |
Scope Management Plan
The following process verifies deliverables have been created correctly in accordance with which plans?
Question 44 options:
Create WBS | |
Control Scope | |
Control Quality | |
Validate Scope |
Control Quality
Which of the following project products are used to measure progress in predictive projects?
Question 45 options:
Work Breakdown Structure | |
Baselines | |
Subsidiary Plans | |
Burndown Charts |
Baselines
Which of the following activities must be completed to create the scope baseline?
Question 46 options:
Work Breakdown Structure | |
Scope of Work | |
All the above | |
WBS Dictionary |
all
What is the used to provide the basis for determining product and project scope?
Question 51 options:
Activities | |
Tasks | |
Stakeholder Register | |
Requirements |
Requirements
What is the name of the technique used to create a WBS?
Question 47 options:
Planning Package | |
Rolling Wave Planning | |
Decomposition | |
Work Packages |
Decomposition
What is the name of the subsidiary plan other that the Scope Management Plan that is an output for the Plan Scope Management process?
Question 50 options:
Scope Change Management Plan | |
Configuration Management Plan | |
Requirements Management Pan | |
Scope Acceptance Plan |
Requirements Management Pan
Adaptive projects break scope into increments, then use the following to create and develop the deliverables?
Question 48 options:
Retrospective | |
Product Backlog | |
Daily Scrum | |
Iterations |
Iterations
Which of the following is not a characteristic of Scope Creep?
Question 49 options:
Minor changes in scope | |
Major and minor changes in scope | |
Unapproved adjustments | |
Occurs over a long period |
Major and minor changes in scope