1/106
Flashcards covering key vocabulary terms from the Project Management glossary (Course 3).
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
Backward pass
Starting with the final task or milestone and moving backwards through the schedule to find the shortest path
Baseline
The reference dollar amount used to gauge whether a project is on track and to measure its success
Baseline a budget
Creating a fixed spending reference point to measure and compare project progress
Bottom-up approach
Listing all project parts and their costs from start to finish and adding them together
Budget
The estimated monetary resources needed to meet a project’s goals and objectives
Budget pre-allocation
A situation in which a budget is set before the project begins
Budget risk
The possibility that project costs will rise because of poor planning or scope creep
Buffer
Extra time added to a task or project to absorb unexpected delays
Capacity
The amount of work people or resources can reasonably complete in a given period
Capacity planning
Allocating people and resources to tasks and confirming needed resources are in place
CAPEX (capital expenses)
Expenditures incurred to create future benefits
Cash flow
The inflow and outflow of cash on a project
Cause-and-effect diagram
Visual that shows possible causes of an event or risk; also called a fishbone diagram
Communication
The flow of information—what is shared, how, and with whom
Communication plan
Document that organizes the process, types, and expectations of project communications
Contingency budget
Money included to cover unforeseen events not in the cost estimate
Contingency reserves
Funds added to the estimated cost to manage identified risks
Cost of quality
Costs incurred to prevent problems with products, processes, or tasks
Cost performance index (CPI)
Ratio of percentage complete to actual costs
Cost variance (CV)
Difference between budgeted and actual costs for completed work at a point in time
Critical path
Sequence of milestones and mandatory tasks required to meet the project goal on schedule
Decision tree
Flowchart showing the wider impact of a decision across a project
Dependency
Relationship in which one task’s start or finish relies on another task
Dependency graph
Visual representation of task dependencies in workflow
Direct costs
Costs that occur directly within a project
Earliest start date
In CPM, the earliest a task or project can begin
Earned value management (EVM)
Technique for regularly comparing budget and schedule actuals to the plan
Effort estimation
Prediction of the amount and difficulty of active work needed for a task
Empathy
Ability to relate to others’ thoughts and feelings
Ethical trap
Situation that may lead someone to make unethical choices
Finish-to-finish (FF)
Dependency where Task 1 must finish before Task 2 can finish
Finish-to-start (FS)
Dependency where Task 1 must finish before Task 2 can start
Fishbone diagram
Another name for a cause-and-effect diagram
Fixed contract
Contract paid when specified milestones are achieved
Fixed costs
Costs that remain unchanged over the project duration
Fixed start date
Date on which a task must begin to achieve a goal
Float
Amount of time a task can be delayed before it affects the schedule
Forecast
Cost estimate or prediction over a period
Forward pass
Scheduling method that moves forward from the first task to the last
Gantt chart
Horizontal bar chart that visually maps project tasks, owners, and due dates
High-level risk
Serious risk that can affect overall project success and needs stakeholder discussion
Impact
Degree of damage a risk could cause (high, medium, low)
Indirect costs
Costs that can’t be linked directly to a specific project
Inherent risk
Risk measure calculated by its probability and impact
Issue
Known, real problem that can hinder task completion
Kanban board
Visual tool for managing tasks and workflows
Kickback
Corruption scheme where a percentage of a contract is paid to secure the bid
Knowledge management
Ensuring project data is accessible for future use
Latest start date
In CPM, the latest a task or project can begin
Leverage experts
Using expert insights to perform tasks more effectively
Low-level risk
Risk with low impact or probability; may not need stakeholder communication
Management reserves
Budget percentage set aside for unknown risks
Medium-level risk
Urgent risk likely to impact project; requires stakeholder communication
Milestone
Significant point that shows progress or phase completion in a schedule
Need-to-know basis
Providing only the necessary information at the required time
Network diagram
Visual that sequences project tasks by dependency order
Non-disclosure agreement (NDA)
Document maintaining confidentiality of information
Open-ended question
Question that cannot be answered with yes or no
OPEX (operating expenses)
Day-to-day expenses required to run a company
Optimism bias
Belief that negative events are unlikely to affect oneself
Parallel tasks
Tasks that can occur simultaneously
Personally identifiable information (PII)
Data that can directly identify or locate an individual
Planning fallacy
Tendency to underestimate time, costs, and risks of a task
Planning phase
Second phase of project life cycle involving schedule, budget, and risk plan
Probability and impact matrix
Tool for prioritizing project risks
Probability
Likelihood that a risk will occur
Procurement
Obtaining materials, services, and supplies for a project
Project budget
Estimated monetary resources to meet project goals
Project buffer
Extra time added to the end of a project
Project kick-off meeting
Initial meeting aligning team on vision, goals, scope, and roles
Project management baseline (PMB)
Fixed starting point covering scope, budget, and schedule
Project plan
Document recording scope, tasks, milestones, people, documentation, and time
Project task
Activity to be completed within a set period
Reforecast
Creation of a revised budget based on project tracking
Request for proposal (RFP)
Document outlining project details to solicit vendor bids
Reserve analysis
Method for checking remaining project resources
Resource cost rate
Cost of a given resource
Risk
Potential event that can impact a project
Risk appetite
Organization’s willingness to accept risk outcomes
Risk assessment
Estimating or measuring risk qualities
Risk management
Process of identifying and evaluating project risks and issues
Risk management plan
Living document listing risks, their probability/impact, and mitigation plans
Risk register
Table or chart containing a list of project risks
Root cause
Initial cause that introduces a risk or problem
Schedule
Project timeline including start, end, and interim dates
Schedule performance index (SPI)
Ratio of work complete to the planned budget for that work
Schedule variance (SV)
Difference between planned and actual work completed
Scope risk
Possibility that results won’t meet project goals
Sequential tasks
Tasks that must be completed in a set order
Single point of failure
Risk that can halt work across an entire project
Slack
Time a task can be delayed past its earliest start without delaying the project
Soft skills
Personal traits that help people work well with others
Sole-supplier sourcing
Restricting bidding to one supplier, eliminating competition
Start-to-finish (SF)
Dependency where Task 1 must start before Task 2 can finish
Start-to-start (SS)
Dependency where Task 2 can’t start until Task 1 starts
Statement of work (SoW)
Document specifying products and services a vendor will provide
Subtasks
Smaller tasks required to complete a larger task
Subject matter expert (SME)
Person with deep knowledge of a specific area
Summary task
Header describing a collection of subtasks in a project plan
Task buffer
Extra time added to a specific task