OPRE 3330 - Cost Managemen

0.0(0)
studied byStudied by 0 people
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/66

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

67 Terms

1
New cards

What is a common cause of project failure?

Cost

2
New cards

What do PMs need to consider in order to determine the overall cost of a project?

Time, Resources, Scope

3
New cards

Project Cost Management:

Planning, budgeting, financing, funding, and controlling costs so that the project can be completed within the APPROVED budget

4
New cards

Project Cost Management Challenges) Lack of resources

The PM will have a hard time securing the resources(people, technology, materials) necessary to complete the project on-time

5
New cards

Project Cost Management Challenges) Poor Cost Estimation

Most common issue in failing projects. Poor estimation/forecasting can occur when a PM isn’t experienced enough(Ex. cost, scope, schedule). Poor cost estimation can often lead to cost overruns.

6
New cards

Project Cost Management) What DO you need for an accurate cost estimate?

A well-defined scope, robust WBS, a complete project schedule with activities and their durations and resource estimates, etc.

7
New cards

Fixed Cost:

This type of cost doesn’t change as production changes throughout the project

8
New cards

Variable Cost:

This type of cost will vary with the amount of work or production and changes month to month

9
New cards

Direct Cost:

Only occurs because of the project and can be DIRECTLY attributed to it(Ex. Salaries/wages, purchased parts, manufacturing supplies)

10
New cards

Indirect Cost:

Cost incurred for the benefit of MORE than one project. Not incurred for one specific project.(Ex. Heating, lighting, taxes, renting out an office space)

11
New cards

Plan Cost Management(Planning Phase):

Define how the project costs will be estimated, controlled, and monitored through the project lifecycle.

12
New cards

Estimate Costs(Planning Phase):

Approximate the costs of all resources that are needed to complete project work(Ex. Labor, materials, equipment, services)

13
New cards

Determine Budget(Planning Phase):

Add the estimated costs of individual activities or work packages in order to establish a baseline

14
New cards

Control Cost(Monitoring & Control):

Monitor the project status in order to update project costs and MANAGE changes to the cost baseline

15
New cards

Estimate Costs) Types of Costs for Estimation

  1. Cost of quality efforts and risk efforts

  2. Cost of the PM’s time.

  3. Cost of project management activities

  4. Expenses for physical office spaces, and overhead costs

  5. Salaries and general office expenses.

16
New cards

Estimate Costs) Use following inputs to estimate costs

Cost management plan, risk register and previous projects, scope baseline and project schedule

17
New cards

Analogues Estimating:

Your neighbor made a perimeter fence and it cost them $100, THEREFORE, you can estimate that it will take around $100 dollars for you to make YOUR fence.

18
New cards

Parametric Estimating:

Uses a mathematical model based on historical records from other projects.

19
New cards

Parametric Estimating: Example

It costs you $100 to build 5 feet of fence. To build 10 feet of fence, it can be estimated that it will cost $200(100 × 2)

20
New cards

Bottom-Up Estimating:

Rollup the cost for individual activities, with each schedule activity being calculated and then aggregated

21
New cards

3-point Estimating:

Takes a weighted average of the optimistic, pessimistic, and most likely estimates.

22
New cards

3-Point Estimating(Formula):

(0 + 4M + P)/6

23
New cards

Reserve Cost:

The extra money in the project budget that’s to be used if necessary

24
New cards

Reserve Cost) Contingency Reserve:

The money held in order to pay predictable but unspecified extra costs(Ex. a breakdown in the manufacturing line)

25
New cards

Reserve Cost) Management Reserve:

Money assigned to the project for unknown costs, it’s money that senior management controls.(Ex. If something happens during the project that changes the scope, the money would be used then)

26
New cards

Estimated Cost:

The TOTAL project cost estimate that the PM makes

27
New cards

Budgeted Cost:

A budget that the manager has prepared and allocated to the project

28
New cards

Determine Budget:

You aggregate the estimated costs of individual activities/individual costs to come up with an authorized cost baseline

29
New cards

Cost Baseline:

Time-phased budget used to measure, monitor, and control cost performance during the project(Includes contingency reserve but NOT management reserve)

30
New cards
<p>Q: What is the <strong>project estimate?</strong></p>

Q: What is the project estimate?

$100 + $200 + $400 +$100 = $800

31
New cards
<p>What’s the <strong>cost baseline?</strong></p>

What’s the cost baseline?

The project estimate + contingency reserve = $800(project estimate) + $80(Contingency Reserve) = $880

32
New cards
<p>What’s the <strong>Project Budget?</strong></p>

What’s the Project Budget?

Cost Baseline + Management Reserve = $880(cost baseline) + $50(Management Reserve) = $930

33
New cards

Earned Value Management)Control Costs

Monitor the project status in order to update project costs and manage changes to the cost baseline

34
New cards

Earned Value Management(EVM):

Method of project performance and progress measurement through the project lifecycle regarding schedule control and cost control

35
New cards

Earned Value Management(EVM):Part 1

Integrates project schedule, costs, and scope in order to measure overall performance

36
New cards

Earned Value Management(EVM): Part 2

Compares the BUDGETED and ACTUAL costs of a project

37
New cards

When do PMs use EVM?

  1. When there is a risk to on-time and on-budget project delivery

  2. When cost and schedule need to be managed

38
New cards

What questions do EVMs answer?

  1. Are we AHEAD or BEHIND of schedule?

  2. Are currently UNDER or OVER budget?

  3. When is the project LIKELY to be complete?

  4. What’s the remaining work LIKELY to cost?

39
New cards

Planned Value:

How FAR ALONG the project work is supposed to be at any point in the schedule.

40
New cards

Budget at Completion(BAC):

The total Planned Value for the project

41
New cards

Earned Value:

Shows the work that’s been performed until now(represents the COST of the work completed until now)

42
New cards

Actual Cost(AC):

Amount of resources used to perform the work thus far(sum of $ used so far)(represents the ACTUAL money spent to-date on a project)

43
New cards

EV< PV:

Project is BEHIND SCHEDULE(earned less than planned)

44
New cards

EV>AC:

Project is UNDER BUDGET(spent less than the value earned)

45
New cards

EV<AC:

Project is OVER BUDGET(earned value less than money spent)

46
New cards

EV = AC

Project is on-budget

47
New cards

EV>PV:

Indicates a project is AHEAD Of schedule

48
New cards

Schedule Variance(SV): A measure of schedule performance. How is it calculated?

EV - PV(it’s the difference betweeen the work DONE and the work PLANNED to be done)

49
New cards

Positive SV:

Project is AHEAD of schedule

50
New cards

Negative SV:

Project is BEHIND schedule

51
New cards

Cost Variance(CV):

The amount of budget deficit or surplus at a given time

52
New cards

Cost Variance Calculation:

EV(Earned Value) - AC(Actual Cost)

53
New cards

Positive CV:

A project is UNDER budget

54
New cards

Negative CV:

A project is OVER budget

55
New cards

Schedule Performance Indicator(SPI):

Shows how efficient a project team is in utilizing time during a project

56
New cards

SP > 1

Project team is VERY EFFICIENT in using time during the project.

57
New cards

SP < 1

Project team is NOT EFFICIENT in using time during the project

58
New cards

CPI:

Shows how efficient a project team is in utilizing resources(money) for the project

59
New cards

CPI > 1

GOOD efficiency in using the resources allocated to the project

60
New cards

CPI < 1

BAD efficiency in using the resources allocated to the project

61
New cards
<p>What is the SV for the project?</p>

What is the SV for the project?

EV - PV = $70,000 - $60,000 = $10,000

62
New cards
<p>What is the CV for the project?</p>

What is the CV for the project?

EV - AC = $30,000 - $50,000 = -$20,000(OVER BUDGET)

63
New cards
<p>What is the SPI?</p>

What is the SPI?

EV/PV = 30,000/15,000 = 2(ahead of schedule)

64
New cards
<p>What is the CPI?</p>

What is the CPI?

EV/AC = 30,000/60,000 = 0.5

65
New cards
<p>You have a project you’re managing with an SPI of 1.1. What’s the best way of describing this project?</p>

You have a project you’re managing with an SPI of 1.1. What’s the best way of describing this project?

C. The project is progressing at 110% of the rate originally planned for the schedule.

66
New cards
<p>What does a CPI of 0.63 on a project imply?</p>

What does a CPI of 0.63 on a project imply?

The project only EARNS $0.63 value of work for every $1 spent

67
New cards
<p>What are the <strong>schedule variances </strong>and <strong>cost variances?</strong></p>

What are the schedule variances and cost variances?

SV: $7,300 - $9625 = -$2325(behind schedule)

CV: $7300 - $12000 = -$4,700(behind schedule)