Gantt chart
A visual representation of a project schedule showing activities and the time required to complete each.
Main uses of a Gantt chart
To list project activities, estimate time for each, and track progress against the schedule.
Adjusting project resources with a Gantt chart
Shift workers to other projects if ahead of schedule or add workers if behind schedule.
PERT chart
A graphical representation of a project's tasks, their sequence, and the critical path for project completion.
Critical path in a PERT chart
The longest stretch of dependent activities that determines the minimum time needed to complete the project.
Difference between PERT and Gantt charts
PERT charts emphasize task dependencies and critical paths, while Gantt charts focus on individual task timelines.
Importance of identifying the critical path
Delays in critical path activities will directly impact the project's completion deadline.
Critical activities in the classroom renovation project
Activities A, B, D, G, H, and I, as any delays will cause the project to miss its deadline.