1/83
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
egress
a means or a place of going out, an exit
egress system (three parts)
Exit access (hall, stairs) exit (door to outside) and exit discharge (route from exit door to the public way — IE street) MUST BE CONTINUOUS
Exit Passageway
Enclosed exit connecting a required exit or exit access with a public way— like a hall on ground floor must have 1 or 2 hour rating
panic hardware
door latching assembly using an unlatching device that has an activating portion
travel distance
total distance an occupant in a building must travel from any point (usually the farthest) to reach an exit
Occupancy classification (10)
assembly (theater, stadium, nightclub etc.)
business (office, higher education, Clinics)
educational (K-12 education)
factory and industrial (low hazard factories)
high hazard (flammable products)
institutional (inpatient care, nursing homes)
mercantile (retail, grocery stores, gas stations)
residential (1&2 family dwelling, apartments)
storage (warehouse)
utility and miscellaneous (towers, tanks, greenhouse)
exit code
Two exits (at all time, except less than 30 people) must be places a distance not less than ½ the diagonal dim of building or area to be served
two exit stairs must be minimum 30 feet apart
what is the maximum travel distance to nearest exit
200 ft if un-sprinklered and 250 ft if sprinklered, may increase up to 100 ft in 1 hour fire rated exit corridor
Width of exits
in occupancies w/ sprinklers-in inches take occupancy load and multiply by 0.3” for stairs and 0.2” for other exits
total width divided among all exits
exits cannot pass through….
kitchens, storerooms, restrooms, or closets
corridors
must be 1 hr rated
dead end max length of 50 ft (w/ sprinklers)
min width (occupancy load x .2”)
absolute min 44” for 50 or more occupants
36” min for 49 or less
stairways
50 or more occupancy- 44” min width
49 or less- 36” width
multiply occupancy by 0.3”
6’8” clear head room
high rise buildings
over 75 ft (fire apparatus cant reach above)
need automatic sprinkler, smoke detectors, alarms, communication systems, central control for fire dept, smoke control, and stand by power
Types of construction
type 1 Fire resistive (protected steel & Concrete)
type 2 Non-Combustible (unprotected steel)
type 3 Ordinary (noncombustible walls, combustible floors & roofs)
type 4 Heavy Timber (minimum thickness wood construction)
type 5 Wood Frame Construction (any Material allowed by code)
Material and engineering
Structural requirements (dead loads, live loads, wind, seismic)
Interior finishes (smoke & fire development)
exterior assemblies (roof, walls, glass)
prescriptive design ( prescribed, requirements & referenced standards)
performance design (performance objectives engineering analysis)
prescriptive design
relies on code minimum referenced standards the design team requires in drawing and specifications (energy requirements, fire testing, wind loading)
Performance design
Typically involves an outside engineer/ consultant that is part of the design team or that the contractor employs to design an assembly or system
existing and historic structure codes
don’t require all provisions of new construction
specific allowances for items such as fire separation, doors and stairways req.
appeals are a tool to maintain existing elements
form based zoning
compact, pedestrian friendly, mixed-use communities
counteracts excessive consumption of land and erosion of character of the built environment
pattern books are heavily used to align with initial development
long range plans
preferred physical development of municipality
address land use, community goals, housing, infrastructure, economic development environmentally sensitive areas, quality if life, etc
iterative and many adjustments are made over time
allows citizens to become involved in planning
environmental plans
long range plan can strike a balance between environmental quality and stewardship
communities can realize the cost benefits of planning, designing, and building w/ sustainable methods
environmental plans should include a statements of goals policies and guidelines for critically sensitive
fire protection
Sprinkler system (NFPA 13, NFPA 13R, MFPA 13D)
standpipes
portable fire extinguishers
fire alarm and detection system
smoke control systems
requirements for fire protection systems are based on
occupant load, number of stories above and below grade, and building height
life safety systems include
fire- suppression systems (sprinklers, standpipes, etc.)
fire alarm and voice evacuation systems
emergency lighting systems
exit sign systems
when are fire suppression and alarm system required
when fire separations do not exist between more than one occupancy type (IE apartments over mercantile)
req. in type IV and VI construction, especially in combination with large occupancies, large interior spaces, &/or tall buildings
wet pipe systems
fixed fire protection using piping filled with pressurized water, supplied from a dependable source
closed, heat sensitive automatic sprinkler
how wet pipe works
as water flows through an alarm system is activated to indicate the system is operating
only sprinklers immediately over or adjacent to the fire operate, minimizing water damage
exit and egress lighting
exit lights at all exits and directional exit lights in pathways to exits
illumination of means of egress (the exit access, the exit, and the exit discharge) should average one footcandle at floor level
fire alarm (where required)
smoke detectors req. in bedrooms or residences, hotel rooms, dormitories, etc.
fire alarm system in all educational occupancies
fire alarm system in office buildings with 5000 sqft or more above or below the first floor
fire alarm system consists of
a main fire alarm control panel
an annunciator Panel at the main building entry for fire department use
initiating devices: smoke detectors, heat detectors, duct-mounted smoke detectors, flame detectors, manual pull stations
signaling devices: horns, strobes, speakers, phone connections to offsite monitoring
Construction administration or contract administration
least understood phase of design by the public
underestimated in terms of time required
3 hats of the CA architect
as an independent contractor (for the owner)
as an agent of the owner
as quasi-judicial officer
as an independent contactor (for the owner)
during design
during CDs
during construction
having authority to act for the owner
during construction, represent owner’s best interest
keep owner informed
reject non-conforming work
as quasi-judicial officer
judge performance of the contract between owner & contractor
make fair interpretations of the documents
make decisions of claim by the parties against each other (IE late payment by owner, nonconforming work by contractor)
CA services
ensure that construction conforms to CD’s
support design intent
lessen project risks
identify & resolve cost. problems early
supplement the client’s const. knowledge
importance of CA
owners lack experience
architects are liable for their designs, correct execution is critical for their own protection
usually constitutes 25% of an architect’s fee
our contract with the owner calls for us to preform periodic observation of construction
typical “day to day” services
one day per week on site
responding to questions from contractor and material suppliers
review show drawings & submittals
review & certify monthly certificates for payment
typical CA team
construction administration
project architect
project assistant
administrative assistant
cost estimators & spec writers
consultants
required record keeping
log of distribution of plans (& deposits) during bidding
document and distribute bidding results
record contractors application for payment
record submittals from contractor
records relative to change in the work
contracts
records the promise made by the parties
delineates the service and compensation
allocates risk
helps in coping with change
provides methods for resolving disputes
lawsuits against architects
55% by owners
bc owners are dissatisfied, unclear expectations, or architects have unclear expectations of their clients
contracts make explicit what otherwise remains unsaid
architects usually prepare the contracts
between owners and contractors
proposals
preliminary
marketing
generalities regarding services, fees and schedules
can require an owner’s signature acknowledging acceptance
oral agreements are
valid, just difficult to prove
AIA documents
over 100 years old
most widely accepted contracts
AIA Pro Practice CD
construction contract structure
owner- contract agreement
general conditions
supplementary conditions
special or other conditions
drawings
specifications
addenda
modifications
owner- contractor agreement
signed portion
identifies parties, project name, location
contract sum
describes work
time of commencement & completion
process for contractors payment
types of contractor compensation (3)
stipulated sum (fixed price bid)
cost plus fee
unit-price
liens (mechanical Lien)
used in cases were individuals who provide work (which can not be repossessed) and are not paid can use the work as collateral
must be filed 30-90 days
bid bonds
guarantees that contractors will enter into a contract with the owner id bid accepted and that the contractor will provide a performance and labor& material bond
preformance bonds
covers 100% of construction cost (bond can cost 1 to 1.5 %)
labor & material bond
protects owners against claim of subs
types of insurance
AIA G610 gives guidelines for selecting types and coverage of insurance
contractors insurance
owners insurance
site observation
periodic observation of construction by the architect is required
must notify the owners of construction progress and/or changes
observation of construction is required in order to check contractors pay application
how often site visits
at least once a month but usually every week
may occur on specified day and time each week or impromptu
things to bring to site visit
notepad
camera
pay application
CDs
tape recorder
boots/ hardhat
what to do on the site
1st meet with superintendent to review
take notes for field report
take photo of job conditions
notify owner of any urgent questions/observations
observe on-site testing if possible
field reports
note date, time, weather, persons on site at time of report
short bullet points for observations and actions
record observations
show be dictated or typed
emailed and mailed to all parties
on-site/off-site testing
usually required by public owners but a good idea for any job
specs notify parties which items are to be tested
paid for by owner, separately, could be included in the contract
types of testing
soil tests
boring, bearing capacity, percolation
concrete tests
slump test, cylinder, core test
welding tests
bolt torque tests
what items are included in construction documents
specifications, drawings, contracts, addenda, modifications, and architect fee proposal
true or false: an architects’ standard of reasonable care determined by a judge, is to do the best we can
false
who dictates the standard and conventions drawing preparation
office standards, user/client standards, CSI
define life cycle cost analysis and give an example
when you have to inform the owner that their may be extra cost depending on if something will last EX: wall paint lasts longer than vinyl wall coverings
when should cost estimating and/ or budget evaluation be provided by the architect to the owner per the AIA documents
initial client meeting and at the end of each phase of design
True or false: it is not customary that architects revise the construction documents if the lowest construction bid exceeds the budget
false
define a construction cost contingency and give an example
A construction cost contingency is a budget buffer included in project cost estimates to cover unforeseen expenses or changes during construction. EX: extra money set aside that can be used if inflation raises prices
five main design phase as defined by AIAs
1. schematic design 2. design development 3. construction documents 4. bidding and negotiations 5. construction development
true or false: Bidders may be required to be pre-qualified on public construction projects
false
true or false: typical bid periods for public projects are 30 days
true
what is the procedure for commercial plan review in Lafyette
architects sends to Lafyette plan review and State fire marshal
true or false: addendums may be issued no less than 72 hours prior to the bid date
true
what are two advantages and two disadvantaged a design build project delivery method?
advantages- faster construction completion and single point of responsibility
disadvantage- less owner control over design and not anyone to offer oversight
in a negotiated contract, the builder may be asked to provide a cost-plus with guaranteed max. what is this?
it means that there is a max amount of money spent when constructing a building. they cannot exceeds this amount, if they spend under the amount they may receive an incentive
True or false: if a publicly funded project is re-bid, some conditions of the contract must be revised prior to re-bidding
true
what is an advantage of a design bid build project delivery system
architect can offer oversight
true or false: drawings usually do not refer to the level of quality of product, materials etc
true
who are construction documents for?
builders, owners, code officials
true or false: an additive alternate to a bid is an option for the contractors to make product submissions
false
if specifications lists a specific manufacture and model number then they are
property specs
true or false: cash allowances in specs are an incentive for contractors to save money for the owner
false
BIM is sometimes referred to as being 5 or 7 dimensional besides X,Y,and Z what are other dimensions
time & sustainability, cost & operation, performance
Define addendum and give an example
any corrections or additions made to CDs during the bidding process
list three of the items not usually included in a cost estimate which the architect must remind the owner of
furniture costs
architects fees
inflation