1/74
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
0
0
1
1
Critical Path Method and Crashing
0
Steps 1-4
Make network diagram.
Determine paths and critical path (the longest).
Find slack. (Occasional)
Find Available Weeks of Crashing.
Steps 5-8
To make network diagram, use
activity, immediate predecessor, and normal time (NT).
Normal time can be
days, weeks. Just make sure it's TIME.
To determine paths and critical path, use
network diagram.
During step 2, add all of the NTs that are in a path together. The path that's the
longest is the critical path.
During step 3, first, find EARLY start and EARLY finish. Next, find
LATEST start and LATEST finish.
EARLY start and EARLY finish is moving to the
right.
With EARLY start and EARLY finish, ALWAYS start with
0.
With LATEST start and LATEST finish, ALWAYS pick the
LARGEST number from ES and EF.
LATEST start and LATEST finish is moving to the
left.
Available Weeks of Crashing is
normal time - crash time. = NT - CT.
Crashing Cost Per Day is
crash cost - normal cost / normal time - crash time.
Essentially, Cost/Time.
= CC - NC / NT - CT
After finding total normal cost, find
total project cost.
Total Project Cost =
Total Normal Cost + Indirect Cost + Penalty Cost
To find Total Project Cost, you must take the Indirect Cost given and
multiply by the Critical Path found earlier.
To find Total Project Cost, you must take the Penalty Cost given and
multiply by the Critical Path found earlier subtracted by the "if the project takes longer than _ number _"
additional cost.
what you save.
REALLY think of the numbers underneath + as
positive.
REALLY think of numbers underneath - as
negative.
When trying to find the Net, use the
correct signs for the numbers underneath the + and -.
Total in the graph is
Total Project Cost.
First action will ALWAYS be
DO Nothing.
After first crash, look at
After you select the activity to crash, cross out
the number associated with Available Weeks of Crashing. Make it one less.
Take $ from Crashing Cost Per Week and
write it underneath +.
Take Indirect Cost and Penalty Cost and
write it underneath -.
The same Indirect Cost and Penalty Cost will always be written underneath - until a certain point. It's related to
"if the project takes longer than _ number."
After the Critical Path reaches the number associated with "if the project takes longer than _ number" then for the next crash,
there is NO MORE Penalty.
Take PREVIOUS Total and subtract by
CURRENT Net.
Whenever crashing an activity, subtract 1 week by
ALL the paths that are affected by THAT specific activity. If it's multiple, do this as well.
Take this: "If the project takes longer than _ days." When the critical path reaches that day,
stop putting Penalty Cost underneath -.
Minimum Cost Schedule is the
last Critical Path.
Minimum Cost Schedule Savings is
FIRST Total - LAST Total.
Skim the information before
drawing the network diagram.
When finding the paths, go from the
top of the diagram to the bottom. Really follow the lines.
Duration for the project is the / "Before crashing, the project duration is _ week(s)." is the
Critical Path.
"The total cost of the project if we do nothing is $ __ " is the
Total Project Cost.
Essentially, duration is
critical path.
Must subtract both F
FINISHES. Late first.
Must subtract both S
STARTS. Late first.
LF - EF and LS - ES must be the
same.
If we were to draw Activity Time with a circle around it, ES and EF would be together at the top and
LS and LF would be together at the bottom.
The first paths in the graph are the
paths you found while trying to find the Critical Path.
When trying to figure out what to crash next, go back to the
Critical Path.
When you are down to 2 letters in the critical path OR after a while,
find a letter that impacts ALL paths and crash that one.
Look for opportunities to
crash two things at once.
When trying to figure out two things to crash at once,
pick the combination that is the smallest.
After crashing for a while, if a letter is only on ONE path, consider
stopping. There may be nothing else you can do.
STATISTICAL PROCESS CONTROL
0
Mean
is the total sum of all the values in a sample.
X-Bar
is the mean of the sample. The average value of a set of numbers
X-Double Bar
is the average of the means of the samples.
R-Bar
is the average of the measurement differences R for all samples.
R
is range.
σ
is the standard deviation of the process distribution.
“selects a random box of 5 packets” means
sample size is 5 packets.
“decided to take random samples of 53 patients” means
sample size is 53
“concerned over the number of times patients must wait more than 30 minutes” or “to see how many in each sample had to wait more than 30 minutes” means
data is an attribute.
Steps to Find LCL R and UCL R:
1 Find data type. Attribute or Variable. This will determine what chart to
2 Determine what chart you are making and what formula you are solving for.
3 Determine sample size (n).
4 Find R-Bar.
5 Find either D3 or D4.
6 Solve
Steps to Find σ p
1 Find data type. Attribute or Variable. This will determine what chart to
2 Determine what chart you are making and what formula you are solving for.
3 Determine sample size (n).
4 Number of Defects / Sample Size (n). Do this for EACH sample in graph.
5 Add all of the PREVIOUS answers up and then divide by the number of samples ON THE GRAPH to find the average/p-bar. Focus. Find the average/p-bar
6 Use the equation inside the square root (formula sheet) to find σ p.
*Steps to Find LCL P and UCL P
1 Find data type. Attribute or Variable. This will determine what chart to
2 Determine what chart you are making and what formula you are solving for.
3 Determine sample size (n).
4 Number of Defects / Sample Size (n). Do this for EACH sample in graph.
5 Add all of the PREVIOUS answers up and then divide by the number of samples ON THE GRAPH to find the average/p-bar. Focus. Find the average/p-bar
6 Use the equation inside the square root (formula sheet) to find σ p.
7 Use equation (formula sheet) to find the control limits.
“the range in the weight of each sample has averaged 9 grams” means
the R-bar is 9.
A2, D3, and D4 are determined by
the sample size (n).
Data is attribute if it’s the following:
Categories, good/bad, # of mistakes, pass/fail, yes/no, shift #
Data is variable if it’s the following:
Weight, time, cost, length, speed, money, rate, pressure.
Equation inside the square root (formula sheet) is
σ p. It’s also known as standard deviation.
In (), lower limit first, then
upper limit.
Must use subtraction to find
lower limit.
Must use addition to find
upper limit.
LCL can never be
negative - because negative proportions don’t exist. The LCL will be 0 instead.