185 Terms

1
New cards

The project must be reevaluated in view of the new long term strategic plans.

Your company has just revised its long-term goals and objectives as well as its long term strategic plans. What is the impact on an existing project?

None. Proceed as planned.

The project must be reevaluated in view of the new long term strategic plans.

Accelerate the schedule before any directive to change the project.

Finish the project. It conformed with the company's strategy at the time it was approved.

2
New cards

scope, schedule, and budget

The final __________, _________, and ____________ plans are captured as baselines for the project, which the sponsor approves before the project moves into the execution phase.

3
New cards

Dedicated

a ____________ project manager's role in life is to be a project manager regardless of the operational needs of the business.

4
New cards

working

a product design manager was also responsible for the operational delivery of the product is a __________project manager

5
New cards

scope, time and budget

the triple constraints of a project

6
New cards

project plan

A _____________ __________

should include approved requirements, a schedule resource plans, and budgeting requirements.

7
New cards

stakeholder

Anyone who is involved with the project from inside or outside of the organization that is either a user or contributor to the project and the organization

8
New cards

Project Manager

Who manages the varying interests of stakeholders?

9
New cards

regularly and timely

The frequency of project status meetings is based on stakeholders' interests and communication needs, but they must be regular and timely.

It is important that project status meetings are held ____________________________

10
New cards

weekly internal status

During the meeting, each leader speaks to the status of their work. Risks and the status of any mitigation activities are discussed. Based on the discussion, the PM assembles the team reports and updates them into one document.

11
New cards

Monthly Management Project Review

This meeting includes three highlights, three lowlights, three issues, milestones that show the project schedule performance compared to baseline, and a standard financial performance trend chart.

12
New cards

Monthly Customer Meeting

Using the team's last prior weekly report and the customer meeting information from last month, the PM covers project performance to schedule and financial performance for the project. Product and contract issues and discussions are also held at this time.

13
New cards

False

The real purpose of a status meeting beyond informing, which can be done in writing, is to get questions and raise issues before they become problems! You will save time if you find out information and issues as early as possible.

True or False: Status meetings should be held only with the sponsor to keep questions to a minimum and conserve time.

14
New cards

project status meeting

Choosing the reports that a project will use is closely linked with selecting the_____________________ __________ _____________

15
New cards

scheduling

A Gantt chart is an example of a

____________________

tool.

16
New cards

The maximum number of hours that should go by before checking in with a team member

One of the project manager's tools for communicating is the 8 and 80 Rule. What does the number 80 refer to in this rule?

17
New cards

Setting aggressive deliverables and schedules

Combining people of different skills and backgrounds

Asking people to work on the tasks needed without giving them the whole picture

Which of the following are causes of conflict in teams? (Select all that apply.)

Setting aggressive deliverables and schedules

Combining people of different skills and backgrounds

Working on risk resolution through a variety of collaborative platforms

Asking people to work on the tasks needed without giving them the whole picture

18
New cards

communication with the team

Which is a way to avoid conflict in a project?

19
New cards

Conflict can teach the project manager and team members something critical about the project that was not previously known.

How can conflict be an opportunity?

20
New cards

They are best practices that may not apply to every project in every company in every industry.

Which of the following statements about the PMBOK and PRINCE2 standards is correct?

They enforce systems and processes to ensure efficiencies and project safety.

The review process is lengthy so standards may not be relevant and don't reflect the best practices of the time.

They are best practices that may not apply to every project in every company in every industry.

They dictate the project management processes and standards that a PM needs to understand and adhere to.

21
New cards

Standards

What specifically do PMBOK and PRINCE2 to provide to projects?

22
New cards

PMP - Project Mgmt Professional

Which certification has the largest number of practitioners registered globally?

23
New cards

IPMA

Which organization issues competency-based certifications but does not have a standard such as the PMBOK?

AXELOS, Ltd

Project Management Institute (PMI)

International Project Management Association (IPMA)

Association for Project Management (APM)

24
New cards

Axelos

Which organization oversees the PRINCE2 certification?

AXELOS, Ltd

Association for Project Management (APM)

Project Management Institute (PMI)

International Project Management Association (IPMA)

25
New cards

PMI

Which organization would you go to if you wanted to become a certified PMP?

Project Management Institute (PMI)

AXELOS, Ltd

Association for Project Management (APM)

International Project Management Association (IPMA)

26
New cards

Functional (Departmentalized)

Projectized

Matrix

There are essentially three types of organizational structures:

27
New cards

depends on the type of matrix

A project manager's level of authority in a matrix organization:

28
New cards

project manager

In a strong matrix organization, a, SMEs assignments come from the

29
New cards

functional

A project manager has no authority in a _________________ organization

30
New cards

matrix

In a _______________organization, administrative personnel are not duplicated in each project team.

31
New cards

projectized

Timely decision making is an advantage of a ________________________ organization.

32
New cards

functional

organizational structure used by gov entities?

33
New cards

projectized

The project manager always has a full-time role on a project when the organizational structure being used is

34
New cards

PMO - project management office

In an organization with only one project that is not very complex, there is no need for a

35
New cards

project maturity model

a process for determining if the level of documentation and best practices were followed in project execution.

36
New cards

The lowest maturity level of any of the processes

The overall organizational maturity level is determined by

37
New cards

Lessons and best practices are applied

According to OPM3, what takes place during the fifth and final level of project management maturity?

38
New cards

corporate strategy

PMOs can help an organization to align project investment to __________ ____________

39
New cards

alignment

In project management the term ______________ is used to describe connecting project outcomes to company goals.

40
New cards

Models are singular in their vision of reality..

Because of their singularity of vision, models can ignore other aspects of a future project.

Which is a possible shortcoming of using a project selection model?

Models are singular in their vision of reality.

Models are not beneficial for estimating costs.

Models require an artist's conception.

41
New cards

False - Project checklists can include hundreds of items with many participants.

T or F: Project checklists are always a quick and simple approach to project selection.

42
New cards

False - he criteria used to accept or reject has nothing to do with an initiative being a project, program, or portfolio.

T or F: the selection criteria determines if the initiative is a project, program, or portfolio.

43
New cards

False - Any project is open to rejection if it cannot be justified. There may be other options to what was proposed that are more effective.

T or F; An operating necessity project is always approved.

44
New cards

False - A sacred cow project may be canceled once the project sponsor understands the lack of justification for continuing.

T or F: "Sacred cow" projects are never canceled.

45
New cards

True - Non-numeric analysis can be equally as good as numeric analysis, depending on the type of project being analyzed and the type of analysis used.

T or F: Non-numeric analysis

can be as good as

numeric analysis.

46
New cards

False - Checklists are not weighted but are basically a list of questions about the characteristics of the project.

T or F: Checklists assign weights to each selection criteria.

47
New cards

operating necessity

checklist model

What is an example of a type of non-numeric model for selection criteria?

48
New cards

sometimes

can also be based on scoring model

Numeric selection is

(sometimes or always)

based on profit/loss projections.

49
New cards

sometimes

Scoring models are numeric if relative important weights are assigned to each criteria.

Scoring models are

(sometimes or always)

numeric.

50
New cards

time value of money

the concept of _________________________________ suggests that money is worth more to an organization now than in the future

51
New cards

discounted

When adding the consideration of the time value of money to a payback period model, cash flows are Hint, displayed below

____________________

to reflect a more accurate estimate for the payback period.

52
New cards

True - There is not enough information provided. We would need to know how long each project lasts before we started to get any revenue to know the impact of the time value.

T or F: Including time value of money in the payback period equation will

have an unknown impact on

which of two projects being compared will be chosen.

53
New cards

Internal Rate of Return (IRR)

Which financial concept used for project selection evaluates projects in the same way that financial investments are evaluated?

54
New cards

True - This is a financial calculation using time and an interest rate.

T or F: The concept of IRR uses time value of money.

55
New cards

positive

If the future benefits exceed the costs of the project, the NPV is : + or -

56
New cards

True

The discount rate can be based on bank interest rates as well as other comparative rates for acquiring capital.

T or F: The discount rate in NPV can be equivalent to the interest rate that would be paid to a bank.

57
New cards

False

NPV includes all incomes and all expenses.

T or F: When calculating NPV, any one time expenses do not need to be included.

58
New cards

selection of the project

(if selected)

creation of project charter

Conclusion of the defining phase results in:

59
New cards

project proposal

Major project outcomes and deliverables, how the project will be completed, a high level estimate of the cost and completion time are included in the

60
New cards

When an idea for a project is identified by a company

When does the project defining phase begin?

61
New cards

planning

We officially leave the ______________+phase when the scope, budget (cost), and schedule (time) are approved by the customer and/or sponsor and the project team.

62
New cards

scope, budget, and schedule

The approved ________, ___________, and ______________become the baselines which will be used to measure project performance throughout execution

63
New cards

Work Breakdown Structure

The intent of a ___________ _____________ _____________is created to help ensure that stakeholders are satisfied that the project outcomes will be achieved and the project team understands the work which needs to be completed.

64
New cards

Scope creep

___________ __________ can quietly sneak in and sap money, resources and time.

65
New cards

Adding functionality without considering impacts

Which is an example of project scope creep?

Adding functionality without considering impacts

Having an incomplete project scope

Continually using change management procedures

66
New cards

deliverables

The intermediate outcomes from work activities are called

67
New cards

True - It is during the executing phase that changes to triple constraints are often identified and must be addressed.

True or false? During the executing phase, the project team may need to return to the planning phase in order to make adjustment to the budget, schedule, and/or scope.

68
New cards

closing

The project ____________ phase is when the project outcomes are delivered to the customer and/or sponsor and the customer and/or sponsor evaluates them to determine if they are acceptable

69
New cards

closing

During the _____________ phase, the customer may identify items that need to be corrected, which can require the team to replan parts of the project and then execute the revised activities in order to satisfy the expectations of the customer.

70
New cards

lessons learned

What is gathered and documented by the PM during the project closing phase?

71
New cards

Reassign project resources back to the company

Document the project results

Verify that the completed project is transitioned over to the customer

What does the PM need to do during project closeout? (Select all that apply.)

Reassign project resources back to the company

Document the project results

Verify that the completed project is transitioned over to the customer

Create downstream communication plans

72
New cards

measurable goals

Examples of _____________ ________________ include price point, maximum production time, total cost, and other factors.

73
New cards

business case

The project justification may also be referred to as the ___________ _____________

74
New cards

monitoring and controlling

During the monitoring process, if the PM detects that the project is not being executed as planned, she may need to intercede in order to correct the situation. We call this process, _____________________________

75
New cards

cost, schedule, scope

In the project execution phase, which are major areas for monitoring?

76
New cards

executing

The project deliverables and outcomes are created during the

___________________

phase of the project life cycle.

77
New cards

They will occur repeatedly as problems are detected.

Why are planning and executing considered iterative activities?

78
New cards

Completing administrative closeout

Which phase of the project closeout includes the archiving of all records?

79
New cards

Deliver project outcomes

Close all procurement activity

Complete administrative closeout

3 phases of project closing:

80
New cards

Each phase is a project with a deliverable.

How do the phases of iteration differ from the phases of the project life cycle?

81
New cards

uncertainties

Using phases of the iteration process to accomplish overall project outcome is a way of addressing

82
New cards

False

Iterative planning methods can allow the team to move forward with specific deliverables which will contribute to planning and executing future deliverables which will eventually lead to the desired project outcome.

True or false? An iterative planning process can be used if the team does not have sufficient time to thoroughly plan the project.

83
New cards

A decision point between phases of iteration.

Which is the definition of phase-gate?

84
New cards

Scope

_____________ is the number and type of features or functions

85
New cards

scope

statement of work (SOW)

The project ___________ is what the result of the project is desired to be. It defines the product of the project. It is sometimes referred to as the ___________ ____ ______________

86
New cards

scope creep

A well-written scope will clearly define every aspect of the project including functions and features, quality expectations, and time constraints. This helps prevent:

87
New cards

Triple Constraint

___________________ means that three items—scope, cost, and schedule—are tied together, and changing one affects the other two.

88
New cards

False - There are sometimes government mandated safety levels. In addition, reduction in safety level can lead to litigation if there are any injuries related to quality defects.

T or F: In the quality constraint, the customer can always revise the quality level to reduce costs or schedule.

89
New cards

critical path

The __________ ________ is defined as the path with the longest duration from the start of the project to its completion

90
New cards

milestone dates

________ _______ are key dates and critical events, such as safety inspections, which shape the project schedule.

91
New cards

False -

Float time is the difference between the time required for the critical path to complete and the time for another path to complete.

True or False.

Float time means that the time required to complete a task is unknown and can vary (float around).

92
New cards

True

T or F: Even though milestone dates are key dates in the project schedule, there are instances where they may be changed.

93
New cards

True

T or F: It is just as important to track progress of paths with long float times as tasks on the critical path.

94
New cards

True

T or F: Tasks on noncritical paths can have resources temporarily diverted to other tasks without impacting the schedule.

95
New cards

False -

The Gantt chart shows the elapsed time of the project but not the actual work hours. In order to do the budget, we need work hours X's hourly cost or fixed price for the elapse time to do the budget. Just having the calendar does not help us create a budget.

True or false? The PM has created a Gantt Chart for the project. She can now do the budget.

96
New cards

baseline

The ______________ determines what is included in the scope, what the schedule is, and what the costs are

97
New cards

The baseline documents the initial project scope that was agreed to.

The baseline provides a means of determining how much requested changes will cause deviation from original project plans.

The baseline can help determine how much, if any, float time has been used.

Which of the following statements about a project baseline are correct? (Select all that apply.)

The baseline documents the initial project scope that was agreed to.

The baseline provides a means of determining how much requested changes will cause deviation from original project plans.

It provides a way for the PM to assign blame when things go wrong.

The baseline can help determine how much, if any, float time has been used.

The baseline document indicates what we based all our estimates on.

98
New cards

Projected scope, schedule, and cost

What does a project baseline help to establish?

99
New cards

Deck staining is postponed until following summer.

In examining the triple constraints for a proposed vacation home, which development will impact the project scope?

Contractor must postpone the project start due to delays on another project.

Cost of specialized labor increases.

Sprinkler system takes extra day to install due to rainwater.

Deck staining is postponed until following summer.

100
New cards

PERT - Project evaluation and review technique

________________ is used to estimate activity duration times.