SAP Project Management (PS) oversees:
Projects, tasks, and timelines
Which of the following is a feature of SAP PS?
Automated project controlling linked to finance and accounting
Project coordination in SAP PS involves
Assigning work to the responsible person’s dashboard
Which of the following describes SAP PS organizational structure?
Needs to be defined for project execution and inherits structures via assignment
SAP PS productivity is mostly created through
Integration with other SAP modules
Which SAP modules is PS integrated into?
Finance and Logistics
The tool that allows users to edit projects quickly and efficiently in SAP PS is called:
Project Builder
Which of the following is a type of project in SAP PS?
Investment Projects
WBS stands for
Work Breakdown Structure
A WBS element describes
A concrete activity or sub-activity
Possible statuses of WBS elements include all EXCEPT
Rejected
The Hierarchy Graphic in SAP PS is used for
Planning costs, revenues, budgets, and schedules
Activities in SAP PS can be
Internally and externally processed
Which standard describes activities as “components of a process”?
DIN 69900
Which of the following is NOT a characteristic of an activity?
Customer Invoice
Which relationship type means an activity cannot start before the previous one ends?
Finish–Start (FS)
In Start–Start (SS) relationship
Both activities start together
Which relationship is defined as end of one activity linked to end of another?
Finish–Finish (FF)
Milestones in SAP PS are created in
Project Builder
Milestone Trend Analysis (MTA) is used to
Check payroll trends
In earned value analysis using the milestone technique, each milestone represents
Portion of work completed in an activity or WBS element
Which of the following is NOT a task of milestones?
Recruiting project team members
In Word Data, which field specifies the planned amount of work?
Work
The field “Number of Required Capacities” refers to
Required people or machines to complete an activity
Which PS process uses the project planning board as a graphical interface?
Project Planning
If a percentage is not entered in the Percent field, the system assumes
100%
Easy Cost Planning is executed at the
Project structure level
Which is NOT an entry in Easy Cost Planning?
Payroll Salary
In Project Closure, which type of settlement first settles costs to higher-level WBS element?
Multi-level Settlement
The SAP PS information system provides
Reports, graphs, and overview of performance, schedule, and costs