when old out of date
initial out of service was 2014, extended to 2023
what
British army’s new armored fighting vehicle program
how much money
5.5bn pounds for 589 vehicles
when expected
in march 2023, MoD announced 2025, with full operating capability expected in 2028-2029
ajax
recon
ares
personnel carrier
athena
command and control
argus
engineer recon
atlas and apollo
recovery and repair
when began
2010, initial expectation ajax enter service in 2017
issue 1
noise and vibration issues causing injury to soldiers
issue 2
management of program - high turnover of senior personnel with 5 since 2011 who only spent 10% of their time (up to 30% in 2018)
first full time program man
senior responsible owner (SRO) in october 2021
issue 3
MoD selected a “technically unproven and immature 40mm cannon”, caused technical problems
how many exposed to noise and vibration
310 total, 17 in specialist outpatient care, 4 discharged from army
issue 4
morpheus (computing and info system for ajax) has been delayed and had significant cost increases, meaning Ajax’s full digital capability will not be ready as early as intended
early trials couldn’t
travel more than 20mph or fire while moving
who said what 1
national audit office (NAO) said MoD not managed program effectively, it “faces significant challenges”
who said what 2
Public Accounts Committee said MoD’s management of program was “flawed from the outset”
2024 development 1
completed first firing on the move exercise
2024 development 2
over 150 ajax vehicles been produced