1/79
4-2 CPM Midterms
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No study sessions yet.
Project
Repetitive set of daily tasks
Main purpose of project management
To plan, organize, and control resources to meet objectives
Initiation
Phase that authorizes the start of a new project
Reopen the planning phase for proper completion
(Situational): A project nearing closure faces issues in deliverable hand-off because documentation is incomplete. What should the manager do?
Characteristic of Project
Unique purpose
Defined start and end
Progressive elaboration
Triple Constraint of Project Management
Scope, Time, and Cost
Fast Tracking
(Situational): The project manager decides to shorten the timeline by overlapping dependent tasks while managing risk. What scheduling strategy is being applied?
Initiate a formal change control process
(Situational): During project execution, a stakeholder requests an additional deliverable outside the original scope. How should the manager respond?
Analyze the critical path and adjust the schedule dependencies
(Situational): A project manager notices that certain high priority tasks are dependent on delayed materials. What should be the first step?
Schedule Compression
(Situational): A project manager observes that frequent design revisions are delaying progress. Which technique will best help realign the schedule?
Scope Verification
(Situational): A team completes most deliverables early but discovers missing documentation. Which process should be revisited?
Integration Management (Situational)
(Situational): A project halfway complete when a new regulation requires additional reports. Which knowledge area should guide how these changes are incorporated?
Milestone
A significant event marking progress
Responsibility Assignment Matrix
(Situational): Team members report confusion about overlapping responsibilities. Which document should clarify this?
100% Rule
Rule that ensures the WBS covers all project work?
Work Package
Lowest level of detail in a WBS
Accomplishment of WBS
Decomposes deliverables into manageable components
Gantt Chart (Purpose)
Tool for sequencing activities and identifying dependencies
Scope Statement
Defines the boundaries of what is included and excluded in the project
Integration Management (Definition)
Ensures that all project elements are coordinated effectively
Risk Management
Knowledge area that focuses on identifying, analyzing, and responding to uncertainties
Project Sponsor
Primary subject responsible for approving the project charter
Closing
The phase where final deliverable acceptance happens
Monitoring and Controlling
Process which ensures that the project objectives are being met
Planning
Process group that involves developing detailed schedules and budgets
Project Charter
The key output of the initiation phase
Gantt Chart (Represents)
Tasks over time using horizontal bars
Closing (Situational)
(Situational): The sponsor demands a report on whether objectives were achieved and lessons learned documented. Which process is being referred to?
Stakeholder Management
Knowledge area that governs stakeholder satisfaction
Cost Management
(Situational): The project’s cost baseline is exceeded while scope remains unchanged. Which area requires review?
Cost
(Situational) Rising material prices increase the project budget. Which constraint is affected?
Quality
(Situational) If the sponsor shortens the timeline but doesn’t add resources, it threatens what?
Cost Performance Index
(Situational) Completing tasks early but overspending requires checking the what?
Communication Management Plan
Document that ensures effective communication across all groups?
Cost Overrun
Indicates unapproved additions to the project work
Procurement Management
(Situational) Late delivery of outsourced materials should be handled under what?
Monitoring and Controlling (Situational)
(Situational) Conducting an ISO quality audit belongs to what?
Monitored periodically
(Situational) A high probability but low impact risk should be what?
Updating the Risk Register
(Situational) Identifying new risks during execution requires what?
Inefficiency through micromanagement
(Situational) An overly detailed WBS may cause what?
Gantt Chart
Chart that shows task dependencies clearly
Planning
Where using past lessons learned improves the process group
Project Documents and Lessons Learned
Outputs stored for future reference when the project ends
Critical Path
(Situational) A milestone delay caused by dependencies should lead the manager to inspect the what?
A formal change approval is obtained
(Situational) Both accepting a client’s change request, the manager must ensure that?
Ahead of schedule
(Situational) Completing 60% of tasks in 40% of the time indicates the project is what?
Progressive Elaboration
Refining project plans as new information becomes available
WBS Dictionary
Contains the detailed explanation of each WBS element
Behind schedule
(Situational) Earned value below planned value tells the manager the project is what?
Close the project and finalize documents
(Situational) Once objectives are achieved and deliverables accepted, the next step is what?
Change Management Plan
Document that outlines how changes will be requested, reviewed, and approved
Identified risks
Risk owners
Risk reponses
Risk Register contains
Activity List
An output of the “Define Activities” process
Primary Purpose of Schedule Baseline
Serves as the approved version of the project schedule
Rough Order of Magnitude
An estimate that is the least accurate during early planning
Stakeholder Register
Document listing individuals, their interests, influence, and engagement
Request for Quotation
Procurement document used to solicit price quotes
Project Management Plan
A collection of subsidiary plans that guide the execution and control
Critical Path in Schedule
Represents the longest path determining project duration
RACI Chart
Responsibility matrix used to assign tasks to team members
Variance Analysis
(Situational) When a project team compares actual performance against the baseline, they are performing what?
Lessons Learned Register Purpose
Capture insights to improve current and future projects
PERT
A scheduling technique uses optimistic, pessimistic, and most likely durations?
Pareto Chart
A quality tool used to display categories of defects in descending order
Float / Stack Scheduling
Time a task can be delayed without affecting the schedule
Resource Leveling
(Situational) A project team is adjusting resources to resolve over-allocation. This technique is what?
Avoided / Transferred
(Situational) A risk with low probability but very high impact should be what?
Contract Change Log
A document used to record formal communication during contract execution
FTF / Synchronous Communication
Communication method that is best for urgent, sensitive decision
Quality Management Plan
Defines the standards, metrics, and quality control procedures
Parametric Estimating
Cost estimation method that uses historical data and statistical relationships
Fallback plan
A backup response if the primary plan fails during risk planning
Issue
A current problem requiring action
Facilitation
An interpersonal skill which helps reduce conflicts and build consesus
Business Case
Identifies “WHY” a project is being undertaken
Highest-value Features
(Situational) A project uses agile-style iterations. What is prioritized first?
Close Procurements
(Situational) A project has multiple contractors. Which process ensures all agreements are completed?
Validation Scope
Performs formal acceptance of completed deliverables
Example of Preventive Action
Implementing a process to avoid future defects
Change Request
(Situational) A project needs a new tool to meet quality requirements. This request should be added to the what?