Midterms

0.0(0)
studied byStudied by 14 people
0.0(0)
full-widthCall with Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/79

flashcard set

Earn XP

Description and Tags

4-2 CPM Midterms

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No study sessions yet.

80 Terms

1
New cards

Project

Repetitive set of daily tasks

2
New cards

Main purpose of project management

To plan, organize, and control resources to meet objectives

3
New cards

Initiation

Phase that authorizes the start of a new project

4
New cards

Reopen the planning phase for proper completion

(Situational): A project nearing closure faces issues in deliverable hand-off because documentation is incomplete. What should the manager do?

5
New cards

Characteristic of Project

  1. Unique purpose

  2. Defined start and end

  3. Progressive elaboration

6
New cards

Triple Constraint of Project Management

Scope, Time, and Cost

7
New cards

Fast Tracking

(Situational): The project manager decides to shorten the timeline by overlapping dependent tasks while managing risk. What scheduling strategy is being applied?

8
New cards

Initiate a formal change control process

(Situational): During project execution, a stakeholder requests an additional deliverable outside the original scope. How should the manager respond?

9
New cards

Analyze the critical path and adjust the schedule dependencies

(Situational): A project manager notices that certain high priority tasks are dependent on delayed materials. What should be the first step?

10
New cards

Schedule Compression

(Situational): A project manager observes that frequent design revisions are delaying progress. Which technique will best help realign the schedule?

11
New cards

Scope Verification

(Situational): A team completes most deliverables early but discovers missing documentation. Which process should be revisited?

12
New cards

Integration Management (Situational)

(Situational): A project halfway complete when a new regulation requires additional reports. Which knowledge area should guide how these changes are incorporated?

13
New cards

Milestone

A significant event marking progress

14
New cards

Responsibility Assignment Matrix

(Situational): Team members report confusion about overlapping responsibilities. Which document should clarify this?

15
New cards

100% Rule

Rule that ensures the WBS covers all project work?

16
New cards

Work Package

Lowest level of detail in a WBS

17
New cards

Accomplishment of WBS

Decomposes deliverables into manageable components

18
New cards

Gantt Chart (Purpose)

Tool for sequencing activities and identifying dependencies

19
New cards

Scope Statement

Defines the boundaries of what is included and excluded in the project

20
New cards

Integration Management (Definition)

Ensures that all project elements are coordinated effectively

21
New cards

Risk Management

Knowledge area that focuses on identifying, analyzing, and responding to uncertainties

22
New cards

Project Sponsor

Primary subject responsible for approving the project charter

23
New cards

Closing

The phase where final deliverable acceptance happens

24
New cards

Monitoring and Controlling

Process which ensures that the project objectives are being met

25
New cards

Planning

Process group that involves developing detailed schedules and budgets

26
New cards

Project Charter

The key output of the initiation phase

27
New cards

Gantt Chart (Represents)

Tasks over time using horizontal bars

28
New cards

Closing (Situational)

(Situational): The sponsor demands a report on whether objectives were achieved and lessons learned documented. Which process is being referred to?

29
New cards

Stakeholder Management

Knowledge area that governs stakeholder satisfaction

30
New cards

Cost Management

(Situational): The project’s cost baseline is exceeded while scope remains unchanged. Which area requires review?

31
New cards

Cost

(Situational) Rising material prices increase the project budget. Which constraint is affected?

32
New cards

Quality

(Situational) If the sponsor shortens the timeline but doesn’t add resources, it threatens what?

33
New cards

Cost Performance Index

(Situational) Completing tasks early but overspending requires checking the what?

34
New cards

Communication Management Plan

Document that ensures effective communication across all groups?

35
New cards

Cost Overrun

Indicates unapproved additions to the project work

36
New cards

Procurement Management

(Situational) Late delivery of outsourced materials should be handled under what?

37
New cards

Monitoring and Controlling (Situational)

(Situational) Conducting an ISO quality audit belongs to what?

38
New cards

Monitored periodically

(Situational) A high probability but low impact risk should be what?

39
New cards

Updating the Risk Register

(Situational) Identifying new risks during execution requires what?

40
New cards

Inefficiency through micromanagement

(Situational) An overly detailed WBS may cause what?

41
New cards

Gantt Chart

Chart that shows task dependencies clearly

42
New cards

Planning

Where using past lessons learned improves the process group

43
New cards

Project Documents and Lessons Learned

Outputs stored for future reference when the project ends

44
New cards

Critical Path

(Situational) A milestone delay caused by dependencies should lead the manager to inspect the what?

45
New cards

A formal change approval is obtained

(Situational) Both accepting a client’s change request, the manager must ensure that?

46
New cards

Ahead of schedule

(Situational) Completing 60% of tasks in 40% of the time indicates the project is what?

47
New cards

Progressive Elaboration

Refining project plans as new information becomes available

48
New cards

WBS Dictionary

Contains the detailed explanation of each WBS element

49
New cards

Behind schedule

(Situational) Earned value below planned value tells the manager the project is what?

50
New cards

Close the project and finalize documents

(Situational) Once objectives are achieved and deliverables accepted, the next step is what?

51
New cards

Change Management Plan

Document that outlines how changes will be requested, reviewed, and approved

52
New cards
  1. Identified risks

  2. Risk owners

  3. Risk reponses

Risk Register contains

53
New cards

Activity List

An output of the “Define Activities” process

54
New cards

Primary Purpose of Schedule Baseline

Serves as the approved version of the project schedule

55
New cards

Rough Order of Magnitude

An estimate that is the least accurate during early planning

56
New cards

Stakeholder Register

Document listing individuals, their interests, influence, and engagement

57
New cards

Request for Quotation

Procurement document used to solicit price quotes

58
New cards

Project Management Plan

A collection of subsidiary plans that guide the execution and control

59
New cards

Critical Path in Schedule

Represents the longest path determining project duration

60
New cards

RACI Chart

Responsibility matrix used to assign tasks to team members

61
New cards

Variance Analysis

(Situational) When a project team compares actual performance against the baseline, they are performing what?

62
New cards

Lessons Learned Register Purpose

Capture insights to improve current and future projects

63
New cards

PERT

A scheduling technique uses optimistic, pessimistic, and most likely durations?

64
New cards

Pareto Chart

A quality tool used to display categories of defects in descending order

65
New cards

Float / Stack Scheduling

Time a task can be delayed without affecting the schedule

66
New cards

Resource Leveling

(Situational) A project team is adjusting resources to resolve over-allocation. This technique is what?

67
New cards

Avoided / Transferred

(Situational) A risk with low probability but very high impact should be what?

68
New cards

Contract Change Log

A document used to record formal communication during contract execution

69
New cards

FTF / Synchronous Communication

Communication method that is best for urgent, sensitive decision

70
New cards

Quality Management Plan

Defines the standards, metrics, and quality control procedures

71
New cards

Parametric Estimating

Cost estimation method that uses historical data and statistical relationships

72
New cards

Fallback plan

A backup response if the primary plan fails during risk planning

73
New cards

Issue

A current problem requiring action

74
New cards

Facilitation

An interpersonal skill which helps reduce conflicts and build consesus

75
New cards

Business Case

Identifies “WHY” a project is being undertaken

76
New cards

Highest-value Features

(Situational) A project uses agile-style iterations. What is prioritized first?

77
New cards

Close Procurements

(Situational) A project has multiple contractors. Which process ensures all agreements are completed?

78
New cards

Validation Scope

Performs formal acceptance of completed deliverables

79
New cards

Example of Preventive Action

Implementing a process to avoid future defects

80
New cards

Change Request

(Situational) A project needs a new tool to meet quality requirements. This request should be added to the what?