Construction Project Management: Key Terms and Definitions

0.0(0)
studied byStudied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/49

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 11:44 PM on 2/3/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

50 Terms

1
New cards

Scope

The defined work required to complete a project; includes tasks, deliverables, and boundaries.

2
New cards

Schedule (or Timeline)

Planned start and finish dates for activities.

3
New cards

Critical Path

Sequence of tasks that determines the minimum project duration; delays here delay the whole project.

4
New cards

RFI (or Request for Information)

Formal question submitted by contractors about plans, specifications, or omissions.

5
New cards

Submittals

Documents/material samples sent to the design team for review before installation (mix designs, rebar shop drawings).

6
New cards

CO (or Change Order)

Approved document allowing modifications to scope, time, or cost.

7
New cards

Punch List

Final list of items to complete before project closeout.

8
New cards

Closeout

Final documentation, inspections, turnover, and completion certification.

9
New cards

Retainage

A percentage (typically 5%-10%) of the contract value that is withheld by the project owner until certain conditions are met, usually until the work is completed and accepted.

10
New cards

Risk Management

Identifying, assessing, and mitigating potential risks to the project. Risks might include cost overruns, delays, or safety incidents.

11
New cards

Stakeholder

Any individual, group, or organization that may affect or be affected by the project (e.g., clients, architects, regulatory agencies, etc.).

12
New cards

GC (or General Contractor)

Company responsible for overall construction execution.

13
New cards

SOV (or Schedule of Values)

A detailed, itemized breakdown of the total contract price for a construction project.

It's most commonly used in progress billing to track work completed and determine the amount to be paid to the contractor or subcontractors at various stages of the project.

14
New cards

Foreman

Crew leader supervising tradespeople.

15
New cards

Mobilization

Process of moving manpower, equipment, and materials to a jobsite to start work.

16
New cards

Demobilization

Removal of equipment/crew after work completion.

17
New cards

Slump

Measure of concrete's consistency/workability.

18
New cards

PSI (or Compressive Strength)

Concrete's load-bearing capacity (e.g., 3,000 PSI, 5,000 PSI).

19
New cards

Superintendent

Onsite leader who manages daily field operations.

20
New cards

Laydown Area

Space used for storing materials and equipment.

21
New cards

Concrete Mix Design

Detailed specification of cement, aggregates, admixtures, and water ratio to achieve required strength.

22
New cards

Air Entrainment

Tiny air bubbles added to improve durability, especially for freeze-thaw climates.

23
New cards

Admixture

Chemical additives modifying concrete behavior.

24
New cards

Rebar (or Reinforcing Bar)

Steel bars used to strengthen concrete.

25
New cards

Formwork

Temporary structure that shapes and supports wet concrete until it cures.

26
New cards

Curing

Maintaining moisture and temperature to ensure proper hardening.

27
New cards

Accelerator

A chemical admixture that speeds up the setting and curing time of concrete.

Typical Use(s): Reduce Setting Time, Increase Early Strength, Cold Weather Work

28
New cards

Retarder

A chemical admixture that slows down the setting time of concrete, allowing more time to work with it.

Typical Use(s): Hot Weather Concreting, Large Pours, Transportation of Concrete

29
New cards

Water-Reducing Agent

An admixture that reduces the amount of water needed in the concrete mix while maintaining workability.

Typical Use(s): High-Strength Concrete, Harsh Environments, Long-Distance Transportation, High-Performance Concrete

30
New cards

Lien

A legal claim against a property for unpaid work or materials, often filed by subcontractors or suppliers if they are not paid.

31
New cards

Baseline

The approved version of the project schedule, cost, and scope plan, which is used as a benchmark for performance measurement.

Any changes to this baseline require formal approval (via change order).

32
New cards

Estimate (or Takeoff)

Calculation of materials, labor, equipment, and cost.

33
New cards

Cost Code

Accounting category to track costs (labor, equipment, materials, concrete placement, etc.).

Example(s): 101, 102, 103

34
New cards

Budget

Approved cost baseline for a project.

35
New cards

PPE (or Personal Protective Equipment)

Hard hat, gloves, safety glasses, boots, hi-visibility vest, etc.

36
New cards

JHA/JSA (Job Hazard Analysis/Job Safety Analysis)

Document identifying job tasks and associated hazards.

37
New cards

SWPPP (or Stormwater Pollution Prevention Plan)

Environmental protection requirements for managing site runoff.

38
New cards

OSHA Compliance

Regulations governing workplace safety.

39
New cards

Screed

Tool used to level concrete surface after pouring.

40
New cards

Line Pump

Ground-level hose-based concrete pump.

41
New cards

Boom Pump

Truck-mounted concrete pump with extendable arm.

42
New cards

Bull Float

Long-handled float for surface smoothing.

43
New cards

Vibratory Compactor

Used to compact soil before foundations or slabs.

44
New cards

Laser Level

Tool used for precise leveling and elevation control.

45
New cards

Quality Control Logs

Records of tests, samples, and quality checks.

46
New cards

Shop Drawings

Detailed drawings from subcontractors/suppliers (e.g., rebar layout, formwork plans).

47
New cards

Plans/Blueprints

Scaled drawings showing layout, dimensions, and construction details.

48
New cards

Float (or Slack)

Amount of time a task can be delayed without affecting overall schedule.

49
New cards

Production Rate

Output per crew per day or hour (e.g., cubic yards poured/day).

50
New cards

Lead Time

Time required to procure materials (rebar, formwork systems, admixtures).

Explore top flashcards

WY 4 Unit 4
Updated 1063d ago
flashcards Flashcards (40)
Ordlista 1
Updated 498d ago
flashcards Flashcards (30)
Bio Cell Membrane
Updated 512d ago
flashcards Flashcards (22)
AP EURO unit 1
Updated 904d ago
flashcards Flashcards (34)
Vocab 6B
Updated 1148d ago
flashcards Flashcards (23)
german final vocab
Updated 1157d ago
flashcards Flashcards (78)
WY 4 Unit 4
Updated 1063d ago
flashcards Flashcards (40)
Ordlista 1
Updated 498d ago
flashcards Flashcards (30)
Bio Cell Membrane
Updated 512d ago
flashcards Flashcards (22)
AP EURO unit 1
Updated 904d ago
flashcards Flashcards (34)
Vocab 6B
Updated 1148d ago
flashcards Flashcards (23)
german final vocab
Updated 1157d ago
flashcards Flashcards (78)