1/49
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No analytics yet
Send a link to your students to track their progress
Scope
The defined work required to complete a project; includes tasks, deliverables, and boundaries.
Schedule (or Timeline)
Planned start and finish dates for activities.
Critical Path
Sequence of tasks that determines the minimum project duration; delays here delay the whole project.
RFI (or Request for Information)
Formal question submitted by contractors about plans, specifications, or omissions.
Submittals
Documents/material samples sent to the design team for review before installation (mix designs, rebar shop drawings).
CO (or Change Order)
Approved document allowing modifications to scope, time, or cost.
Punch List
Final list of items to complete before project closeout.
Closeout
Final documentation, inspections, turnover, and completion certification.
Retainage
A percentage (typically 5%-10%) of the contract value that is withheld by the project owner until certain conditions are met, usually until the work is completed and accepted.
Risk Management
Identifying, assessing, and mitigating potential risks to the project. Risks might include cost overruns, delays, or safety incidents.
Stakeholder
Any individual, group, or organization that may affect or be affected by the project (e.g., clients, architects, regulatory agencies, etc.).
GC (or General Contractor)
Company responsible for overall construction execution.
SOV (or Schedule of Values)
A detailed, itemized breakdown of the total contract price for a construction project.
It's most commonly used in progress billing to track work completed and determine the amount to be paid to the contractor or subcontractors at various stages of the project.
Foreman
Crew leader supervising tradespeople.
Mobilization
Process of moving manpower, equipment, and materials to a jobsite to start work.
Demobilization
Removal of equipment/crew after work completion.
Slump
Measure of concrete's consistency/workability.
PSI (or Compressive Strength)
Concrete's load-bearing capacity (e.g., 3,000 PSI, 5,000 PSI).
Superintendent
Onsite leader who manages daily field operations.
Laydown Area
Space used for storing materials and equipment.
Concrete Mix Design
Detailed specification of cement, aggregates, admixtures, and water ratio to achieve required strength.
Air Entrainment
Tiny air bubbles added to improve durability, especially for freeze-thaw climates.
Admixture
Chemical additives modifying concrete behavior.
Rebar (or Reinforcing Bar)
Steel bars used to strengthen concrete.
Formwork
Temporary structure that shapes and supports wet concrete until it cures.
Curing
Maintaining moisture and temperature to ensure proper hardening.
Accelerator
A chemical admixture that speeds up the setting and curing time of concrete.
Typical Use(s): Reduce Setting Time, Increase Early Strength, Cold Weather Work
Retarder
A chemical admixture that slows down the setting time of concrete, allowing more time to work with it.
Typical Use(s): Hot Weather Concreting, Large Pours, Transportation of Concrete
Water-Reducing Agent
An admixture that reduces the amount of water needed in the concrete mix while maintaining workability.
Typical Use(s): High-Strength Concrete, Harsh Environments, Long-Distance Transportation, High-Performance Concrete
Lien
A legal claim against a property for unpaid work or materials, often filed by subcontractors or suppliers if they are not paid.
Baseline
The approved version of the project schedule, cost, and scope plan, which is used as a benchmark for performance measurement.
Any changes to this baseline require formal approval (via change order).
Estimate (or Takeoff)
Calculation of materials, labor, equipment, and cost.
Cost Code
Accounting category to track costs (labor, equipment, materials, concrete placement, etc.).
Example(s): 101, 102, 103
Budget
Approved cost baseline for a project.
PPE (or Personal Protective Equipment)
Hard hat, gloves, safety glasses, boots, hi-visibility vest, etc.
JHA/JSA (Job Hazard Analysis/Job Safety Analysis)
Document identifying job tasks and associated hazards.
SWPPP (or Stormwater Pollution Prevention Plan)
Environmental protection requirements for managing site runoff.
OSHA Compliance
Regulations governing workplace safety.
Screed
Tool used to level concrete surface after pouring.
Line Pump
Ground-level hose-based concrete pump.
Boom Pump
Truck-mounted concrete pump with extendable arm.
Bull Float
Long-handled float for surface smoothing.
Vibratory Compactor
Used to compact soil before foundations or slabs.
Laser Level
Tool used for precise leveling and elevation control.
Quality Control Logs
Records of tests, samples, and quality checks.
Shop Drawings
Detailed drawings from subcontractors/suppliers (e.g., rebar layout, formwork plans).
Plans/Blueprints
Scaled drawings showing layout, dimensions, and construction details.
Float (or Slack)
Amount of time a task can be delayed without affecting overall schedule.
Production Rate
Output per crew per day or hour (e.g., cubic yards poured/day).
Lead Time
Time required to procure materials (rebar, formwork systems, admixtures).