Construction Bonds & Delay Claims

0.0(0)
studied byStudied by 0 people
0.0(0)
full-widthCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/19

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

20 Terms

1
New cards
Bond
A special form of contract in which one party (the surety) guarantees performance by another party (the principal) of certain obligations to the obligee
2
New cards
Obligee
The party to whom obligations are owed and is protected by the bond to have claim rights if the principal defaults
3
New cards
T/F Bonds are a form of insurance
False
4
New cards
Law of suretyship
A 3-party agreement where a surety promises a creditor to fulfill the debt/obligation of a principal debtor if they default by acting as a guarantee through surety bonds
5
New cards
Indemnity Agreement
The surety requires the principal and major shareholders to indemnify the surety against any loss
6
New cards
Bid bond

'- Principal = tenderer

- Obligee = tendering authority

- 10% of bid price

- Risk = contractor fails to enter into construction contract after bid acceptance by owner

- Surety pays the difference between tenderer's bid and next lowest bid up to bond amount

- 6 month actionable period

7
New cards
Performance bond

'- Principal = contractor

- Obligee = owner

- 50% of contract price

- Risk = default in contract performance

- 2 year actionable period from contract termination date

8
New cards
Labour and material payment bond

'- Principal = contractor/subcontractor (+ material suppliers)

- Obligee = owner/contractor

- 50% of contract price

- Risk = non-payment for 90 days

- 120 day claim filing period from last work/material supply

- 1 year actionable period on date of ceased work

9
New cards
Lien bond

'- Principal = contractor

- Obligee = registar of the court of contractor's lawyer

- Lien amount

- Risk = non-payment of lien judgement

- Actionable period set out in Limiation Act and Builders' Lien Act

10
New cards
Causes of delay (3)
Design process, material delivery, work performance
11
New cards
Entitlement to delay damages (delay claims)
Owner entitled to damages due to late completion; contractor entitled to demanages/extension due to factors beyond their control
12
New cards
Compensable delays
One party is contractually entitled to recover damages solely caused by the delaying party (no concurrent delays)
13
New cards
Concurrent delays
2+ events occurring at the same time, both of which would have been sufficient to have caused the delay; results in excusable time extension but no damages
14
New cards
Excusable delays
Not attributable to the fault of any party (unforeseeable event, not a result of negligence); entitles a party to time extension; may/may not be compensable
15
New cards
Critical path
Longest path through the contract completion date
16
New cards
Float
Available slack time in an activity or project schedule; Critical path activities have no float
17
New cards

Notice provisions for delays (3)

'- Contractor must give a notice of delay claim within 10 working days to be entitled to claim time extension

- Contractor must give timely notice of monetary claims

- The party making the claim shall submit a detailed account and grounds for claim to the consultant within a reasonable time

18
New cards
Delay damages
A claim for costs that arise from inefficiencies created by delays
19
New cards
Contractor costs (2)
Time-driven costs, escalation costs
20
New cards
Owner costs (3)
Extended project oversight costs, increased construction costs, lost profits