Lecture 7 - Management and Control

0.0(0)
studied byStudied by 0 people
0.0(0)
full-widthCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/40

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

41 Terms

1
New cards

monitoring and control

detect & correct budget, schedule and quality deviations

2
New cards

monitoring

set of procedures and management practices used to collect info about performance, based on set of performance metrics

3
New cards

performance analysis

process of determining performance variances based on monitored/forecasted performance

4
New cards

project control

adjust project to meet its goals by assessing performance, analyzing causes of problems, and desgining and implementing changes for problems

5
New cards

Performance Measurement Baseline (PMB)

approved, integrated scope-schedule-cost plan for project work, to measure and manage execution performance (excl. management reserves, incl. contingency reserves)

6
New cards

Project Budget Baseline (PBB)

total budget for project, including all reserves and not completely defined work

7
New cards

Contract Budget Base (CBB)

project is chartered by a contract

8
New cards

Budget at Completion (BAC)

total approved budget for entire project

9
New cards

Contingency budget/reserve

budget within PMB that covers known risks

10
New cards

management reserves

budget within PBB that covers unknown risks (approx. 3-5% of costs)

11
New cards

progress ratio (%)

ratio of actual performed quantity over total scheduled quantity

12
New cards

measuring project progress

don’t base it on costs, but on physical output

13
New cards

Earned Value Management (EVM)

integrating cost, schedule, and work peformed by attributing monetary values to each

14
New cards

Budgeted Cost of Work Scheduled (BCWS)

value of work scheduled to be accomplished in given time period (Planned Value (PV))

15
New cards

Actual Cost of work Performed (ACWP)

costs actually incurred in accomplishing work performed within control time (Actual Cost (AC))

16
New cards

Budgeted Cost of Work Performed (BCWP)

Monetary value of work actually performed within control time (Earned Value (EV))

17
New cards

Cost Variance (CV)

EV - AC = BCWP - ACWP

18
New cards

CV > 0

underrun (gain of value)

19
New cards

CV < 0

overrun (loss of value)

20
New cards

Cost Performance Index (CPI)

EV / AC = BCWP / ACWP

21
New cards

CPI > 1

Underrun

22
New cards

CPI < 1

overrun

23
New cards

Schedule Variance (SV)

EV- PV = BCWP - BCWS

24
New cards

SV > 0

ahead (gain of time)

25
New cards

SV<0

behind (loss of time)

26
New cards

Schedule Performance Index (SPI)

EV / PV = BCWP / BCWS

27
New cards

Limitations of SV / SPI

in the end SV = 0 and SPI = 1, which is incorrect (as it doesnt reflect excess)

28
New cards

Earned Schedule (ES)

point in time where EV was the value of PV in planning

29
New cards

SV(t)

ES - AT = Earned Schedule - Actual Time

30
New cards

SPI(t)

ES / AT = Earned Schedule / Actual Time

31
New cards

Earned Schedule (ES) - calculation

C = ( EV - PV( c ) ) / PV(c + 1) - PV(c ) : C = #completed time increments where EV exceeds PV

32
New cards

Cost Estimate At Completion (CEAC)

expected total cost of completing project

33
New cards

CEAC calculation

cost spent + (work remaining * expected unit cost)

34
New cards

expected unit cost

costs spent / work accomplished

35
New cards

Original Estimate Appraoch (OEA)

AC + (BAC - EV) = BAC - CV

36
New cards

Revised Estimate Appraoch (RAO)

AC + (BAC - EV) / CPI = BAC / CPI

37
New cards

Time Estimation At Completion (TEAC)

expected duration of completing project

38
New cards

TEAC (calculation)

AT + (PD - ES)

39
New cards

Critical Ratio (CR)

SPI * CPI

40
New cards

Project Control

monitoring to alert us when there’s a problem

41
New cards

Re-Baselining (RB)

set of actions to revise original baseline schedule/budget in case of cost and duration not manageable (crashing / fast-tracking)