1/40
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
monitoring and control
detect & correct budget, schedule and quality deviations
monitoring
set of procedures and management practices used to collect info about performance, based on set of performance metrics
performance analysis
process of determining performance variances based on monitored/forecasted performance
project control
adjust project to meet its goals by assessing performance, analyzing causes of problems, and desgining and implementing changes for problems
Performance Measurement Baseline (PMB)
approved, integrated scope-schedule-cost plan for project work, to measure and manage execution performance (excl. management reserves, incl. contingency reserves)
Project Budget Baseline (PBB)
total budget for project, including all reserves and not completely defined work
Contract Budget Base (CBB)
project is chartered by a contract
Budget at Completion (BAC)
total approved budget for entire project
Contingency budget/reserve
budget within PMB that covers known risks
management reserves
budget within PBB that covers unknown risks (approx. 3-5% of costs)
progress ratio (%)
ratio of actual performed quantity over total scheduled quantity
measuring project progress
don’t base it on costs, but on physical output
Earned Value Management (EVM)
integrating cost, schedule, and work peformed by attributing monetary values to each
Budgeted Cost of Work Scheduled (BCWS)
value of work scheduled to be accomplished in given time period (Planned Value (PV))
Actual Cost of work Performed (ACWP)
costs actually incurred in accomplishing work performed within control time (Actual Cost (AC))
Budgeted Cost of Work Performed (BCWP)
Monetary value of work actually performed within control time (Earned Value (EV))
Cost Variance (CV)
EV - AC = BCWP - ACWP
CV > 0
underrun (gain of value)
CV < 0
overrun (loss of value)
Cost Performance Index (CPI)
EV / AC = BCWP / ACWP
CPI > 1
Underrun
CPI < 1
overrun
Schedule Variance (SV)
EV- PV = BCWP - BCWS
SV > 0
ahead (gain of time)
SV<0
behind (loss of time)
Schedule Performance Index (SPI)
EV / PV = BCWP / BCWS
Limitations of SV / SPI
in the end SV = 0 and SPI = 1, which is incorrect (as it doesnt reflect excess)
Earned Schedule (ES)
point in time where EV was the value of PV in planning
SV(t)
ES - AT = Earned Schedule - Actual Time
SPI(t)
ES / AT = Earned Schedule / Actual Time
Earned Schedule (ES) - calculation
C = ( EV - PV( c ) ) / PV(c + 1) - PV(c ) : C = #completed time increments where EV exceeds PV
Cost Estimate At Completion (CEAC)
expected total cost of completing project
CEAC calculation
cost spent + (work remaining * expected unit cost)
expected unit cost
costs spent / work accomplished
Original Estimate Appraoch (OEA)
AC + (BAC - EV) = BAC - CV
Revised Estimate Appraoch (RAO)
AC + (BAC - EV) / CPI = BAC / CPI
Time Estimation At Completion (TEAC)
expected duration of completing project
TEAC (calculation)
AT + (PD - ES)
Critical Ratio (CR)
SPI * CPI
Project Control
monitoring to alert us when there’s a problem
Re-Baselining (RB)
set of actions to revise original baseline schedule/budget in case of cost and duration not manageable (crashing / fast-tracking)