critical path
the longest path (from start to finish) through the network
the shortest time in which the project can be completed
any delay in activities in the critical path delays the projext
critical paths have NO slack time
earliest start (ES)
earliest time at which an activity can start, assuming all predecessors have been completed
earliest finish (EF)
earliest time at which an activity can be finished
latest start (LS)
latest time at which an activity can start so no delays affect the completion time of the entire project
latest finish (LF)
latest time by which an activity has to be finished to not delay the completion time of the entire project
work breakdown structure
project
major tasks in the project
subtasks in the major tasks
activities (or “work packages”) to be completed
kanban
the japanese word for card
the cart is an authorization for the next container of material to be produced
a sequence of kansans pulls materials through the process
many different sorts of signals are used, but the system is still called a kanban
weighted moving average
used when trend is present (older data usually less important)
weights based on intuition equation: sum of (weight for period n)(demand in period n)/sum weights
exponential smoothing method
form of weighted moving average (weights decline exponentially with most recent data weighted most)
requires smoothing constant (ranges from 0 to 1)
involves little record keeping of past data