Looks like no one added any tags here yet for you.
Project:
a temporary endeavor undertaken to create a unique products, service, or result” (Deliverable)
3 Major/Distinct Aspects of a project:
Temporary, Unique, constraints
Examples of Projects
1. Developing a new product, service, or result.
2. Conducting research that yields documented results.
3. Changing the structure, staffing, or style of a company .
4. Developing an information system (hardware/software).
5. Constructing a building, industrial plant, or infrastructure.
6. Implementing, improving, or enhancing existing business processes and procedures
Program
A group of related projects, subprograms, and program activities managed in a coordinated way to obtain benefits not available from managing them
Work Package
Work defined at the lowest level of a work breakdown structure for which cost and duration can be estimated and managed.”
Work packages are divided up into smaller components called
activities that represent the work effort required to complete the work package
6 Competing Constraints:
Scope, Quality, Schedule, Budget, Resource, Risk
Activity
A distinct, scheduled portion of work performed during the course of a project.”
Milestone
A significant point or event in a project, program, or portfolio. (Instantaneous)
Project Management Process Groups:
A logical grouping of project management inputs, tools and techniques, and output
Project Management Process Groups are
not project phases
Initiating Process Group
The ins performed to define a new project or a new phase of an existing project by obtaining the authorization to begin
Planning Process Group
The planning process group consists of those processes performed to establish the total scope of effort, define and refine objectives, and develop the course of action
Executing Process Group:
The executing process group consists of those processes performed to complete the work defined in the project management plan to satisfy the project specifications.
Monitoring & Controlling Process Group
The monitoring and controlling process group consists of those processes needed to track, review, and coordinate the progress and the performance of a project or phase.
Closing Process Group
The closing process group consists of those processes performed to conclude the activities across all the PM process groups to formally complete a project or phase
Deming Cycle:
A continuous quality improvement model consisting of a logical sequence of four repetitive steps for continuous improvement and learning... (PDCA).
Predictive Life Cycle
Traditional approach, most of the planning occurs upfront, then executing in a single pass
Predictive Life Cycle Example:
Designing and manufacturing a new plane model
Iterative Life Cycle
Approach that allows feedback for any unfinished work to improve and modify that work
Iterative Life Cycle Example
Software updates
Incremental Life Cycle
Approach that provides finished deliverables that the customer may use immediately
Incremental Life Cycle Example
Fully functional website and then adding features
Agile Life Cycle
An approach that is both incremental and iterative to refine work items and deliver frequently. The increment to produce is approved before starting a given iteration. The iteration is used to address uncertainty on the requirements and the potential for plans to get rapidly out of date by only planning for the upcoming iteration in detail.
Agile life cycle example:
(Construction of an Apartment): Constructing a building
Scrum
An agile framework for developing and sustaining complex products, with specific roles, events, and artifacts
Project Manager’s Responsibilities stakeholders
Parent company, project and client, team members
Parent company
Proper conservation of resources, timely and accurate project communications, and the careful, competent management of the project.
project and client
Preserve the integrity of the project in spite of the conflicting demands made by the many parties who have legitimate interests in the project
team members
Provide support to the project workers when transitioning between old/new projects or going back to their functional homes (concerned with future)
The majority of a PM’s time is spent
communicating with the many groups interested in the project
The PM is the project’s
liaison to the outside world
Management Styles: Three Categories
Autocratic, democratic, Laissez-faire
Autocratic
Follows the top-down approach, with one-way communication. It is the most controlling, with management making all the workplace decisions and holding all the power
Democratic
Managers encourage employees to give input but are ultimately responsible for the final decision. Team cohesiveness is increased by using two-way communication
Laissez-Faire
Management takes a hands-off approach to leadership. Employees are trusted to do their work without supervision; control their decisions and problem-solving
4 values of ethics
Responsibility, respect, fairness, honesty
Organizational Structure
is an enterprise environmental factor, which can affect the availability of resources and influence how projects are conducted
The organizational system is comprised of
both human and nonhuman resources
Project coordinator
power to make some decisions, have some authority, reports to higher level manager
Project Expeditor
works as staff assistance and communications coordinator
Project Management Office (PMO)
An organizational structure that standardized project related governance processes and facilities the sharing of methodologies, resources, tools, and techniques
The main purpose of the PMO
is to assimilate good project management practices into the entire organization
Conflict in the project life cycle generally fall under one of three categories
goals, authority, and interpersonal
Categories of conflict with goals
include schedules and priorities
Categories of conflict with authority
include technical
Categories of conflict with interpersonal
include personality
Withdraw/avoid
retreating from an actual conflict or a potential conflict situation
smooth/accomodate
emphasizing areas of agreement rather than areas of difference
compromise/reconcile
searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict
force/direct
pushing one's viewpoint at the expense of others
collaborate/problem solve
incorporating multiple viewpoints and insights from differing perspectives
Conflict between PM and Project personnel
confrontation, compromise, smoothing
Conflict between PM and Superior
compromise
Conflict between PM and functional personnel
withdrawal
Sponsor
person or group who provides resources and support for project/program and is accountable for enable success
Creating WBS
is the process of subdividing the project deliverables and project work into smaller, more management components
RAM
a grid that shows the project resources that are assigned to each work package - used to illustrate connections between work packages or activities and project team members
RACI Matrix
a common type of responsibility matrix that uses responsible, accountable, consult, and inform statuses to define involvement of stakeholders in project activities
Project charter elements
business case, scope description, strategic plan, schedules, resources, personnel
The purpose of the launch meeting
bring everyone up to speed, not to discuss every item in detail. Every attendee (sponsor, team members, and stakeholders) needs to see the PM taking charge and leading
WBS
Hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives and create the required deliverables
Precedence Diagramming Method (PDM)
Technique used for constructing a schedule model in which the activities are represented by nodes and graphically linked by one or more logical relationships (i.e., sequence of performed activities)
PERT Formula
RE = (O + 4M + P) / 6
Scheduling Flexibility
Measured by the amount of time a schedule activity can be delayed or extended without negatively affecting other scheduling constraints (slack)
Lag example
You have two scheduled activities, including: (1) Install server into computer lab; and (2) Move server into the data center. The second task cannot start until the server has run in the computer lab for five days without failure
Schedule Compression Techniques
Used to shorten the schedule duration without reducing the project scope, in order to meet the schedule constraints or imposed dates
Crashing principles
1. Focus on critical path activities 2. Select the least expensive approach
Fast-tracking principles
1. Always start with this techniqie first 2. Fast-tracking only works if the activities can be overlapped in order to shorten the project duration
Gantt Chart
A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and the activity durations are shown as horizontal bars placed according to start and finish dates
Gantt charts are mostly used to
follow project schedules. Data about the various tasks or phases of a project are shown; one can observe how they relate to one another and their progress
resource
skilled human resources (specific disciplines either individually or teams), services, equipment, supplies, commodities, material, budgets, or funds
Time is
a constraint
When scheduling, PMs consider resources in terms of:
1. Those that are needed in a specific amount for an activity 2. Those that are needed to accompany the labor for as long as the labor is used
Time Limited
The project must be finished by a certain time, using as few resources as possible. It is time, not resource usage that is most critical.
Resource Limited
The project must be finished as soon as possible, but not exceeding some specific level of resource usage or some general resource constraint
System constrained
task requires a fixed amount of time and known quantities of resources
Resource Loading
Defines the amounts of the individual resources a schedule requires during specific time periods. It gives a general understanding of the resource demands
Resource Calendar
Identifies the working days and shifts on which each specific resource is available. Specifies when and how long the identified project resources will be available
Monitor:
Collect project performance data with respect to a plan, produce performance measures, and report as well as disseminate performance information
Control
Comparing actual performance with planned performance, analyzing variances, assessing trends for process improvements, evaluating possible alternatives, and recommending proper corrective action as needed
Constraints to monitoring and controlling
cost (budget), time (schedule), and performance (scope)
Routine
Reports issued on a regular basis (not necessarily on calendar basis)
Exception:
Reports distributed to the team members who are responsible for PM decision-making and distributed to inform other managers of the decision (have a clear ‘need to know’)
Special Analysis
Reports used to disseminate the results of special problems that arise during a project. Generally cover matters that are of interest to other PM (analytic methods)
Earned Value Management (EVM)
is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress (common)
Actual Cost (AC)
is the total cost incurred for the work to be accomplished for an activity or for a WBS component. It is the actual amount spent to date to complete work.
Cost Variance (CV)
is expressed as the amount of budget deficit or surplus at a given point in time. It is a measure of cost performance on a project
Schedule Performance Index (SPI)
measures the schedule efficiency (how efficiently the project team is using time), it compares the actual progress to the planned progress
The primary purpose of evaluation is
deciding whether the project is “successful.”
The secondary purpose of evaluation is
translating the achievement of a project’s goals into contributing to the parent organization’s goals
General Audit:
Normally most constrained by resources and time and is usually a brief review of a project
Detailed Audit
A typical detailed audit is conducted when a follow-up to the general audit is required. This occurs due to unacceptable level of risk or performance in project area/s.
Technical Audit:
Typically performed by a qualified technician under the direct guidance of a project auditor. Although not always the case, the technical audit is often the most detailed
Post-Project Audit
Often a legal necessity because the client specified in the contracta. It is a major part of the post-project report, which is a main source of managerial feedback. It is needed to account for all project property and expenditures
The first audits are usually done
early in a project’s life. Early audits are often focused on the technical issues in order to make sure that key problems have been solved.
Audits done later in the life cycle of a project are
of less immediate value to the project. As the project develops, conformity to schedule and budget are the key concerns.
Management issues are major matters of interest of the audits made
late in the project’s life (e.g., disposal of the equipment or the reallocation of the project personnel)
Project Audit Report sections
introduction, current status, future status, critical management issues, risk management, limitation and assumptions
Termination by Addition
projects are “in-house,” that is, carried out by the project team for use in the parent firm. If the project is a major success, it may be terminated by institutionalizing it as a formal part of the parent firm