CPM and PERT are two ___________ use for planning and scheduling
Project Management technique
What is the Critical Path Method? { CPM }
It is deterministic
Uses for project which is predictable
Focuses on finding the critical path
It tells which task must complete so that project will not delay
Besf for construction , manufacturing
What is PERT (project evaluation and reviewing technique)?
Used for project with is not predictable or uncertain
It uses three time estimations
Optimistic
Pessimistic
Most likely
Uses in risk analysis
Best for research
Its probablistic
What is critical path?
The longest path of dependent tasks