capacity of a resource
1/activity time
bottleneck
stage with the smallest capacity or the longest processing time
process capacity
bottleneck resource capacity
process designed cycle time
1/process capacity
stage designed cycle time
1/stage capacity
designed cycle time
1/process capacity
capacity of n parallel resources
capacity of res 1 + capacity of res 2 + … + capacity of res n
resource utilization
process capacity/resource capacity
idle time of a worker
cycle time - activity of that worker
direct labor cost
total wages / process capacity
flow rate (throughput)
min {Process capacity, Demand rate}
actual cycle time
1 / flow rate
stage utilization
flow rate / stage capacity
process utilization
flow rate / process capacity