Concrete Technology

0.0(0)
studied byStudied by 1 person
0.0(0)
call with kaiCall with Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/142

flashcard set

Earn XP

Description and Tags

EA's Self-Paced Course by Martin Larisch

Last updated 10:37 PM on 2/1/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

143 Terms

1
New cards

What are the 2 main targets of a structural designer of reinforced concrete?

  1. Determining the amount and location of the steel

  2. Sufficient Cover to protect steel from environment, chemical attacks (corrosion) and fire

2
New cards

What do all these Concrete Mix acronyms mean?

  1. ATIC

  2. QRS

  3. MWR

  4. HWR

  5. AEA

  6. Re

  7. PU

  8. SS

  9. RA

  10. HP

  11. SL

  1. ATIC - Australian Technical Infrastructure Committee

  2. QRS - Quarry Registration System

  3. MWR - Mid (range) Water Reducing

  4. HWR - High (range) Water Reducing

  5. AEA - Air Entraining Agents

  6. Re - Retarder

  7. PU - Polyurethane

  8. SS - Stabilised Sand or Steel slag

  9. RA - Recycled Aggregate

  10. HP - High Performance

  11. SL - Slump

3
New cards

Properties of Self Compacting (Super Workable) Concrete? Background?

  1. Low Viscosity

  2. Greater Flow Rate

  3. Good for flow through dense reo & fills voids under its own weight.

  4. No external compaction.

  5. Reduce costs of labour & construction time for placement & vibration

  6. Less repairs due to poor placement & compaction

  7. Reduced aggregate size

  8. More fines

  9. More high-range water reducers (superplasticiser)

  10. Potential slower strength gain if large volumes of fly ash.

Made by Japan in the 80s to combact lack of skilled concreters. Implementing polycarboxylate-based high-range water-reducing admixture in the 90s, supported its rapid development.

4
New cards

What constitutes as a fine? What are the limits?

All materials passing 150-micron sieve (cements & other cementious materials). 500-600 kg/m3. Fine content impacts plastic shrinkage.

5
New cards

HRWR & PCE

High-Range Water Reducers (Superplasticisers). Polycarboxylates.

6
New cards

Dos and don'ts for self-compacting concrete

Do

Don't

  • Ensure high fluid mix to highly flowable concrete mix, if SCC is specified and required.

  • Carry out laboratory trials to assess the performance criteria of self-compacting concrete.

  • Allow for additional formwork pressure if normal class concrete is replaced with self-compacting concrete.

  • Ever use the slump test to assess the flow of self-compacting concrete

  • Ever apply external vibration to self-compacting concrete (the concrete is self-compacting, additional energy input will cause segregation)

  • Ever over-dose chemical admixtures as it might cause unwanted side-effects or defects to the concrete member.

7
New cards

When is a Tremie used?

Tremie concrete is used when fresh concrete must be placed under water or fluid.

For foundation elements like bored piles or retaining walls like diaphragm, secant piled, or contiguous piled walls must often be carried out using the tremie method if groundwater levels are high or drilling support fluids like bentonite or polymer-based fluids are used to temporarily stabilise the pile excavation.

8
New cards

Key 'dos and don'ts' for tremie concrete

Do

Don't

  • ensure the water level inside a pile is sufficient for a dry pour (<100mm of water inside the pile at the pile base prior to concrete placement)

  • always allow for at least 500 mm of over-break when placing concrete under fluid as this over-break is usually ‘contaminated’ with drilling fluid and must be trimmed off

  • ensure pre-construction concrete testing is carried out including filtration testing, slump, and slump flow testing.

  • ever place concrete through water unless the tremie technique is used

  • use concrete pumps as a replacement for tremie pipes (especially rubber hoses shall not be used for concrete placement under water or fluids)

  • use free-fall concrete unless the excavation is 'dry' and the allowable free-fall height is approved prior to concrete placement on site.

9
New cards

Key 'dos and don'ts' for marine concrete

Do

Don't

  • Ensure the exposure classification of the concrete is correct.

  • Consider SCM as a replacement of Portland cement to reduce the heat of hydration and increase strength and density of the concrete.

  • Use HRWR to enhance concrete strength and/or increase workability.

  • Use water-cement ratios larger than 0.4 for marine applications.

  • Add water to the concrete onsite above the permitted w/c ratio. Especially for marine applications, strength and density of the concrete are crucial.

  • Use concrete with strengths less than 50 MPa unless approved in writing.

10
New cards

Key 'dos and don'ts' for shotcrete

Do

Don't

  • Ensure the concrete mix has the correct workability for the application.

  • Ensure sufficient cement and fines are included in the shotcrete.

  • Always prepare test panels to ensure the mix suits the applications.

  • Ever use personnel with insufficient qualifications and training.

  • ever carry out shotcreting works without appropriate PPE.

  • Increase the thickness of the shotcrete layer beyond design tolerances, as this will cause additional weight and might damage the wall surface (cracking).

11
New cards

What is req content of cementious material for producign high quality self-compacing concrete?

400-600 kg/m3. Addition of fly ash & micro silica is advantageous to limit heat of hydration and control viscosity & segregation resistence

12
New cards

What test checks a mixes chloride resistence the quickest? What do they do?

Rapid Permeability Test (Nordtest Build 492). Tests chloride ion levels with depth. Tested on 28 day samples.

Dissolve chloride ions are forced through section of slice due to applied voltage in approx. 24 hours.

Dissolved chloride ions are forced through the section of the slice due to an applied voltage, in approximately 24 hours.

After the exposure of the specimen, it is split into two halves and the section is sprayed with a solution of silver nitrate. This leads to a precipitation of grey-white silver chloride in the part of the section that was penetrated by chlorides during the test. The penetration depth is easily measured as shown in the accompanying image showing the test set-up of the rapid permeability coefficient test.

13
New cards

Non-Destructive Testing method?

Schmidt/Rebound Hammer

  • Rebound Hammer Principle: Measures rebound of an elastic mass → rebound depends on surface hardness.

  • Surface Hardness: Higher rebound = harder surface; lower rebound = weaker concrete.

  • Concrete Strength Link: Low strength/stiffness concrete absorbs more energy → lower rebound value.

  • Test Method:

    • Press plunger against concrete surface.

    • Increase pressure until hammer impacts.

    • Read rebound value (Q-value) from scale.

  • Strength Estimation: Use manufacturer’s conversion tables to estimate compressive strength.

  • Other Non-Destructive Tests: Can locate reinforcement and assess corrosion potential.

  • Overall Purpose: Non-destructive tests provide insight into member behaviour and condition without damaging the structure.

<p>Schmidt/Rebound Hammer</p><ul><li><p><strong>Rebound Hammer Principle</strong>: Measures rebound of an elastic mass → rebound depends on surface hardness.</p></li><li><p><strong>Surface Hardness</strong>: Higher rebound = harder surface; lower rebound = weaker concrete.</p></li><li><p><strong>Concrete Strength Link</strong>: Low strength/stiffness concrete absorbs more energy → lower rebound value.</p></li><li><p><strong>Test Method</strong>:</p><ul><li><p>Press plunger against concrete surface.</p></li><li><p>Increase pressure until hammer impacts.</p></li><li><p>Read rebound value (Q-value) from scale.</p></li></ul></li><li><p><strong>Strength Estimation</strong>: Use manufacturer’s conversion tables to estimate compressive strength.</p></li><li><p><strong>Other Non-Destructive Tests</strong>: Can locate reinforcement and assess corrosion potential.</p></li><li><p><strong>Overall Purpose</strong>: Non-destructive tests provide insight into member behaviour and condition without damaging the structure.</p></li></ul><p></p>
14
New cards

What is the chloride test you conduct when more time is available?

Chloride Diffusion Test (Nordtest Build 443).

Measures the charge which passes across a hardened concrete specimen. Specimen needs to be soaked in saltwater for min. 35 days but can go for up to months.

The test is $$$

15
New cards

3 Do’s of Validation & Testing

  1. Carry out slump testing on a level surface

  2. Rod concrete inside slump cone prior to testing

  3. Apply sufficient moisture to surface when carrying out slump tests

16
New cards

3 Dont’s of Validation & Testing

  1. Accept a collapsed slump—carry out another test and if the slump still fails, reject the concrete.

  2. Lift the slump cone too fast or too slow—find the right balance.

  3. Ignore permissible tolerances on slump testing.

17
New cards

Difference between Chloride Diffusion test vs. the Rapid Permeability test

Diffusion is more realistic but more expensive and requires more time

18
New cards

Why is the Rapid Choride test more inaccurate?

Chloride particles are ‘drawn’ through hardened concrete by applying an electrical charge as shown.

<p>Chloride particles are ‘drawn’ through hardened concrete <span>by applying an electrical charge as shown.</span></p>
19
New cards

3 concrete strength tests as per AS 1012

  1. Compressive strength testing - Concrete Cylinder

  2. Indirect tensile strength testing - Concrete Cylinder

  3. Flexural strength testing - Concrete Beam

20
New cards

Explain the Indirect Tensile Strength Test

Tensile Strength is approximately 5-8% of max compressive strength of unreinforced concrete

AKA “Brazilian” or “Splitting test”

150×300mm concrete cylinder placed horizontally & apply compressive force to it.

AS 1012.10

21
New cards

Explain the Flexural Strength test

Determines tensile strength of concrete in flexure. Used on pavements.

AS 1012.9

Gives higher value for tensile strength than indirect test. When nominating tensile strength, the test type should clearly be outlined

22
New cards

How to perform shrinkage & creep tests

AS 1012.3. Prisms of concrete are set and creep is monitored using gauges at each end

23
New cards
24
New cards

List the 3 type of cracks that form in plastic concrete (pre-hardened)

  1. Plastic settlement cracks - Follows reo. Fixed by re-compaction whilst workable

  2. Plastic shrinkage cracks -

    1. Most concrete shrinks as much as 0.5 mm/m & plastic shrinkage shall be limited to 0.85 mm/m (as per AS1379).

    2. Caused by excessive evaporation (sun, wind).

    3. Random & unconnected cracking

    4. Usually 200-600mm. Can be up to 2m. Few mm deep

    5. How to control:

      1. Change water / m3

      2. Specify max w/c ratio & use stiffest mix design that can be pleced

      3. Use largest nominal max size aggregate that is practical. 10mm max agg usually requires ~15L more water per m3 to get the same slump as concrete with 20mm agg

      4. Use Water reducing, set controlling admixtures w/ good performance in shrinkage tests

      5. Clean, course sand & specify shrinkage limit cement (Type SL)

      6. Prevent evaportaion: Mist spray, wind screens, sun shades, plastic sheet cover

      7. Evaporation retardant sprayed on surface after screeding

  3. Cracks caused by movement of formwork

In general, if cracks that occur before hardening are detected early enough (prior to the stiffening of concrete), they can be easily rectified by either re-compacting, re-trowelling or re-floating the concrete surface

25
New cards

How do cracks form after hardening?

Drying shrinkage, movement or settling of teh ground, or applying higher loads than concrete was designed for.

26
New cards

How to remediate hardened concrete?

  • Epoxy Resin placement might be possible ($$$)

  • Cracking at control joints or controlled by steel reinforcement is acceptable

27
New cards

Can putting cold water on curing concrete on a hot day cause cracking?

Yes as cold water contracts the concrete and create tension cracks. Use warm water

28
New cards

What is Thermal cracking? What are the rules of thumb with concrete temperatures?

If dimensions exceed 1m in thickness anywhere. High temperatures and large gradients of temps inside the member causes cracks during the cooling phase

It may also facilitate Ettringite formation - A concern with durability of piles

Temperature of concrete should not exceed 70 ᵒC

  • 100kg of General Purpose (GP) cement is 14 ᵒC above ambient temperature during hydration

  • 400 kg/m3 of GP would result in 56 ᵒC above ambient temp, therefore, ambient temp can only be 14 ᵒC or less

  • 300 kg/m3 of GP & 100 kg/m3 of fly ash would result in 42 ᵒC above ambient fresh concrete temperature, ambient temp can be 28 ᵒC

Usually controlled by using blended cement using fly ash or granulated blast-furnace slag, by chilling mix water, or insulation concrete member sufficiently

29
New cards

List 3 types of concrete joints

Control: Installed in wet concrete using grooving tool or saw. To prevent shrinkage cracks. Depth of 25-33% of slab to be effective. If too late, cracks may have already formed. If too early, joint might not be clean. Often in squares. Spaced at distance of 20-30x the slab thickness in unreinforced concrete. In reinforced concrete, spacing can be increased and depends on amount of steel used.

Isolation/Expansion: Typically filled with rubber or other elastic materials & filling should cover depth & length of joint.

Construction/Cold Joint: Reo runs through joint to connect to future member. Existing concrete to be thoroughly cleaned & roughened before new member’s pour to support bond.

30
New cards

What is consistency?

the ability of the concrete to hold its shape when unsupported and to do so without segregating or falling apart. The most commonly used test for this is the slump test.

31
New cards

Slumps tolerances as per AS1012 & AS1379

Specified slump, mm

Tolerance, mm

<60

±10

≥60, ≤80

±15

>80, ≤110

±20

>110, ≤150

±30

>150

±40

32
New cards

If the first sample fails can you try again?

Yes. Concrete should be rejected if the 2nd fails.

33
New cards

How do you see teh cohesion of a mix from a slump test

Tap the board after the test is complete. Harsh mixes fall apart.

34
New cards

When can a sample be taken of concrete

After 0.2 m3 is poured

35
New cards

In a slump test, how many times does the sample need to be rodded? Will it get rejected if wood or rebar is used as tamping rod? or # of layers?

25 for both layers. Yes it will get rejected

36
New cards

What contributes to the air content in a mix

  • Sand

  • Cement

  • Air-Entraining Admixture

37
New cards

What is the percentage (%) of volume is air in air-entrained concrete

4-6%

38
New cards

Why make air-entrained concrete if it often makes the concrete weaker?

Workability and Freezing-Thawing condtitions.

Friction of concrete is reduced

39
New cards

3 Do’s & 3 Don’ts of placement

Do:

  • Sufficiently compact concrete in its plastic state (never let concrete dry out and stiffen because it will be too difficult to compact).

  • Keep the concrete moist at all times for efficient curing.

  • Clean and roughen the existing concrete at a construction joint (this will ensure sufficient bonding with the new concrete member).

Don’t:

  • Touch the formwork with an internal vibrator (poker).

  • Place concrete directly from the truck without a chute (the chute helps to avoid segregation).

  • Spread or move concrete sideways with the poker as it may cause segregation. Always use a shovel for sideways spreading.

40
New cards

What AS discusses testing for air entrained concrete? 3 ways to test for a concrete’s air content

AS 1012.4

  1. Pressure is applied to fresh concrete & reduction in the volume is measured. Don’t user this for porous aggregates

  2. Same as first* refer AS1012.4

  3. Volumetric method involving displacment of entrained air with water. Lightweight & Porous aggregates.

41
New cards

What should specified air content be within for the specified air content when tested?

1.5%

42
New cards

Equation for density?

Mass/Volume (kg/m3)

43
New cards

What is Ettringite

Ettringite is a mineral and a product of cement hydration, a hydrous calcium aluminum sulfate with the formula Ca₆Al₂(SO₄)₃(OH)₁₂·26H₂O.

It crystallizes in the trigonal system and forms during the normal setting and hardening of Portland cement. In some cases, delayed ettringite formation can lead to expansive stresses and cracking in concrete structures. Its unique crystal structure also allows it to function as an effective ion exchanger, capable of sequestering toxic heavy metals and radionuclides.

44
New cards

What is Yield?

The comparison of the theoretical weight of the mix constituents with the actual weight of the mix for a similar volume
or

Yield is the volume of fresh concrete produced in a batch, expressed in cubic meters. It is calculated by dividing the total mass of the material by the measured density of the freshly mixed concrete.

45
New cards

What is the ideal Yield in a mix?

2-5% tolerance

46
New cards

How to calculate yield

  1. Total mass of cement, aggregates, water, and admixture in a batch of 6.00 m3 is 14,265 kg

  2. Concrete density (unit weight) of 2330 kg/m3

  3. Theoretical volume of fresh concrete = 14,265 kg / 2330 kg/m3 = 6.12 m3

  4. Yield = 6.12 m3 / 6.00 m3 = 1.021 (2.1%).

47
New cards

Is under vibration or over vibration more common in normal class concrete?

Under vibration

48
New cards

Why does bleeding happen?

What AS explains testing of bleeding?

How is it tested?

  1. Bleeding occurs naturally but may occur if tto much water or cement paste is in the mix

  2. AS 1012.6

  3. Cylindrical test. Water from bleeding drained via pipette at intervals until amount collected during 30 mins is less than 5 mL.

49
New cards

Name the 3 imperfections that occur due to insufficient consolidation?

  1. Bug Holes - Surface air voids. Sometimes regarded as natural if small. Issue if there is a lot and they’re large as cover might be limited. Prevented by formwork release agents or mix design.

  2. Honeycombs - ‘Aggregat’ or ‘rock pockets’. Cement paste does not fill all spaces between aggregate. Repair or removal of the concrete section

  3. Placement/Lift Lines - Dark lines between adjacent batches of concrete. Prove that vibrator was not lowered far enough to benetrate below layer, or too much time passed between placement of successive layers and concrete had set.

<ol><li><p><strong>Bug Holes</strong> - Surface air voids. Sometimes regarded as natural if small. Issue if there is a lot and they’re large as cover might be limited. Prevented by formwork release agents or mix design.</p></li><li><p><strong>Honeycombs </strong>- ‘Aggregat’ or ‘rock pockets’. Cement paste does not fill all spaces between aggregate. Repair or removal of the concrete section</p></li><li><p><strong>Placement/Lift Lines</strong> - Dark lines between adjacent batches of concrete. Prove that vibrator was not lowered far enough to benetrate below layer, or too much time passed between placement of successive layers and concrete had set.</p></li></ol><p></p>
50
New cards
51
New cards

List the 10 surface defects and why they happen

Issue

Properties of fresh concrete

Placement

Compaction

Honeycomb

Insufficient fines, low workability, early stiffening, excessive mixing, too large an aggregate for placing conditions

Excessive free fall, too thick a layer (lift) of concrete in forms, drop chute omitted or of insufficient length, too small a tremie, segregation due to horizontal movement

Vibrator too small, too low a frequency, too small an amplitude, too short immersion time, excessive spacing between immersions, inadequate penetration

Air surface voids

Lean, sand with high fineness modules (FM), low workability with low FM sand, excessive cement content, particle degradation, excessive sand, high air content

Too slow, caused by inadequate pumping rate, undersized bucket

Too large an amplitude, external vibration inadequate, head of vibrator only partially immersed

Form streaking

Excess water or high slump

Improper timing between placing and timing

Excessive amplitude or frequency for form design

Aggregate transparency

Low sand content, gap­-graded aggregate dry or porous, excessive coarse aggregate, excessive slump with lightweight concrete

Excessive external vibration, over-vibration of lightweight concrete

Subsidence cracking

Low sand, high water content, too high slump, poorly proportioned mix

Too rapid

Insufficient vibration and lack of re-vibration

Colour variation

Non-uniform colour of materials, inconsistent grading, variation in proportions, incomplete mixing; calcium chloride can cause darker colour; too high a slump

Segregation (slump too high)

Vibrator too close to form, vibration next to forms variable, overworking the concrete

Sand streaking

Lean over-sanded mixtures and harsh wet mixtures deficient in fines

Too rapid for type of mix

Excessive vibration, excessive amplitude, overworking the concrete

Layer lines

Wet mixture with tendency to bleed

Slow placement, lack of equipment or manpower

Lack of vibration, failure to penetrate into previous layer

Form offsets

Excessive retardation of time of setting of concrete

Rate too high

Excessive amplitude, non-uniform spacing of immersion, horizontal movement of concrete

Cold joints

Too dry, early stiffening, slump loss

Delayed delivery, layers (lifts) too high

Failure to vibrate into lower layer (lift), insufficient vibration

52
New cards

Pump rates in m3/hr? Distances? Do you need to prime/lube it by pumping a ‘priming

mortar before starting?

50-200m3

50m veritcally to 500m horizontally

Yes

53
New cards

List the 5 types of concrete finishes

  1. Floating - done by hand or with a power float, but power floating leaves a better finish than hand-floating. Floating helps compact and level the surface and close minor cracks.

  2. Trowelling - another method of surface finishing and is how dense, hard, smooth and durable surfaces can be achieved. The surface should be trowelled twice and can be done either by hand or with a power trowel. All the edges of a concrete slab should be finished with a special edging tool to achieve a stronger edge, which is less prone to chipping.

  3. Joints - should be planned before placing and are usually formed into the concrete during finishing (you'll be covering joints in detail later in this module). The achievement of a skid-resistant surface can be done by drawing a broom across the surface of the concrete. The broom can be drawn in straight or 's' shape lines.

  4. Polished concrete - by using liquid polishes, latex coatings, chemical sealers or grinding, to expose the aggregates. Care should be taken to avoid surface cracks in polished concrete applications.

  5. Exposing the aggregate - another architectural finish. Typically, normal class concrete is used. After placement, the coarse aggregate will be exposed from the firm (not fully hardened) surface by forceful brushing or washing away the cement paste until the aggregates are exposed. 

<ol><li><p><strong>Floating </strong>- done by hand or with a power float, but power floating leaves a better finish than hand-floating. Floating helps compact and level the surface and close minor cracks.</p></li><li><p><strong>Trowelling </strong>- another method of surface finishing and is how dense, hard, smooth and durable surfaces can be achieved. The surface should be trowelled twice and can be done either by hand or with a power trowel. All the <strong>edges </strong>of a concrete slab should be finished with a special edging tool to achieve a stronger edge, which is less prone to chipping.</p></li><li><p><strong>Joints - </strong>should be planned before placing and are usually formed into the concrete during finishing (you'll be covering joints in detail later in this module).&nbsp;The achievement of a skid-resistant surface can be done by drawing a <strong>broom </strong>across the surface of the concrete. The broom can be drawn in straight or 's' shape lines.</p></li><li><p><strong>Polished concrete</strong> - by using liquid polishes, latex coatings, chemical sealers or grinding, to expose the aggregates. Care should be taken to avoid surface cracks in polished concrete applications.</p></li><li><p><strong>Exposing the aggregate</strong> - another architectural finish. Typically, normal class concrete is used. After placement, the coarse aggregate will be exposed from the firm (not fully hardened) surface by forceful brushing or washing away the cement paste until the aggregates are exposed.&nbsp;</p></li></ol><p></p>
54
New cards

What is curing? How to cure?

To prevent surface cracks, evaporation is reduced. Lack of curing can weaken the concrete by up to 50%. Curing happens after placment, compaction & finishing.

Maintain temp & moisture content for at least 3-7 days after placement. Allows ongoing hydraulic cement hydration & pozzolanic reactions to occur (if reqd).

Moisten surface & edges for moisture. Ensures hardened, abrasion resistant surface is developed & surface dusting is reduced

How to cure:

  1. Cover in plastic foil - Avoids wind & sunlight evaporation. Don’t leave a mark.

  2. Mist spray - twice daily for up to 7 days. Don’t over water.

  3. Membrane-forming curing compounds - Waxes, natural & synthetic resins & solvents. Applied by brush, spray or roller. Single application is normally enough. Do not walk on concrete until dry. Don’t put on surfaces that need additional layers of concrete, paint, tiles or carpet

  4. Wet mats - Cotton mats, rugs or other absorbent coverings. Keep damp with applications of water or cover with plastic.

  5. Plastic membrane - Don’t put on aesthetic concrete slabs as wrinkles can affect texture. No discolouration though

Don’t want concrete surface to dry before cement is hydrated

55
New cards

Hot weather’s affects?

🔥Hot Weather Concrete

  • Can cause problems with mixing, placing, curing → reduced long-term strength & serviceability.

  • Wind, sun, dry air worsen effects → rapid evaporation.

  • Risks:

    • Non-uniform surface & low strength (improper curing).

    • Increased plastic shrinkage cracking.

    • Premature stiffening if >21 °C → more water needed, lower later strength.

Procedures

  • Keep surroundings cool.

  • Cool concrete & ingredients (e.g. ice, liquid nitrogen, shaded aggregates).

  • Work rapidly → avoid delays.

  • Adjust mix proportions.

  • Delay pours → night shifts / cooler times.

  • Cool formwork, reinforcement, subgrade with water before placing.

  • Spray surfaces after placing; wet-cure tops of walls & columns.

  • Schedule ready-mix trucks efficiently → avoid slump loss.

  • Use light-coloured trucks to reduce heating.

  • Finishing & curing are critical → curing compounds, spraying, ponding.

  • Postpone pour if extreme hot weather predicted.

56
New cards

Cold weather’s affects?

🥶 Cold Weather Concrete

  • Keep concrete >4 °C to allow hydration.

  • Protection from early freezing is most critical.

  • At 10 °C, concrete usually gains enough early strength after 24–48 hrs.

  • Low temps = slow setting, delayed strength.

  • Insulating blankets only retain heat, don’t raise temperature without external source.

Procedures

  • Heat water & materials.

  • Heat placement area.

  • Use extra cement or high-early-strength cement.

  • Add accelerating admixtures (faster hydration, but reduces working time).

  • Don’t place on frozen subgrade → thaw & recompact if needed.

  • Protect massive pours (piers, dams, foundations) by insulating formwork & surfaces.

  • Preheat formwork in very cold conditions.

🧰 Insulation Options

  • Polystyrene / polyurethane sheets.

  • Sprayed urethane foam (continuous layer).

  • Mineral wool or cellulose fibre.

57
New cards

Do precast & prestressed members have accelerated curing procedures? What requirements need to be met as per AS3600?

Yes. Saturated Steam or dry heat, which requires concrete member to be sealed to prevent loss of mixing water.

AS3600 - min curing times are critical for compressive strength targets prior to formwork stripping

If table below is not adhered to, severe defects or even collapse of members may occur

Minimum strength and curing requirements in accordance with AS 3600:

Exposure classification 

Minimum fc (MPa)

Minimum initial curing requirement (see Clause 1.7.1.5.1)

Minimum average compressive strength at the time of stripping of forms or removal from moulds (MPa)

A1

A2

20

25

Cure continuously for at least three days

15

B1

B2

32

40

Cure continuously for at least seven days

20

25

C1

C2

50

50

32

58
New cards

Consolidation = Compaction

Yes

59
New cards

What is the amplitude of a vibration?

The deviation in mm from the point of rest

60
New cards

Is this true?: In general, high amplitude and low frequency of vibration are preferred for stiffer concrete mixes, and low amplitude and high frequency typically work better with more plastic mixtures.

Yes

61
New cards

List the 3 common vibrators

  • Internal vibrators are vibrating elements that can be inserted into the fresh concrete at selected locations and are generally applicable to construction sites.

  • External vibrators employ vibrating devices attached at strategic positions on the formwork. External (or formwork) vibration is mostly applicable to the manufacture of precast concrete items, and for vibration of tunnel-lining forms.

  • Surface vibrators employ portable horizontal platforms on which a vibrating element is mounted.

62
New cards

How to Internal Vibrate properly

  1. Immersed vertically full depth & at least 150mm into preceding layer

  2. Put in quickly and taken out slowly

  3. Spacing is 1.5 times the radius of the vibrator

63
New cards

Tell me about Roller Compacted concrete

  • 0 Slump

  • Dams & Pavements

  • Consolidation by smooth drum rollers weighing 1500 - 5000 kg/m3

64
New cards

VPM

Vibrations per Minute

65
New cards

Give a form of manual consolidation

Rodding - repetitive poking or tamping of a steel rod into the fresh concrete. The rod should be long enough to penetrate the full depth of the layer being placed, and thin enough to pass between the reinforcing steel and the formwork.

Heavy Flat Faced Tools - For dry concrete with very low slumps, the surfaces can be rammed with heavy flat-faced tools until a film of mortar or cement paste appears at the surface. This film indicates that the voids within have been sufficiently filled. Please note that over-ramming should be avoided.

66
New cards

What is a Tremie? When is it used?

Underwater

<p>Underwater</p>
67
New cards

What is dry-mix and wt-mix in Shotcrete?

Dry-Mix: cementious materials and aggregates are mixed w/o water. Then transported by compressed air into a nozzle with compressed water to spray

Wet-Mix: Everything is mixed but chemical admixtures as they are applied at the end.

68
New cards

Should concrete testing be done at the end of the pump? Not at the truck dispatch.

Yes. Can reduce the slumpb by up to half the desired amount.

69
New cards

The 90-minute limitation may be waived by mutual agreement between the customer and the supplier if, after that period, the….

…consistency of the concrete is such that it can be properly placed and compacted without the addition of any more water to the mixer

70
New cards

Temperature limits of concrete

Not less than 5C nor greater than 35C. If ambient temp is not 10-30C, measures may need to be adopted to comply with those requirements

71
New cards

Does stiffening occur in hot dry weather?

Yes

72
New cards

In hot dry weather can the limit be reduced on the time from the commencement of mixing to the initial set from 90 mins? Can this time be extended in the cold?

Yes

73
New cards

Name the 15 items to be listed on the concrete document

  1. Name of supplier and place of concrete plant

  2. Serial number of the record/certificate

  1. Date of supply

  1. Name of customer

  1. Project name and location

  2. Delivery vehicle identification, if applicable

  1. Quantity of concrete covered by the certificate

  1. Specified class and strength grade, or other mix identification

  1. Specified slump, if applicable

  1. Maximum nominal size of aggregate

  1. Time of commencement of mixing

  1. For concrete specified by water-cement ratio, the estimate of the quantity of water, if 13any, added after completion of batching and whether the addition occurred before, or after, the commencement of discharge

  1. For concrete specified by slump, the estimate of the quantity of water added after commencement of discharge

  1. Any other detail that may be agreed between the customer and the supplier.

74
New cards

What are the 3 “Do’s” of for concrete production

  • Wash and clean concrete mixers after use to ensure sufficient mixing will be maintained for future works.

  • Fill out delivery dockets in accordance with AS 1379 and your requirements.

  • Calibrate weighting and batching facilities regularly.

75
New cards

What are the 5 “Don’ts” of for concrete production

  • Add water beyond the allowable amount as per the relevant mix design to make the concrete more fluid—it generally lowers the strength of the hardened concrete.

  • Carry out batching by volume, but always by mass (exceptions might be acceptable for small size DYI or low-risk projects if approved by the engineer).

  • Accept concrete that was batched 90 minutes prior to arrival on site, unless sufficient slump retention is provided.

76
New cards

Can you place a layer of concrete more than 500mm thick?

No! The concrete must be compacted before continuing

77
New cards

List 4 tools used to pour in concrete to formwork

  1. Drop chutes

  2. Lay flat

  3. Tremie

  4. Placement pipes

78
New cards

Concrete trucks in Australia have typical transport capacities from __ m3 to more than __ m3. The most common truck sizes in Australia are __ m3 and __ m3 trucks

  1. 1

  2. 12

  3. 6

  4. 8

79
New cards

Discharge of concrete in a batch should be completed within ______ mins from commencement of mixing or _____________. To what code?

  • 90

  • before proper placement

  • AS1379

80
New cards
81
New cards

2 batch ingredients with different tolerances

  1. Aggregates & Cement

  2. Water

82
New cards

The quantity of each ingredient in a batch shall be measured and controlled within the tolerances given for each ingredient in _____?

AS1379-2007

83
New cards

Tolerance for Q<2 m3 of total cementious material?

-5 +30 kg

<p>-5 +30 kg</p>
84
New cards

The quantity of water added to a batch is achieved by _______________, and by maintaining the specified __________

  1. accomplishing the specified slump

  2. design water-cement ratio

85
New cards

Tolerance of w/c ratio?

+10%

86
New cards

Where the w/c ratio is specified, regular moisture content checks of aggregate in accordance with _________ shall be taken

AS 2758.1

87
New cards

The rated mixing capacity of a batch mixer must be not more than % of the gross internal volume of the mixing chamber. If a batch mixer is operated as an agitator, for this purpose only, the rated agitating capacity may be taken as up to __% of the gross internal volume of the mixing chamber.

  1. 65

  2. 80

88
New cards

What is an Agitator?

A concrete agitator looks like a truck with a large, revolving concrete drum at the back, which is the most distinctive feature.

Inside this drum are angled blades designed to mix and keep the concrete from setting during transport and before it's discharged.

The truck also has a hydraulically operated chute that swings out to pour the concrete where it's needed.

<p>A concrete agitator looks like a truck with a large, revolving concrete drum at the back, which is the most distinctive feature. </p><p>Inside this drum are angled blades designed to mix and keep the concrete from setting during transport and before it's discharged.</p><p>The truck also has a hydraulically operated chute that swings out to pour the concrete where it's needed.  </p>
89
New cards

The minimum number of revolutions of the mixing mechanism should be as determined from the mixer manufacturer’s recommendations unless determined in accordance with _____.

Mixing should be carried out by either central mixing, mobile mixing, or staged mixing in compliance with _____. Select the following headings to find out more about each.

AS 1379

90
New cards

What is the % of each element (typically) in concrete?

Water = 14-21%
Cement = 7-15%
Aggregate (Sand/Gravel) = 65-80%

Air = <2%

<p>Water = 14-21%<br>Cement = 7-15%<br>Aggregate (Sand/Gravel) = 65-80%</p><p>Air = &lt;2%</p>
91
New cards

3 types of mixing

  1. Central Mixing - Stationary

  2. Mobile Mixing - Truck-mounted drum mixer

  3. Staged Mixing - Partially mixed centrally, and rest added later in mobile mixer

92
New cards

What is the chemical process of concrete hardening called?

Hydration

93
New cards

Does concrete have low thermal conductivity?

Yes

94
New cards

What environment does concrete make for the embedded steel reinforcement?

Alkaline (opposite of acidic on pH scale)

95
New cards

Concrete is a mix of what?

Cement, water, and aggregates (stone or sand), and sometimes other cementitious materials and chemical admixture

96
New cards

What is most concrete today made out of? What is an SCM?

Portland cement and supplementary cementitious materials (SCMs), which react with water to form the cement paste. Sand, gravel, and stones make up the largest fraction of concrete, and the cement paste is the ‘glue’ that sticks them together.

97
New cards

What is concrete grade?

Design characteristic compressive strength after 28 days (f’c) MPa

<p>Design characteristic compressive strength after 28 days (f’c) MPa</p>
98
New cards

What standards ties to concrete?

AS1379 - Concrete Specification & Supply

AS1012.12.1 - Concrete Testing

99
New cards

What is MPa a measure of?

Metric unit of Pressure

100
New cards

What is the range of compressive strength for ‘Normal Class’ (Conventional) concrete?

20-50 MPa