what powers NC pumps
NB
NC pump auto start indications?
what else can bring in the indication ?
what will auto start the pump?
starts on 79 psig
Amber light indication
can only auto start a green flagged pump
amber light also from local start on breaker
purpose of NC v99
NC V99 is the supply to non priority loads and is closed when crosstieing EW
NC containment Isolation valves auto actuation
Close on CSAS (containment pressure of 8.5PSIG)
NC containment relief valves
one 6 in valve set at 135 PSIG for High pressure seal leakage
one set at 150 PSIG between both outlet valves due to trapped water during a CSAS. prevents overpressure during temp rise in containment. protects against water solid system
both vent to containment
Surge tank lvl control and makeup
NC has no BYPASS valve and is made up form DW
can be made up from the Cooling water holdup tank
NC RU 6 goes off, what are the likely leaked in systems? what does it detect and where is it?
RCP seals and CVCS letdown HX
detects gamma
located out in the North yard by NC pumps
Bonus relief valve on inlet to RCP
relieves at 110PSIG. in case the outlet to the RCP HX is isolated
What RU monitors will monitor NC when cross tied to EW. status of RU-6
RU-2 train A
RU-3 train B
RU-6 is isolated
what are the NC priority loads?
RCP seals
CEDM ACUS
Nuclear sample coolers
Normal chiller
what is the normal discharge pressure on the NC system
about 90 to 100 PSIG
what is the sequence for opening the containment inlet valves when restoring?
why?
open the outlet, the middle, then the inlet to prevent spiking pressure and creating a leak in containment
what is the sequence for opening containment isolation valves when containment temp is high
inlet, middle, and outlet to prevent water hammer
How much flow is sent to the normal chillers A, B, and C
2500 GPM per chiller (500gpm to E)
How much flow is sent to the CEDM ACU
400 GPM
How much flow is sent to the RCP’s
511 GPM
how much flow is sent to the Nuclear sample coolers
16-26 gpm each
How much flow is sent to the PC HX
2500 GPM
How much flow is sent to the Letdown HX
1500 gpm
How can we cross connect EW to NC? what loads can be cooled by EW? what limitations exist
When EW is cross tied by isolating non priority loads using NC V 99. then EW is aligned to the Priority loads
It can also be aligned to the PC HX (Non priority)
A train from the control room, B from the field
Cross tie will inop the train of EW