MGT 301 Exam 2

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/214

flashcard set

Earn XP

Description and Tags

chapters 3, 7, S7, 12, and 13

Last updated 6:18 AM on 3/25/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

215 Terms

1
New cards

Project

-series of related tasks directed toward a major output.
-unique, temporary, and have defined goals, deadlines, and resource constraints

-require cross‑functional teams and special coordination

2
New cards

project examples

new product launch, building a house, wedding planning, semester‑long assignment

3
New cards

Critical path

- The longest time path through the project network.
-Determines minimum project duration.
-Any delay on a critical activity delays the entire project

4
New cards

slack

amount of time an activity can be delayed without delaying the project

5
New cards

critical time activites have _____ slack

no

6
New cards

Work breakdown structure (WBS) def

Breaks the project into manageable components

7
New cards

Work breakdown structure (WBS) levels

Project → Major tasks → Subtasks → Activities (work packages).

8
New cards

Work breakdown structure (WBS) is used for

planning, scheduling, budgeting, and assigning responsibility.

9
New cards

Network diagram

-Graphical representation of project activities and precedence relationships.

-Activity‑on‑Node (AON) AND Activity‑on‑Arrow (AOA).

10
New cards

Activity‑on‑Node (AON)

-uses nodes as activites

-most popular

11
New cards

Activity‑on‑Arrow (AOA)

-uses arrows as activities and nodes as events

-consume no time

12
New cards

PERT/CPM are network techniques developed in

1950s for complex project scheduling

13
New cards

PERT

uses three time estimates and handles uncertainty

14
New cards

CPM

uses one time estimate and assumes known activity durations

15
New cards

BOTH PERT AND CPM identify:

critical path, slack, and project duration

16
New cards

gantt chart

 -Bar chart showing activities over time.
-Useful for simple projects.
-Shows planned vs. actual progress.
-Does not show interdependencies.

17
New cards

process

ongoing, repetitive, and part of daily operations

18
New cards

What increases the need for project management?

time based competition and short production life cycles

19
New cards

5 steps to identify the critical path

  1. Draw the network.
    2. Compute ES and EF using a forward pass.
    3. Compute LS and LF using a backward pass.
    4. Critical path = activities with zero slack.
    5. Determines project duration and bottlenecks.

20
New cards

crashing

-shortens project duration by adding resources to critical activities.
-Increases cost.
-Used when deadlines must be met.
-Only critical path activities should be crashed.

21
New cards

Crashing may create a new critical path.

true

22
New cards

unique projects are

new products or service introductions

23
New cards

poor scheduling may cause

delays and cost overruns

24
New cards

3 phases of project management

planning, scheduling, controlling

25
New cards

1st phase of project management

Planning: goal setting, defining the project, organizing the team

26
New cards

2nd phase of project management

Scheduling: linking people, money, and materials to activities

27
New cards

3rd phase of project management

Controlling: monitoring resources, costs, quality, budgets, and revising plans

28
New cards

Project manager responsibilities

Ensure activities finish in sequence and on time
Keep project within budget
Meet quality goals
Provide motivation, direction, and information

29
New cards

what are some ethical issues that arise to project managers?

gifts from contractors, pressure to alter reports, false time sheets, and quality compromises

30
New cards

what set of standards help project managers with ethics?

PMI

31
New cards

Gross requirements for people, supplies, and equipment are estimated during ….

planning

32
New cards

PERT/CPM are computerized.

true

33
New cards

what does project scheduling do?

Shows relationships among activities
Identifies precedence
Encourages realistic time and cost estimates
Identifies bottlenecks
Improves resource use

34
New cards

project control

 Monitors resources, costs, quality, and budgets.
Uses feedback loops to revise plans.
Software tools generate cost, labor, variance, and status reports.

35
New cards

Well‑defined projects

clear inputs, processes, outputs (example: buildings, roads).
Use waterfall approach

36
New cards

ill defined projects

 many unknowns (example: software, new tech).
Use agile approach with iterative work and frequent feedback

37
New cards

most projects fall

in between waterfall and agile

38
New cards

6 steps of PERT/CPM

 Define the project and WBS
Determine activity relationships
Draw the network
Assign time/cost estimates
Compute the critical path
Use the network to plan, schedule, monitor, control

39
New cards

critical path

Longest time path through the network.
Delays on critical activities delay the project.
Noncritical activities provide flexibility.

40
New cards

PERT uses ____ time estimates .

3

41
New cards

CPM uses ____ time estimates .

1

42
New cards

What do PERT/CPM answer?

completion time, critical activities, probability of meeting deadlines, and resource sufficiency

43
New cards

Network diagrams

Show activities and precedence

44
New cards

critical path determines

true duration

45
New cards

Earliest finish (EF)

-Earliest time an activity can finish

-top right

46
New cards

Latest start (LS)

-Latest time an activity can begin without delaying the project.

-bottom left

47
New cards

Latest finish (LF)

-Latest time an activity can finish without delaying the project.

-bottom right

48
New cards

Two‑pass process

Forward pass computes ES and EF.
Backward pass computes LS and LF.

49
New cards

Earliest start (ES)

-Earliest time an activity can begin after all predecessors finish.

-top left

50
New cards

if one predecessor, ES=

EF of predecessor

51
New cards

if multiple predecessors, ES=

max(EF of all predecessors)

52
New cards

Earliest Finish Time Rule

EF = ES + activity time

53
New cards

If one successor → LF =

LS of successor

54
New cards

If multiple successors → LF

= min(LS of all successors)

55
New cards

Latest Start Time Rule

LS = LF − activity time

56
New cards

Slack

how long an activity can be delayed without delaying the project

57
New cards

Total slack

Noncritical activities on the same path share slack

58
New cards

CPM ignores variability because it assumes _____ activity times.

fixed

59
New cards

activity times will vary due to

delays, weather, personnel issues, etc

60
New cards

PERT addresses variability using three time estimates

 Optimistic time (a)
Most likely time (m)
Pessimistic time (b)

61
New cards

PERT assumptions

 Activity times follow a beta distribution & are statistically independent.
Project completion times follow a normal distribution.

62
New cards

Project variance

Sum of variances of activities on the critical path.

63
New cards

Project standard deviation

Square root of project variance.

64
New cards

Reducing variability improves

reliability

65
New cards

Project crashing ________ project duration at the lowest possible cost.

shortens

66
New cards

Each activity has:

 Normal time and normal cost
Crash time and crash cost
Some activities cannot be shortened

67
New cards

Crashing requirements

 Activity must be crashable.
Crashing must reduce project duration.
Crash cost must be minimized.

Crash cost per period

68
New cards

Four steps in crashing

 Step 1: Compute crash cost per period.
Step 2: Identify current critical path(s).
Step 3:
If one critical path → crash cheapest activity on that path.
If multiple critical paths → crash one activity from each path at minimum combined cost.
Step 4: Update times and repeat until due date is met.

69
New cards

PERT/CPM advantages

 Concept is straightforward.
Graphical networks show relationships.
Critical path and slack highlight priorities.
Clarifies responsibility for each activity.
Applicable to many project types.
Useful for monitoring schedules and costs.

70
New cards

PERT/CPM limitations

Activities must be clearly defined and independent.
Precedence relationships must be known.
Time estimates may be subjective or biased.
Near‑critical paths may be ignored even though risky.

71
New cards

Process focus / intermittent / job shop

 Low volume, high variety.
Organized around specific activities or departments.
High flexibility, frequent changes, varied routing.
High variable cost, low equipment utilization

72
New cards

examples of Process focus / intermittent / job shop

welding, painting, bakery, hospital departments.

73
New cards

Repetitive focus / batch / assembly

 Mid‑volume, mid‑variety.
Classic assembly line using modules.
More structure, less flexibility than process focus.

74
New cards

examples of Repetitive focus / batch / assembly

automobiles, appliances, fast‑food assembly.

75
New cards

Product focus / continuous / line

High volume, low variety.
Organized around products.
Long, continuous production runs.
High fixed cost, low variable cost, high utilization

76
New cards

examples of Product focus / continuous / line

glass, paper, potato chips, lightbulbs.

77
New cards

Mass customization

 High volume, high variety.
Rapid, low‑cost production of unique customer desires.
Combines flexibility of process focus with efficiency of product focus.

78
New cards

examples of mass customization

Dell build‑to‑order, Toyota custom cars, digital textile design.

79
New cards

Design capacity

Maximum theoretical output of a system.

80
New cards

Effective capacity

Capacity a firm expects to achieve given maintenance, breaks, scheduling, etc.

81
New cards

utilization calculation

Actual output ÷ design capacity.

82
New cards

efficiency calculation

Actual output ÷ effective capacity

83
New cards

Economies of scale

Unit cost decreases as output increases.

84
New cards

Diseconomies of scale

Unit cost increases as output increases due to complexity, congestion, or management limits.

85
New cards

Process time

Time to complete one unit at a workstation.

86
New cards

Throughput time

 Total time a unit spends in the system.

87
New cards

Bottleneck time

Time of the slowest workstation; limits system capacity

88
New cards

process focus(Volume–Variety)

low volume, high variety

89
New cards

repetitive focus(Volume–Variety)

mid‑volume, mid‑variety

90
New cards

product focus(Volume–Variety)

high volume, low variety

91
New cards

mass customization(Volume–Variety)

high volume, high variety

92
New cards

Objective of process strategy

Transform resources into goods/services while meeting customer requirements within cost and managerial constraints

93
New cards

Product‑focused and repetitive processes have ____ unit costs at ____ volume and ____ utilization.

low, high, high

94
New cards

Process focus is best for ____‑volume differentiated products.

low

95
New cards

Mass customization requires strong design, scheduling, supply chain, and inventory capabilities

true

96
New cards

Crossover charts

 Compare total costs of different processes.
Show volume ranges where each process is cheapest.

97
New cards

Focused processes

 Specialization increases efficiency and reduces complexity.
Focus builds core competence and supports competitive advantage.

98
New cards

Equipment decisions consider

cost, cash flow, market stability, tolerances, maintenance, and flexibility

99
New cards

flexibility

response with little penalty in time, cost, or customer value.
comes from modular, movable, or digitally controlled equipment.
expensive but brings competitive advantage

100
New cards

Flowcharts

 Show movement of materials, products, or people.
Help with understanding, analysis, and communication

Explore top notes

note
NOUNS
Updated 1100d ago
0.0(0)
note
AP Physics 1: Ultimate Guide
Updated 693d ago
0.0(0)
note
CELLULAR RESPIRATION
Updated 1728d ago
0.0(0)
note
Chemistry
Updated 279d ago
0.0(0)
note
Chapter 23- Alkenes
Updated 1278d ago
0.0(0)
note
Chapter 5: Foundations: History
Updated 1082d ago
0.0(0)
note
NOUNS
Updated 1100d ago
0.0(0)
note
AP Physics 1: Ultimate Guide
Updated 693d ago
0.0(0)
note
CELLULAR RESPIRATION
Updated 1728d ago
0.0(0)
note
Chemistry
Updated 279d ago
0.0(0)
note
Chapter 23- Alkenes
Updated 1278d ago
0.0(0)
note
Chapter 5: Foundations: History
Updated 1082d ago
0.0(0)

Explore top flashcards