1/214
chapters 3, 7, S7, 12, and 13
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No analytics yet
Send a link to your students to track their progress
Project
-series of related tasks directed toward a major output.
-unique, temporary, and have defined goals, deadlines, and resource constraints
-require cross‑functional teams and special coordination
project examples
new product launch, building a house, wedding planning, semester‑long assignment
Critical path
- The longest time path through the project network.
-Determines minimum project duration.
-Any delay on a critical activity delays the entire project
slack
amount of time an activity can be delayed without delaying the project
critical time activites have _____ slack
no
Work breakdown structure (WBS) def
Breaks the project into manageable components
Work breakdown structure (WBS) levels
Project → Major tasks → Subtasks → Activities (work packages).
Work breakdown structure (WBS) is used for
planning, scheduling, budgeting, and assigning responsibility.
Network diagram
-Graphical representation of project activities and precedence relationships.
-Activity‑on‑Node (AON) AND Activity‑on‑Arrow (AOA).
Activity‑on‑Node (AON)
-uses nodes as activites
-most popular
Activity‑on‑Arrow (AOA)
-uses arrows as activities and nodes as events
-consume no time
PERT/CPM are network techniques developed in
1950s for complex project scheduling
PERT
uses three time estimates and handles uncertainty
CPM
uses one time estimate and assumes known activity durations
BOTH PERT AND CPM identify:
critical path, slack, and project duration
gantt chart
-Bar chart showing activities over time.
-Useful for simple projects.
-Shows planned vs. actual progress.
-Does not show interdependencies.
process
ongoing, repetitive, and part of daily operations
What increases the need for project management?
time based competition and short production life cycles
5 steps to identify the critical path
Draw the network.
2. Compute ES and EF using a forward pass.
3. Compute LS and LF using a backward pass.
4. Critical path = activities with zero slack.
5. Determines project duration and bottlenecks.
crashing
-shortens project duration by adding resources to critical activities.
-Increases cost.
-Used when deadlines must be met.
-Only critical path activities should be crashed.
Crashing may create a new critical path.
true
unique projects are
new products or service introductions
poor scheduling may cause
delays and cost overruns
3 phases of project management
planning, scheduling, controlling
1st phase of project management
Planning: goal setting, defining the project, organizing the team
2nd phase of project management
Scheduling: linking people, money, and materials to activities
3rd phase of project management
Controlling: monitoring resources, costs, quality, budgets, and revising plans
Project manager responsibilities
Ensure activities finish in sequence and on time
Keep project within budget
Meet quality goals
Provide motivation, direction, and information
what are some ethical issues that arise to project managers?
gifts from contractors, pressure to alter reports, false time sheets, and quality compromises
what set of standards help project managers with ethics?
PMI
Gross requirements for people, supplies, and equipment are estimated during ….
planning
PERT/CPM are computerized.
true
what does project scheduling do?
Shows relationships among activities
Identifies precedence
Encourages realistic time and cost estimates
Identifies bottlenecks
Improves resource use
project control
Monitors resources, costs, quality, and budgets.
Uses feedback loops to revise plans.
Software tools generate cost, labor, variance, and status reports.
Well‑defined projects
clear inputs, processes, outputs (example: buildings, roads).
Use waterfall approach
ill defined projects
many unknowns (example: software, new tech).
Use agile approach with iterative work and frequent feedback
most projects fall
in between waterfall and agile
6 steps of PERT/CPM
Define the project and WBS
Determine activity relationships
Draw the network
Assign time/cost estimates
Compute the critical path
Use the network to plan, schedule, monitor, control
critical path
Longest time path through the network.
Delays on critical activities delay the project.
Noncritical activities provide flexibility.
PERT uses ____ time estimates .
3
CPM uses ____ time estimates .
1
What do PERT/CPM answer?
completion time, critical activities, probability of meeting deadlines, and resource sufficiency
Network diagrams
Show activities and precedence
critical path determines
true duration
Earliest finish (EF)
-Earliest time an activity can finish
-top right
Latest start (LS)
-Latest time an activity can begin without delaying the project.
-bottom left
Latest finish (LF)
-Latest time an activity can finish without delaying the project.
-bottom right
Two‑pass process
Forward pass computes ES and EF.
Backward pass computes LS and LF.
Earliest start (ES)
-Earliest time an activity can begin after all predecessors finish.
-top left
if one predecessor, ES=
EF of predecessor
if multiple predecessors, ES=
max(EF of all predecessors)
Earliest Finish Time Rule
EF = ES + activity time
If one successor → LF =
LS of successor
If multiple successors → LF
= min(LS of all successors)
Latest Start Time Rule
LS = LF − activity time
Slack
how long an activity can be delayed without delaying the project
Total slack
Noncritical activities on the same path share slack
CPM ignores variability because it assumes _____ activity times.
fixed
activity times will vary due to
delays, weather, personnel issues, etc
PERT addresses variability using three time estimates
Optimistic time (a)
Most likely time (m)
Pessimistic time (b)
PERT assumptions
Activity times follow a beta distribution & are statistically independent.
Project completion times follow a normal distribution.
Project variance
Sum of variances of activities on the critical path.
Project standard deviation
Square root of project variance.
Reducing variability improves
reliability
Project crashing ________ project duration at the lowest possible cost.
shortens
Each activity has:
Normal time and normal cost
Crash time and crash cost
Some activities cannot be shortened
Crashing requirements
Activity must be crashable.
Crashing must reduce project duration.
Crash cost must be minimized.
Crash cost per period
Four steps in crashing
Step 1: Compute crash cost per period.
Step 2: Identify current critical path(s).
Step 3:
If one critical path → crash cheapest activity on that path.
If multiple critical paths → crash one activity from each path at minimum combined cost.
Step 4: Update times and repeat until due date is met.
PERT/CPM advantages
Concept is straightforward.
Graphical networks show relationships.
Critical path and slack highlight priorities.
Clarifies responsibility for each activity.
Applicable to many project types.
Useful for monitoring schedules and costs.
PERT/CPM limitations
Activities must be clearly defined and independent.
Precedence relationships must be known.
Time estimates may be subjective or biased.
Near‑critical paths may be ignored even though risky.
Process focus / intermittent / job shop
Low volume, high variety.
Organized around specific activities or departments.
High flexibility, frequent changes, varied routing.
High variable cost, low equipment utilization
examples of Process focus / intermittent / job shop
welding, painting, bakery, hospital departments.
Repetitive focus / batch / assembly
Mid‑volume, mid‑variety.
Classic assembly line using modules.
More structure, less flexibility than process focus.
examples of Repetitive focus / batch / assembly
automobiles, appliances, fast‑food assembly.
Product focus / continuous / line
High volume, low variety.
Organized around products.
Long, continuous production runs.
High fixed cost, low variable cost, high utilization
examples of Product focus / continuous / line
glass, paper, potato chips, lightbulbs.
Mass customization
High volume, high variety.
Rapid, low‑cost production of unique customer desires.
Combines flexibility of process focus with efficiency of product focus.
examples of mass customization
Dell build‑to‑order, Toyota custom cars, digital textile design.
Design capacity
Maximum theoretical output of a system.
Effective capacity
Capacity a firm expects to achieve given maintenance, breaks, scheduling, etc.
utilization calculation
Actual output ÷ design capacity.
efficiency calculation
Actual output ÷ effective capacity
Economies of scale
Unit cost decreases as output increases.
Diseconomies of scale
Unit cost increases as output increases due to complexity, congestion, or management limits.
Process time
Time to complete one unit at a workstation.
Throughput time
Total time a unit spends in the system.
Bottleneck time
Time of the slowest workstation; limits system capacity
process focus(Volume–Variety)
low volume, high variety
repetitive focus(Volume–Variety)
mid‑volume, mid‑variety
product focus(Volume–Variety)
high volume, low variety
mass customization(Volume–Variety)
high volume, high variety
Objective of process strategy
Transform resources into goods/services while meeting customer requirements within cost and managerial constraints
Product‑focused and repetitive processes have ____ unit costs at ____ volume and ____ utilization.
low, high, high
Process focus is best for ____‑volume differentiated products.
low
Mass customization requires strong design, scheduling, supply chain, and inventory capabilities
true
Crossover charts
Compare total costs of different processes.
Show volume ranges where each process is cheapest.
Focused processes
Specialization increases efficiency and reduces complexity.
Focus builds core competence and supports competitive advantage.
Equipment decisions consider
cost, cash flow, market stability, tolerances, maintenance, and flexibility
flexibility
response with little penalty in time, cost, or customer value.
comes from modular, movable, or digitally controlled equipment.
expensive but brings competitive advantage
Flowcharts
Show movement of materials, products, or people.
Help with understanding, analysis, and communication