1/7
Unitywater's Project 24160465
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No study sessions yet.
How many Maintenance holes are being treated?
122 in total
62 Civil - Needing replacement or lifting of the lid. 50 Northern and 12 Southern assets.
60 Coating - Internal prep and resurfacing due to Hydrogen Sulphide (H2S) gas attacks on internal walls, reducer slabs and necks. 560m2 of coating in total. 30 Northern and 30 Southern assets.
UW say these works will be delivered under a Model 3. What is a Model 3? What are the 4 Models?
Lump Sump
TOC - Target Outrun Cost
SOR - Schedule of Rates
Lump Sum
Reimburseable
When does Construction Start and Finish
16th of Feb to 25th of August
What are the 5 parts to the pricing schedule?
Preliminary Services (Subcontractor)
General
Civil
Coating
Schedule of Rates
What is a polymer
A polymer is a large chemical compound formed by the polymerization of many smaller units called monomers. Polymers can be either natural, such as DNA and proteins, or synthetic, like plastics such as polystyrene. They consist of long, repeating chains of molecules, which give them unique properties that can be tailored for various applications. Common examples of polymers include rubber, nylon, and polyethylene, which are used in a wide range of products from clothing to packaging materials
What is a Dilapidation survey?
A detailed inspection and documented record of the current condition of a property before construction or demolition works. It gives photographic record of nearby buildings and their surroundings.
What are the 10 delivery principles for an Engineers?
Engage in Safety meetings and ensure Zero Harm plans are implemented and monitored
Understand contract scope, obligations and entitlements
Notify Manager of scope changes or delays
Follow Downer Delivery Management Methodology
Maintain progress, productivity and performance measurements and escalate abnormal trends or issues
Check the Supervisor’s daily reports for issues and follow up on actions
Maintain a diary of events, discussions and progress
Ensure quality requirements are understood and complied with
Use the Risk Register to identify actions and ensure risks are mitigated
Ensure subcontractors are informed of site requirements and are adequately supervised
What were the 7 documents received from UW for the initiation of the Project?
Draft Work Order
Prelim Services Order (PSO) & Work Request from Mike Basterfield to Paul Bowler
Overview map of the works (C-DR-002)
Detailed map of the works (C-DR-003)
BOQ Draft (D-BQ-001)
Concept Business Case (CBC) (D-CB-001)
Details on each Manhole (D-RG-001)