Flashcards based on lecture notes covering PRINCE2 project management principles and processes.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

14 Terms

1
New cards

What is the purpose of a project according to PRINCE2?

To deliver one or more business products according to an agreed Business Case.

2
New cards

What is the crucial initial document that drives a project, outlining its justification and viability?

A Business Case.

3
New cards

What elements are typically included in a Business Case?

Reasons for the project, options considered, costs, cost/benefit analysis, scenario analysis, and a summary of major risks.

4
New cards

What is the purpose of a Project Brief?

The foundation for the initiation of a project, created in the first process (Starting Up A Project).

5
New cards

What key aspects does the Project Brief outline?

Project Definition,Outline Business Case, Project Product Description, Project Approach, Project Management Team Structure, Role Descriptions and References

6
New cards

During the 'Starting Up a Project' process, what key outputs are produced?

Outline Business Case, Project Brief, and Initiation Stage Plan.

7
New cards

What are the seven principles of PRINCE2 project management?

Continued Business Justification, Learn from Experience, Defined Roles and Responsibilities, Manage by Stages, Manage by Exception, Focus on products, and Tailor method to suit the project environment.

8
New cards

Name the seven themes of PRINCE2?

Business Case, Organisation, Quality, Plans, Risk, Change and Progress.

9
New cards

What roles should be put in place at the Startup of a project?

Project Executive and Project Manager

10
New cards

What is the most important decision when planning a PRINCE2 project?

Do we want to commit to run this project?

11
New cards

In PRINCE2 Projects, what are the products used for?

Milestones

12
New cards

What is the focus of managing a project?

Product rather than Process

13
New cards

What is the purpose of Exception Plans?

PRINCE2 provides the method for dealing with exceptional circumstances.

14
New cards

What is the Project Manager's main tasks at the End Stage?

Check that the current stage work is complete, or almost complete, Plan the next stage or if the end make sure everything is completed. Update the Business Case and Risk Log to reflect the latest information.