1/52
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
Net present value analysis
Method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time.
Positive NPV
Means that the return from a project exceeds the cost of capital - the return available from investing the capital elsewhere.
Discount rate
The interest rate used to discount cash flows.
Takes into account not just the time value of money but also the risk or uncertainty of future cash flows.
The greater the uncertainty of future cash flows, the higher the discount rate.
It is also called the capitalization rate or opportunity cost of capital.
NPV calculations
Determine estimated costs and benefits for the life of the project and the products it produces.
Determine the discount rate
Calculate the net present value
Internal rate of return (IRR)
can be calculated by finding the discount rate that makes NPV equal to zero.
Return on Investment (ROI)
Calculated by subtracting the project's costs from the benefits and then dividing by the costs.
[Blank] = (Total discounted benefits - total discounted costs) / discounted costs
Payback period
Is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project.
Determines how much time will elapse before accrued benefits overtake accrued and continuing costs
Payback occurs when the net cumulative discounted benefits equals the costs
Many organizations have requirements for the length of the payback period of an investment.
Cost overrun
Is the additional percentage or dollar amount by which actual costs exceed estimates
Cost
Is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange.
Project cost management
Includes the process required to ensure that the project is completed within an approved budget.
Planning cost management
Estimating costs
Determining the budget
Controlling costs
Planning cost management
Determining the policies, procedures, and documentation that will be used for planning, executing, and controlling project cost.
Estimating costs
Developing an approximation or estimate of the costs of the resources needed to complete a project.
Determining the budget
Allocating the overall cost estimate to individual work items to establish a baseline for measure performance.
Controlling costs
Controlling changes to the project budget.
Basic principles of Cost Management
Most members of an executive board better understand and are more interested in financial terms than IT terms.
They need to present and discuss project information in both
Profits
Profit margin
Life cycle costing
Cash flow analysis
Profits
Revenue minus expenditures
Profit margin
Ratio of profits to revenues
Life cycle costing
Considers total cost of ownership, or development plus support costs, for a project.
Cash flow analysis
Determines estimated annual costs and benefits for a project and resulting annual cash flow.
Types of costs
Tangible
Intangible
Direct
Indirect
Sunk
Tangible costs
Costs or benefits that an organization can easily measure in dollars.
Intangible costs
costs or benefits that are difficult to measure in monetary terms
Direct costs
Are costs that can be directly related to producing the products and services of the project
Indirect costs
Are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.
Sunk cost
Is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs.
Learning curve theory
When many items are produced repetitively, the unit cost of those items decreases in a regular pattern as more units are produced.
Reserves
Are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict
Types of reserves
Contingency
Management
Contingency reserves
Allow for future situations that may be partially planned for (sometimes called known unknown) and are included in the project cost baseline
Management reserves
allow for future situations that are unpredictable (sometimes called unknown unknown)
Cost management plan includes
Level of accuracy
E.g. rounding guidelines, guidelines for the amount of contingency funds to include.
Units of measure
Each unit used in cost measurements e.g. labor hours or days should be defined
Organizational procedure links
Work breakdown structure (WBS) component used for project cost accounting as the control account (CA)
Control thresholds
A specified amount of variation allowed before action needs to be taken
Rules of performance measurement
Cost measurement rules, e.g., how often actual costs will be tracked and to what level of detail.
Reporting formats
Format and frequency of cost reports required for the project.
Process descriptions
Describe how to perform all of the cost management processes.
Cost estimation tools and techniques
Analogous or top-down estimates
Bottom-up estimates
Three-point estimates
Parametric estimating
Analogous or top-down estimates
Use the actual cost of a previous, similar project as the basis for estimating the cost of the current project.
Bottom-up estimates
Involve estimating individual work items or activities and summing them to get a project total
Three-point estimates
Involve estimating the most likely, optimistic and pessimistic costs for items
Parametric estimating
Uses project characteristics (parameters) in a mathematical model to estimate project costs
Function points
Are a means of measuring software size in terms that are meaningful to end users
User stories
Are a common way to describe requirements in a simple, concise way.
Budgeting
Involves allocating the project cost estimate to individual work items over time
Material resources or work items are based on the activities in the WBS for the project.
Cost baseline
Time-phased budget that project managers use to measure and monitor cost performance.
Earned value Management (EVM)
Project performance measurement technique that integrates scope, time, and cost data
Involves calculating three values for each activity or summary activity from a project’s WBS
Planned value (PV)
Actual cost (AC)
Earned value (EV)
Planned value (PV)
Authorized budget assigned to scheduled work
Actual Cost (AC)
Realized cost incurred for the work performed on an activity during a specific time period.
Earned Value (EV)
Measure of work performed expressed in terms of the budget authorized for that work
Cost variance (CV)
Is the earned value minus the actual cost
Schedule variance (SV)
Is the earned value minus the planned value
Cost performance index (CPI)
Is the ratio of earned value to actual cost
Schedule performance index (SPI)
Is the ratio of earned value to planned value
Estimate at completion (EAC)
is an estimated cost of completing a project based on performance to date
Budget at completion (BAC)
Is the original total budget for the project
To-complete performance index (TCPI)
is a measure of the cost performance that must be achieved with the remaining resources to meet a specific goal.
TCPI Equation to meet BAC
TCPI = (BAC - EV)/(BAC - AC)
TCPI Equation to meet EAC
TCPI = (BAC - EV)/(EAC - AC)