RI/FS
Remedial Investigation/Feasibility Study
What is the basic role of the scoping phase of the RI/FS process?
The initial planning phase of the project where they identify site boundaries and remedial action objectives
What does ARARs stand for?
Applicable or Relevant and Appropriate Requirements
What is the role of the baseline risk assessment during the site characterization phase of the RI/FS process?
It identifies the existing or potential risks that may be posed to human health and the environment by the site
What are the three factors used to initially screen remedial technology alternatives during the development of alternatives phase of the RI/FS process?
Effectiveness, implementability, and cost
Why are treatability investigations performed during the RI/FS process?
What are two of the nine criteria used during the detailed analysis of the remedial alternatives?