6b - Budget

0.0(0)
studied byStudied by 0 people
GameKnowt Play
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/31

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

32 Terms

1
New cards

4 processes of Project Cost Management?

  1. Plan Cost Management,

  2. Estimate Costs,

  3. Determine Budget,

  4. Control Costs.

2
New cards

Output of the Plan Cost Management process?

Cost Management Plan.

3
New cards

Units of Measure in Cost Management

Each unit used in measurements - (staff hours, lump sum)

4
New cards

level of accuracy

The acceptable range of deviation, e.g., ± 10% plus contingency.

5
New cards

Control thresholds

  • Variance thresholds for monitoring cost performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken.

  • Thresholds typically expressed as percentage deviations from the baseline plan.

6
New cards

Estimate Costs Process

  • Accuracy of a project estimate increases as the project progress

  • iterative process from phase to phase

  • Estimate of all resources

7
New cards

What types of costs should be included in cost estimates?

Both direct and indirect costs.

8
New cards

What are the 7 inputs to the Estimate Costs process?

  1. Cost Management Plan,

  2. HR Plan,

  3. Scope Baseline,

  4. Project Schedule,

  5. Risk Register,

  6. EEFs,

  7. OPAs.

9
New cards

What is the difference between 'analogous' and 'bottom-up' estimating techniques?

Analogous estimating is top-down and less accurate, whereas bottom-up estimating is detailed and rolled up.

10
New cards

Three-point estimating

A method that calculates cost estimates based on optimistic, pessimistic, and most likely estimates.

11
New cards

Cost of Quality (COQ)

Includes all costs incurred by investment in preventing nonconformance to requirements, appraising the product or service for conformance requirements and failing to meet requirements

12
New cards

Cost Basline

  • Major output of determining budget step

  • approved time phase budget which serves as the baseline

13
New cards

What are management reserves?

Funds outside the cost baseline but within the total project budget.

14
New cards

What is the main goal of the Control Costs process?

To monitor project costs and manage changes to the cost baseline.

15
New cards

Earned Value Management System' (EVMS)

  • Set of rules and standards to track cost, budget and a quantified view of what is accomplished

  • Helps explains why there are differences in the actual work performed vs planned and mitigation any consequence

16
New cards

What does BCWS stand for?

Budgeted Cost of Work Scheduled.

17
New cards

BCWP is

  • Budgeted Cost of Work Performed

  • What we said we do and when

  • Estimate

18
New cards

ACWP

  • Actual Cost of Work Performed

  • represents what has been paid for everyone for what has been accomplished so far

19
New cards

ETC and EAC

  • ETC = Estimate Time to Completion - estimate cost to perform the remaining work

  • EAC = Estimate at Completion = AWCP + ETC

20
New cards

Cost Variance (CV)

  • difference between expected cost of work and actual

  • BWCP - ACWP

21
New cards

Schedule Variance (SV)

The difference between the cost of work planned to the current point in time and the work that was accomplished expressed as BCWP - BCWS

22
New cards

Positive Cost Variance indicates

the project is under budget.

23
New cards

What does the Percent-Complete Method involve?

  • What percentage of the allotted work has been completed

  • Used to calculate the BCWP

24
New cards

4 Tools and Techniques to Estimate Costs

  1. Cost of Quality

  2. Project Management Estimating Software

  3. Vendor Bid Analysis

  4. Group Decision Making Techniques

25
New cards

Reserve Analysis

Assess Contingency and management reserves for potential project cost uncertainties.

26
New cards

Budget at Completion (BAC)

Equal to BCWS without time passing.

27
New cards

Project Funding Requirements

  • Output of Determining the Budget

  • Temporal

  • Incremental

28
New cards

Organizational Procedure links in the Cost Management Plan?

Each control account (WBS component) is assigned a code or account number linked directly to the performing organization’s accounting system.

29
New cards

BCWS - Budgeted Cost of Work Scheduled

A time-phased estimate of the cost of a project’s work.

30
New cards

BCWP - Budgeted Cost of Work Performed

  • earned value term

  • based on the value of the work that has been done based on the original estimate

  • value not the cost of the work we have done so far

31
New cards

Variance at Completion (VAC)

  • Calculated as BAC - EAC

  • documented with a trend report, starting the reason for the variance

32
New cards