EG

6b - Budget

Project Cost Management

• Concerned with estimating, budgeting, and controlling costs to finish a project within the approved budget.
• Also considers long-term operation, maintenance, and support costs of the final deliverable.
Earliest stages offer the greatest leverage for cost influence ⇒ importance of early scope definition.

Four Core Processes

  1. Plan Cost Management

  2. Estimate Costs

  3. Determine Budget

  4. Control Costs

1 Plan Cost Management

• Establish policies, procedures, and documentation for planning & controlling costs; output is the Cost Management Plan.

Typical CMP Components

Units of measure (e.g., staff-hours, lump sum).
Level of precision – rounding rules.
Level of accuracy – acceptable range, e.g., \pm 10\% plus contingency.
Organizational procedure links – WBS control account codes tied to accounting system.
Control thresholds – variance limits (usually percentage deviations).
Rules of performance measurement – Earned Value rules, weighted milestones, percent complete triggers.
Reporting formats – frequency & layout of cost reports.
Process descriptions – detail each of the three downstream cost processes.

2 Estimate Costs

Approximate monetary resources needed for each activity and aggregate work package.
• Iterative: accuracy improves as project information matures (e.g., early Rough Order of Magnitude \approx \pm 50\%, later \approx \pm 10\%).
• Consider direct and indirect costs; decide upfront if estimates will include both.

Inputs

• Cost Management Plan, HR Plan, Scope Baseline (Statement + WBS + Dictionary).
• Project schedule, risk register.
• EEFs: market conditions, published cost data.
• OPAs: policies, templates, historical info, lessons learned.

Techniques

Expert judgment
Analogous (top-down) – fast, low cost, less accurate.
Parametric – statistical models using historical data; potentially high accuracy.
Bottom-up – estimate work-package detail then roll-up.
Three-point estimating (PERT beta):
CE = \frac{Co + 4CM + C_p}{6}
Reserve analysis (contingency & management reserves).
Cost of Quality (COQ) – \text{Conformance} + \text{Non-conformance}.
• Project management estimating software.
Vendor bid analysis
• Group decision techniques.

Outputs

Activity cost estimates
Basis of estimates detailing assumptions, constraints, allowed range, confidence level.
• Project document updates.

3 Determine Budget

• Aggregate activity/work-package estimates to create the Cost Baseline (time-phased).
Management reserves are outside the baseline but within total project budget.

Funding Requirements

• Derived from cost baseline; expressed in incremental (e.g., annual) disbursements.

4 Control Costs

• Monitor project to update budget and manage changes to the cost baseline.
• Key activities:
– Influence cost-change factors.
– Ensure timely action on change requests.
– Prevent unauthorized cost/usage reporting.
– Keep expenditures within authorized funding by period & total.
– Analyze cost variances; integrate with overall change control.
• Essential to alert stakeholders and bring overruns within acceptable limits.

Earned Value Management System (EVMS)

Purpose

• Extends PM capability to track what was budgeted, what was accomplished, what it cost, and what it will take to finish; mandated on many major government contracts.

Core Questions EVMS Answers

• What did we say we’d do & when?
• How much did we think it would cost?
• What have we done so far?
• What did it really cost?
• What will it cost/when will we finish?
• Why are there differences & how do we mitigate?

Key Terms

BCWS – Budgeted Cost of Work Scheduled (planned value).
BCWP – Budgeted Cost of Work Performed (earned value); value of work accomplished based on original estimate.
ACWP – Actual Cost of Work Performed (actual cost).
ETC – Estimate to Complete (re-estimate for remaining work).
BAC – Budget at Completion (total planned budget).
EAC – Estimate at Completion: EAC = ACWP + ETC.

Variance & Performance Metrics

Cost Variance (CV): CV = BCWP - ACWP (positive = under budget).
Schedule Variance (SV): SV = BCWP - BCWS (positive = ahead of schedule).
Variance at Completion (VAC): VAC = BAC - EAC.

Earned Value Calculation Methods

Percent-Complete Method – Team estimates % complete; BCWP = % × budget for each activity. Example: “2⁄3 finished” ⇒ 66.7\% complete.

Practical & Ethical Implications

• Strong management commitment signals ethical responsibility for worker welfare.
• Transparent cost estimating and EVMS practices deter cost overruns/fraud and build stakeholder trust.
• Early identification of both safety hazards and cost risks prevents harm, saves money, and supports sustainable project success.