152- EVM Formula Tips

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/11

flashcard set

Earn XP

Description and Tags

Flashcards for project management formulas, including BAC, AC, PV, EV, CV, CPI, SV, SPI, EAC, ETC, VAC, and TCPI.

Last updated 2:04 AM on 6/4/25
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

12 Terms

1
New cards

BAC

Budget at Completion; the total budget of the project.

2
New cards

AC

Actual Cost; the amount of money spent on costs for a given period.

3
New cards

PV

Planned Value; the planned percent of work completed, multiplied by the BAC.

4
New cards

EV

Earned Value; the actual percent of work completed, multiplied by the BAC.

5
New cards

CV

Cost Variance; EV - AC; measures the cost performance of a project.

6
New cards

CPI

Cost Performance Index; EV / AC; measures the cost efficiency of a project.

7
New cards

SV

Schedule Variance; EV - PV; measures the schedule performance of a project.

8
New cards

SPI

Schedule Performance Index; EV / PV; measures the schedule efficiency of a project.

9
New cards

EAC

Estimate at Completion; BAC / CPI; a forecast of how much money will be spent at the end of the project.

10
New cards

ETC

Estimate to Complete; EAC - AC; how much more money is needed to finish the project.

11
New cards

VAC

Variance at Completion; BAC - EAC; how much money will be left over at the end of the project.

12
New cards

TCPI

To-Complete Performance Index; (BAC - EV) / (BAC - AC); a measure of the cost performance required to meet the budget.