152- EVM Formula Tips
Memorization Techniques for EVM Formulas
Basic Definitions
- BAC (Budget at Completion): Total budget of the project. No formula is associated with BAC.
- AC (Actual Cost): The actual amount of money spent on costs for a given period. AC also does not have a formula.
Planned Value (PV) and Earned Value (EV)
- Both PV and EV are multiplied against the BAC.
- PV (Planned Value): Represents the budgeted cost of work scheduled to be completed by a certain point in time.
- Formula:
- EV (Earned Value): Represents the value of the work actually completed.
- Formula:
Cost and Schedule Variances and Indices
- Key Observation: CV, CPI, SV, and SPI all start with EV.
- Variance vs. Index: Anytime there's a "V", it indicates a variance, implying subtraction. Anytime there's an "I", it indicates an index, implying division.
Cost Variance (CV) and Cost Performance Index (CPI)
- CV and CPI both deal with costs (Actual Cost - AC).
- CV (Cost Variance): The difference between the earned value and the actual costs.
- Formula:
- CPI (Cost Performance Index): A measure of the value of work completed compared to the actual cost.
- Formula:
Schedule Variance (SV) and Schedule Performance Index (SPI)
- SV and SPI both relate to the project schedule (Planned Value - PV).
- SV (Schedule Variance): The difference between the earned value and the planned value.
- Formula:
- SPI (Schedule Performance Index): A measure of the work completed compared to what was planned.
- Formula:
Forecasting
Estimate at Completion (EAC)
- EAC is a forecast of the total cost of the project upon completion.
- Formula:
- Take the total budget and divide it by the project's spending rate (CPI) to forecast the final cost.
Estimate to Complete (ETC)
- ETC represents how much more money is needed to finish the project.
- Formula:
- Subtract how much you've already spent (AC) from the latest estimate (EAC) to determine how much more funding is required.
Variance at Completion (VAC)
- VAC shows how much money will be left over (or how much more will be needed) at the end of the project.
- Formula:
- Subtract the new forecasted budget (EAC) from the original budget (BAC) to see the expected surplus or deficit.
To-Complete Performance Index (TCPI)
- TCPI indicates the required cost performance to meet the project's objectives.
- Formula:
- TCPI is similar to the CPI formula, but it factors in the total budget. It can be thought of as a "total CPI," where both EV and AC are subtracted from the budget (BAC).
Tips for Memorization
- Write down all 12 formulas multiple times to commit them to memory.
- Use the provided PDF with all the formulas for reference until they're memorized.