Precedence Diagram and Activity Duration Lecture Notes

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/14

flashcard set

Earn XP

Description and Tags

Flashcards covering vocabulary related to precedence diagrams, linking relationships, and productivity calculation in construction management.

Last updated 4:56 AM on 7/26/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

15 Terms

1
New cards

Precedence Diagram Nodes

Represent activities and may be drawn in any shape desired.

2
New cards

Activity Links

Lines used to represent the dependencies between activities in a precedence diagram.

3
New cards

Event / Milestone

A point in time without time duration, represented in precedence diagrams using activity notation with 00 duration.

4
New cards

Dummy Activities

Activities that are required in arrow diagrams (A.D.) but are not required in precedence diagrams (P.D.).

5
New cards

Finish-to-Start (FTS)

A linking relationship where the finish of the activity determines the start of the successor.

6
New cards

Start-to-Start (STS)

A linking relationship where the start of the activity determines the start of the successor.

7
New cards

Finish-to-Finish (FTF)

A linking relationship where the finish of the predecessor determines the finish of the successor.

8
New cards

Start-to-Finish (STF)

A linking relationship where the start of the predecessor determines the finish of the successor.

9
New cards

Lag time

The time that follows an activity or is delayed from the start or finish of its predecessor.

10
New cards

Lead time

The time that precedes the start or finish of an activity.

11
New cards

Duration

Determined by the production rate or the productivity rate of a crew or a sub that performs the task.

12
New cards

Labor Productivity Rate

The number of work hours for a specific crew to place or install one unit of a particular item of construction.

13
New cards

RS Means

A specific source of productivity rate information cited for construction management.

14
New cards

Productivity Factor

A factor used to compensate for the difference between a project under planning and a "standard project."

15
New cards

Adjusted Duration

Calculated as Duration (or workhours)×Productivity factor\text{Duration (or workhours)} \times \text{Productivity factor}.