Chapter 12: Project Management

studied byStudied by 0 people
0.0(0)
learn
LearnA personalized and smart learning plan
exam
Practice TestTake a test on your terms and definitions
spaced repetition
Spaced RepetitionScientifically backed study method
heart puzzle
Matching GameHow quick can you match all your cards?
flashcards
FlashcardsStudy terms and definitions

1 / 122

encourage image

There's no tags or description

Looks like no one added any tags here yet for you.

123 Terms

1

1) PERT and CPM are quantitative analysis tools designed to schedule and control large projects.

Answer: TRUE

Di#: 1

Topic: INTRODUCTION

New cards
2

2) PERT is a deterministic analysis tool allowing for precise times of activities within a project.

Answer: FALSE

Di#: 2

Topic: INTRODUCTION

New cards
3

3) PERT had its beginnings in a military department of the United States.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
4

4) CPM is a probabilistic analysis of managing a project.

Answer: FALSE

Di#: 2

Topic: INTRODUCTION

New cards
5

5) The first step in planning and scheduling a project is to develop the work breakdown structure.

Answer: TRUE

Di#: 2

Topic: INTRODUCTION

New cards
6

6) A PERT/CPM network is a graphical display of a project that connects activities.

Answer: TRUE

Di#: 1

Topic: PERT/CPM

New cards
7

7) The optimistic time is the greatest amount of time that could be required to complete an activity.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
8

8) PERT is a network technique similar to CPM, but PERT allows for project crashing, whereas CPM does not.

Answer: FALSE

Di#: 2

Topic: PERT/CPM and PROJECT CRASHING

New cards
9

9) In PERT, the most likely completion time of an activity is used to represent that activity's time within a

project.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
10

10) The expected completion time and variance of an activity is approximated by the normal distribution in a

PERT analysis.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
11

11) PERT was developed for a project for which activity or task times were uncertain.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
12

12) CPM was developed for use in managing projects about which we have good information about activity or

task completion times.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
13

13) With PERT, we are able to calculate the probability of finishing the project within a specified time.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
14

14) With CPM, we are able to calculate the probability of finishing the project within a specified time.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
15

15) Both PERT and CPM networks show activities and activity sequences.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
16

16) The identification of the project activities and their time, cost, resource requirements, predecessors, and

person(s) responsible is called PERT planning.

Answer: FALSE

Di#: 2

Topic: INTRODUCTION

New cards
17

17) Before drawing a PERT or CPM network, we must identify all activities and their predecessors.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
18

18) The three time estimates employed in PERT are optimistic time, average time, and pessimistic time.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
19

19) Given the variability of the activity completion times, the original critical path we identify in our PERT

analysis may not always be the actual critical path as the project takes place.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
20

20) In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its

immediate predecessors.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
21

21) PERT stands for Probabilistic Evaluation and Review Technique.

Answer: FALSE

Di#: 3

Topic: INTRODUCTION

New cards
22

22) One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the

project in great detail—and thus come to an understanding of relationships between the activities.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
23

23) Slack is the time an activity can be delayed without impacting the completion time of the project.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
24

24) The variance of the project completion time is equal to the sum of the variances of all the activities.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
25

25) In PERT, we assume that the project completion time can be modeled by the normal distribution.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
26

26) One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an

activity.

Answer: TRUE

Di#: 2

Topic: PERT/COST

New cards
27

27) CPM stands for Comprehensive Project Method.

Answer: FALSE

Di#: 3

Topic: INTRODUCTION

New cards
28

28) The longest time path through a PERT/CPM network is called the critical path.

Answer: TRUE

Di#: 2

Topic: INTRODUCTION

New cards
29

29) In CPM, crashing an activity that is not on the critical path increases the cost of the project.

Answer: TRUE

Di#: 2

Topic: PROJECT CRASHING

New cards
30

30) Through the use of PERT/CPM, astute managers can derive flexibility by identifying noncritical activities and

replanning, rescheduling, and reallocating resources such as personnel and finances.

Answer: TRUE

Di#: 2

Topic: INTRODUCTION

New cards
31

31) In PERT, the variance in completion time is equal to the variance of the most time consuming activity on the

critical path.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
32

32) Given the assumptions in PERT, the probability that a project will be completed in less time than required by

the activities on the critical path is approximately 50%.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
33

33) Gantt charts and PERT diagrams provide the same information, just in different formats.

Answer: FALSE

Di#: 2

Topic: PERT/CPM

New cards
34

34) Gantt charts contain information about the time taken by each activity, but not about the sequential

dependencies of the activities.

Answer: TRUE

Di#: 2

Topic: PERT/CPM

New cards
35

35) The critical path of a network is the

A) shortest time path through the network.

B) path with the fewest activities.

C) path with the most activities.

D) longest time path through the network.

E) None of the above

Answer: D

Di#: 2

Topic: INTRODUCTION

New cards
36

36) In a PERT network, the earliest (activity) start time is the

A) earliest time that an activity can be finished without delaying the entire project.

B) latest time that an activity can be started without delaying the entire project.

C) earliest time that an activity can start without violation of precedence requirements.

D) latest time that an activity can be finished without delaying the entire project.

E) None of the above

Answer: C

Di#: 1

Topic: PERT/CPM

New cards
37

37) Slack time in a network is the

A) amount of time that an activity would take assuming very unfavorable conditions.

B) shortest amount of time that could be required to complete the activity.

C) amount of time that you would expect it would take to complete the activity.

D) difference between the expected completion time of the project using pessimistic times and the

expected completion time of the project using optimistic times.

E) amount of time that an activity can be delayed without delaying the entire project.

Answer: E

Di#: 2

Topic: PERT/CPM

New cards
38

38) The first step in planning and scheduling a project is to develop the .

A) employee scheduling plan

B) PERT/CPM network diagram

C) critical path

D) work breakdown structure

E) variance calculations for each

activity

Answer: D

Di#: 2

Topic: INTRODUCTION

New cards
39

39) Which of the following is not a concept associated with CPM?

A) normal time

B) probability

C) normal cost

D) crash cost

E) deterministic

network

Answer: B

Di#: 2

Topic: INTRODUCTION

New cards
40

40) PERT

A) assumes that we do not know ahead of time what activities must be completed.

B) assumes that activity time estimates follow the normal probability distribution.

C) is a network technique that uses three time estimates for each activity in a project.

D) is a deterministic network technique that allows for project crashing.

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

New cards
41

5

41) CPM

A) assumes we do not know ahead of time what activities must be completed.

B) assumes that activity time estimates follow the normal probability distribution.

C) is a deterministic network technique that allows for project crashing.

D) is a network technique that allows three time estimates for each activity in a project.

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

New cards
42

42) Managers use the network analysis of PERT and CPM to help them

A) derive flexibility by identifying noncritical activities.

B) replan, reschedule, and reallocate resources such as manpower and finances.

C) plan, schedule, monitor, and control large and complex projects.

D) All of the above

E) None of the

above

Answer: D

Di#: 2

Topic: INTRODUCTION

New cards
43

43) The expected time in PERT is

A) a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.

B) the modal time of a beta distribution.

C) a simple average of the most optimistic, most likely, and most pessimistic times.

D) the square root of the sum of the variances of the activities on the critical path.

E) None of the

above

Answer: A

Di#: 2

Topic: PERT/CPM

New cards
44

44) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively,

compute the PERT expected activity time for this activity.

A) 8

B) 6

C) 7

D) 9

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
45

6

45) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively,

compute the PERT expected activity time for this activity.

A) 6

B) 7

C) 9

D) 5

E) None of the

above

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
46

46) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively,

compute the PERT expected activity time for this activity.

A) 14

B) 12

C) 11

D) 13

E) None of the

above

Answer: D

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
47

47) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively,

compute the PERT variance for this activity.

A) 3

B) 6

C) 9

D) 18

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
48

48) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively,

compute the PERT variance for this activity.

A) 2.33

B) 5.44

C) 8.00

D) 64.00

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
49

7

days.

49) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively,

compute the PERT standard deviation for this activity.

A) 2

B) 4

C) 5

D) 15

E) None of the

above

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
50

50) Given the following small project, the critical path is Immediate

Time

Activity

Predecessor

(days)

A - 10

B - 4

C A, B 6

A) 10

B) 14

C) 16

D) 20

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
51

51) Given the following small project, the critical path is Immediate

Time

Activity

Predecessor

(days)

A - 8

B A 4

C - 10

days.

A) 4

B) 10

C) 12

D) 22

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
52

8

Table 12-1

The following represents a project with know activity times. All times are in weeks.

Activity

Immediate

Predecessor Time

A - 4

B - 3

C A 2

D B 7

E C, D 4

F B 5

52) Using the data in Table 12-1, what is the minimum possible time required for completing the project?

A) 8

B) 14

C) 25

D) 10

E) None of the

above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
53

53) Using the data in Table 12-1, what is the latest possible time that C may be started without delaying

completion of the project?

A) 0

B) 4

C) 8

D) 10

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
54

54) According to Table 12-1, compute the slack time for activity D.

A) 0

B) 5

C) 3

D) 6

E) None of the above

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
55

9

55) Using the data in Table 12-1, compute the latest finish time for activity E.

A) 4

B) 10

C) 14

D) 25

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
56

Table 12-2

The following represents a project with four activities. All times are in weeks.

Immediate

Predecessor

Optimistic

Time

Most

Likely

Time

Pessimistic

Time

Activity

A - 2 8 14

B - 8 8 8

C A 6 9 18

D B 5 11 17

56) According to the data in Table 12-2, what is the critical path?

A) A-B

B) A-C

C) B-D

D) A-B-C-D

E) None of the

above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
57

57) According to the data in Table 12-2, what is the minimum expected completion time for the project?

A) 18

B) 19

C) 37

D) 11

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
58

10

58) According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate

to use to determine the probability of finishing by a particular time. If you wished to find the probability of

finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard

deviation to be used with the normal distribution. What variance would be used?

A) 2

B) 4

C) 8

D) 12

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
59

59) According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate

to use to determine the probability of finishing by a particular time. What is the probability that the project is

finished in 16 weeks or fewer? (Round to two decimals.)

A) 0.07

B) 0.93

C) 0.43

D) 0.77

E) None of the above

Answer: A

Di#: 3

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
60

60) Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.

What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)

A) 0.98

B) 0.48

C) 0.50

D) 0.02

E) 0.63

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
61

11

61) Your company is considering submitting a bid on a major project. You determine that the expected

completion time is 100 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution

applies. You wish to set the due date for the project such that there is an 85 percent chance that the project will be

finished by this time. What due date should be set?

A) 108.0

B) 110.4

C) 89.6

D) 85.0

E) 100

Answer: B

Di#: 3

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
62

Table 12-3

Immediate

Most

Activity

Predecessor Optimistic

Likely Pessimistic

Standard

Deviation Variance

A -- 4 5 6 0.333 0.111

B -- 12 16 18 1.000 1.000

C A 2 8 14 2.000 4.000

D A 5 5 5 0.000 0.000

E B, C 6 7 8 0.333 0.111

62) According to Table 12-3, there are five activities in a PERT project. Which activities are on the critical path?

A) A-B-C-D-E

B) A-C-E

C) B-D

D) A-B-C-D

E) B-E

Answer: E

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
63

63) According to Table 12-3, there are five activities in a PERT project. What is the variance of the critical path?

A) 5.222

B) 4.222

C) 1.222

D) 0

E) 1.111

Answer: E

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
64

12

64) According to Table 12-3, there are five activities in a PERT project. If the normal distribution were used to find

the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?

A) 20 and 4.222

B) 30 and 5.222

C) 20 and 5.222

D) 30 and 4.222

E) 22.667 and 1.111

Answer: E

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
65

65) The critical path of a network is the

A) path with the least variance.

B) path with zero slack.

C) path with the most activities.

D) path with the largest variance.

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

New cards
66

66) In a PERT network, the latest (activity) start time is the

A) earliest time that an activity can be finished without delaying the entire project.

B) latest time that an activity can be started without delaying the entire project.

C) earliest time that an activity can start without violation of precedence requirements.

D) latest time that an activity can be finished without delaying the entire project.

E) None of the above

Answer: B

Di#: 1

Topic: PERT/CPM

New cards
67

67) The work breakdown structure involves identifying the A) time

B) cost

C) resource requirements

D) predecessors

E) All of the above

Answer: E

Di#: 2

Topic: INTRODUCTION

New cards
68

for each activity.

13

68) PERT stands for .

A) probabilistic evaluation and review technique

B) program evaluation and review technique

C) probability of expected run times

D) program of expected run times

E) project evaluation and review technique

Answer: B

Di#: 2

Topic: INTRODUCTION

New cards
69

69) CPM stands for .

A) critical path management

B) critical project management

C) critical project method

D) critical path method

E) centralized project management

Answer: D

Di#: 2

Topic: INTRODUCTION

New cards
70

70) Which of the following questions can be answered by PERT?

A) When will the entire project be completed?

B) What is the probability that the project will be completed by a specific date?

C) What are the critical activities?

D) What are the noncritical activities?

E) All of the above

Answer: E

Di#: 1

Topic: PERT/CPM

New cards
71

71) In PERT, we assume that

A) the times to complete individual activities are known with certainty.

B) all activities are carried out by sta# from our own organization.

C) the total cost of a project is independent of the time to complete the project.

D) the total time to complete all activities on the critical path is described by a normal distribution.

E) None of the above

Answer: D

Di#: 2

Topic: PERT/CPM

New cards
72

72) The two common techniques for drawing PERT networks are .

A) NOA and NRA

B) AON and AOA

C) GANTT and NOA

D) ONA and OAO

E) CAN and CAA

Answer: B

Di#: 3

Topic: PERT/CPM

New cards
73

14

73) In PERT analysis, the probability of the optimistic time occurring should be on the order of .

A) 1/2

B) 1/3

C) 1/6

D) 1/10

E) 1/100

Answer: E

Di#: 2

Topic: PERT/CPM

New cards
74

74) The expected time in PERT is

A) greater than the most likely time.

B) equal to the most likely time.

C) less than the most likely time.

D) any of the above

E) None of the above

Answer: D

Di#: 2

Topic: PERT/CPM

New cards
75

75) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively,

compute the expected time for this activity.

A) 5

B) 6

C) 7

D) 12

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
76

76) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively,

compute the expected time for this activity.

A) 3

B) 4

C) 5

D) 6

E) None of the above

Answer: D

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
77

15

77) Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively,

compute the PERT expected activity time for this activity.

A) 10

B) 12

C) 9

D) 11

E) None of the above

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
78

78) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively,

compute the PERT variance for this activity.

A) 3

B) 1

C) 9

D) 6

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
79

16

79) The project described by:

Immediate

Predecessor

Time

(days)

Activity

A -- 10

B A 4

C A 6

D B 7

E C 5

is best represented by which of the following networks?

A)

B)

C)

D)

E) None of the above

Answer: A

Di#: 1

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
80

17

80) The project described by:

Immediate

Predecessor

Time

(days)

Activity

A -- 10

B A 4

C A 6

D B, C 7

E C 5

has a critical path of length of .

A) 21 days

B) 14 days

C) 23 days

D) 32 days

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
81

81) The project described by:

Immediate

Time

Activity

Predecessor

(days)

A -- 6

B A 2

C -- 8

D B, C 5

E D 7

has a critical path of length of .

A) 15 days

B) 20 days

C) 17 days

D) 18 days

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
82

18

Table 12-4

The following represents a project with known activity times. All times are in weeks.

Immediate

Predecessor Time

Activity

A -- 4

B -- 3

C A 2

D B 7

E C, D 4

F B 5

G E, F 4

82) Using the data in Table 12-4, what is the minimum possible time required for completing the project?

A) 8

B) 12

C) 18

D) 10

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
83

83) Using the data in Table 12-4, what is the latest possible time that C may be started without delaying

completion of the project?

A) 0

B) 4

C) 8

D) 10

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
84

84) Using the data in Table 12-4, compute the slack time for activity D.

A) 0

B) 5

C) 3

D) 6

E) None of the above

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
85

19

85) Using the data in Table 12-4, compute the latest finish time for activity E.

A) 4

B) 10

C) 14

D) 25

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
86

86) Using the data in Table 12-4, determine the latest time activity A can be started without delaying the project

completion.

A) 4

B) 3

C) 8

D) 6

E) None of the above

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
87

87) Using the data in Table 12-4, determine the latest time activity A can be finished and not delay any activity?

A) 4

B) 0

C) 8

D) 5

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
88

88) Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks.

What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)

A) 0.68

B) 0.78

C) 0.22

D) 0.32

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
89

20

89) Your company is considering submitting a bid on a major project. You determine that the expected

completion time is 150 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution

applies. You wish to set the due date for the project such that there is a 95 percent chance that the project will be

finished by this time. What due date should be set?

A) 108.0

B) 160.4

C) 166.5

D) 135.0

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
90

Table 12-5

Immediate

Predecessor Time ES EF LS LF

Activity

A -- 4 0 4 6 10

B -- 5 0 5 0 5

C A 3 4 7 10 13

D B 8 5 13 5 13

E B 2 5 7 16 18

F C, D 3 13 16 15 18

G C, D 7 13 20 13 20

H E, F 2 16 18 18 20

90) How long could Table 12-5's activity E be delayed without delaying the completion of the project?

A) 7

B) 16

C) 11

D) 18

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
91

91) How long could Table 12-5's activity F be delayed without delaying the project?

A) 2

B) 3

C) 14

D) 16

E) None of the above

Answer: A

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
92

21

92) What is the minimum possible time required for completing the Table 12 -5 project?

A) 14

B) 18

C) 17

D) 20

E) None of the above

Answer: D

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
93

Table 12-6

Immediate

Most

Activity

Predecessor Optimistic

Likely Pessimistic σ σ2

A -- 2 3 4 0.333 0.111

B -- 2 5 8 1.000 1.000

C A 1 2 9 1.330 1.780

D A 5 5 5 0.000 0.000

E B, C 6 7 8 0.333 0.111

F B 14 14 14 0.000 0.000

G D, E 1 5 9 1.333 1.780

H G, F 1 4 8 1.167 1.362

93) Which activities are part of Table 12 -6's critical path?

A) A-B-E-G-H

B) A-C-E-G-H

C) A-D-G-H

D) B-F-H

E) None of the above

Answer: D

Di#: 3

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
94

94) What is the variance of Table 12 -6's critical path?

A) 5.222

B) 4.364

C) 1.362

D) 5.144

E) 2.362

Answer: E

Di#: 3

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
95

22

Figure 12-1

95) Given the network in Figure 12-1, the critical path is

A) A-C-F-H.

B) B-D-E-F-H.

C) A-C-E-G-H.

D) B-D-G-E-F-H.

E) None of the above

Answer: B

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
96

96) Given the network in Figure 12-1, the time to complete those activities on the critical path is expected to be

.

A) 20

B) 22

C) 25

D) 26

E) None of the above

Answer: C

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
97

97) Given the network shown in Figure 12-1, assume that completion of A is delayed by two days. What other

activities are impacted?

A) B

B) D

C) E

D) C

E) None of the above

Answer: D

Di#: 2

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
98

98) Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens

to the project?

A) The critical path is extended by two days.

B) The start of activity F is delayed by two days.

C) The start of activity E is delayed by two days.

D) All of the above

E) None of the above

Answer: D

Di#: 2

Topic: PERT/CPM

New cards
99

99) Given the network shown in Figure 12-1, assume that the completion of activity C is delayed by four

days. What changes will take place?

A) The critical path will change to: A-C-B-D-E-F-H.

B) Activity F will be delayed by four days.

C) Activity E will be delayed by four days.

D) Activity G will be delayed by four days.

E) None of the above

Answer: E

Di#: 3

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
100

100) Given the network shown in Figure 12-1 and the following information, what is the variance of the critical

path?

Activity Expected time Variance

A 3 2

B 5 3

C 6 3

D 4 1

E 5 1

F 4 2

G 6 2

H 7 2

A) 16

B) 7

C) 9

D) 8

E) None of the above

Answer: C

Di#: 3

Topic: PERT/CPM

AACSB: Analytic Skills

New cards
robot