What is the purpose of cultural comparison tools?
To identify broad cultural tendencies that may affect communication, leadership, trust, feedback and teamwork
What are the 6 Hofstede dimensions?
Power distance
Individualism
Motivation toward achievement and success
Uncertainty avoidance
Long-term orientation
Indulgence
What are Erin Meye’s eight cultural scales?
Communicating
Evaluating
Leading
Deciding
Trusting
Disagreeing
Scheduling
Persuading
Difference between low-context and high-context communication
Low context: direct, less need for interpretation
High context: Communication relies more on relationships , feelings, implied meaning etc.
What is the danger of using cultural comparison incorrectly?
Treating national tendencies as fixed rules or stereotypes about every individual
Besides culture, what else can explain a person’s behaviour?
Their personality and the specific situation
What is Cultural Intelligence or CQ?
The ability to work and interact effectively across different cultural settings
What are the four components of CQ?
Drive, Knowledge, Strategy, Action
What is CQ Drive?
The motivation and confidence to learn about and engage with different cultures
What is CQ Knowledge?
Understanding cultural similarities, differences, norms and systems
What is CQ Strategy?
Recognising what is happening culturally, checking assumptions and planning an appropriate response
What is CQ Action?
Adapting verbal and non-verbal behaviour appropriately in different cultural situations.
What is a project charter?
formal document that authorises the project and gives the project manager authority to use organisational resources
At what stage is the charter normally created?
During project initiation
Whaat is the difference between a charter and a detailed project plan?
The charter gives high-level authorisation and direction; the project plan contains detailed instructions for carrying out the work
What should a project charter include?
Project name, objective, success criteria, key deliverables, milestones, requirements, resources or budget, major risks, stakeholders, project manager and approval
What is the difference between an objective and a deliverable?
The objective describes the intended result; a deliverable is a specific output produced by the project
Why is formal approval important?
It confirms that the sponsor supports the project and authorises the project manager to proceed
Why is an international project charter especially useful?
It creates a shared written understanding across countries, organisations, languages and working styles
What is Work Breakdown structure?
A hierarchical breakdown of the total project scope into smaller deliverables and manageable work packages.
What is the main purpose of WBS?
To ensure all required project work is identified, organised and assigned
What is a dependency?
A relationship in which one task relies on another task starting or finishing
What is the critical path?
The longest sequence of dependent activities through the project network which determines the minimum project duration.
What happens when an activity on the critical path is delayed?
The overall project completion date is delayed unless corrective actions is taken.
What is float or slack?
The amount of time a on-critical activity can be delayed without delaying the entire project
Why can international critical paths contain hidden delays?
Because of public holidays, customs, visas, regulatory approvals, time zones and international shipping