1/38
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
Project Manual consists of:
owner contractor agreement
Conditions of contract
Specifications
Procurement documents consist of:
project manual
Contract drawings
Addenda
Bidding documents consist of:
ad to bid / invitation to bid
Instructions to bidders
Bid forms
Bid security info
Performance bond requirement
Labor & material payment bond
IPD task / phase:
conceptualization
Prepare design schedule and identify potential design, and sustainability goals
IPD task / phase:
Criteria design
Create performance specifications, and confirm sustainability targets
IPD task / phase:
Detailed design
Develop concept ideas into constructible forms and conduct detailed code study for compliance
How should Architect prepare for changes in project scope in design or construction scope?
make sure all parties understand scope before agreement
conduct value engineering studies
Record meetings with audio or video
Get written approval from owner before doing work
Firms performance management process:
Goal setting
Supervisor appraisal
Performance coaching
Self evaluation
Ahpp ch. 8.1 pg 448-450
What are the four types of quality cost per science theory?
Prevention costs
Appraisal costs
Internal failure costs
External failure costs
AHPP page 816
Main goal of international green construction code (IgCC):
Establish higher standard for conservation of water, construction materials, energy, and indoor environments
Surety bond
Performance bond; guarantee satisfy completion of project by a contractor
Surety will perform remaining work or provide funds in order to do so
3 documents contractor must present to Architect before final payment can be processed:
consent of surety
Affidavits for payment
Proof insurance will remain in force after final pay
Construction documents are:
Complementary and what is required by one is required by all
AHPP page 176
Tools owner can ask bidders to include in bid documents to avoid unwanted cost increases during construction:
Unit price
Bid alternate
Allowance
Cost plus
AHPP chapter 10.8 page 701 and 707
If email was an approved form of documentation according to consultant contract, what action can Architect take when addressing additional owner request?
Any hi adjustments to schedule / cost of work / scope must be submitted to owner for approval
If emails are approved form documents, Architect should not request letter in order to inform owner of additional service
When reviewing pay application, Architect notices in complete work; how should he proceed?
Withhold entire certification for payment and notify owner and contractor
Agree on a revised amount with contractor and partially withhold payment
Determine amount that will be withheld
Nullify previous issued certificate for payment
Who should Architect recommend to hire before schematic design phase for an integrated project Delivery project?
General contractor
Geotechnical consult consultant for underneath the ground
Historical preservation - if applicable
Construction manager
Where should Architect look for accessibility scope regulations for multifamily housing project?
fair housing act
Provides design and construction requirements as well as accessibility requirements
Consultants retained by Architect that are usually licensed:
Civil engineer
Landscape architect
Structure engineer
MEP engineer
Technology consultant
Security consultant
AHPP chapter 10.2
Contract time is binding, but maybe extended to accommodate:
Faults of Architect, owner or separate contractor
Fire
Adverse weather
Changes to the work
Contract time is of the essence; work must be completed by specified date or general contractor is in breach of contract
Record documents related to modifications contractor must provide architect as part of project closeout?
construction change orders
Supplemental drawings
Product submittals
Architect observed potential hazard material in early stages of Project; how should he address the situation?
Advice owner to engage in third-party hazardous materials testing consultant
Materials at risk of containing of asbestos should be tested by owner engaged third-party company and mitigated properly If found to be hazardous
Guaranteed maximum price:
The last contractor to give owner a price early on in process using the design development drawings, not at construction document detail level
Additional risk to general contractor
Preliminary budget is set at what face?
Schematic design
Owner hired party does not appear to do work; what can the contractor do?
Make a claim for delay and / or additional cost incurred as a result
Obtaining written program from owner is part of what phase?
pre-design
During bidding / negotiation phase, the architect shall assist the owner with the following:
organizing pre bid conferences for Prospect bidders
Preparing summary reports of negotiation results
Organizing and conducting the opening of bids
Participating in negotiations with prospect contractors
Helps the Design team understand and meet deliverables:
Responsibility matrices
Project schedule
Client requirements
AHPP chapter 10.1
What phase does outline specifications take place?
Schematic design
What phase does project manual take place?
Construction documents
Factors to monitor to maintain compliance with established construction document milestones:
Project budget
Percent complete
AHPP page 634 to 637
If agreement with owner is set to expiring 30 days after a substantial completion, but has to be extended for unforeseen results what documents should Architect prepare?
Invoice for additional services for owner payment
Notice to contractor for withholding payment
If a mission is caused by contractor
AIAB101 - 4.2.3
How is contract time measured?
Commencement of work : established in agreement - start
Substantial completion - end
Measuring it in calendar days
AIA 201 - article 8
Used by contractors when submitting bids to manage risk:
contingency
AHPP chapter 10.8 page 705
Per B101 who is responsible for contracting government authorities required to approve construction document?
Architect
AIA B101 ARTICLE 3.1.5
4 main types of schedules:
Critical path method
Milestone charts
Bar charts
Wall schedule
Who is responsible for paying building permits and taxes for the work?
Contractor pays for both taxes and building permit
If Initial information changes later on what changes?
architect Services
Schedule
Cost of work
Structure engineer would develop load calculations and member sizing at which phase of project?
Design development
Structural engineer will make preliminary selections of major structural components and systems