1/16
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
What is a Gannt chart
- type of bar chart that illustrates a project schedule
- start and finish dates of all elements of the work breakdown structure are shown
- dependency relationships between activities are also shown
what does a netowork diagram show you
- looks like a flow diagram
- shows timing information, which is needed by the project manager to manage the completion of the project as quickly as possible
- it is more information per unit area of the chart
network diagram
explicitly defines and makes visible dependencies (precedence
relationships) between the WBS elements
• facilitates identification of the critical path and makes this visible
• facilitates identification of early start, late start, and slack for
each activity,
• potentially reduces project duration due to better understanding
of dependencies leading to improved overlapping of activities
and tasks where feasible
there are 2 common approaches = program evaluation and review technique (PERT)- US navy/ critical path method (CPM)- construction projects
EET (earliest event time)
earliest time any task can possible start/ finish based on timings of predecessor activities
LET (latest event time)
the latest a task can possibly start/ finish without delaying project completion
Network diagram formats
- made from a series of nodes and connected arrows
- 2 common formats = AoA (arrow to arrow) / AoN (activity on node)
- AoA = uses arrow to represent activities (tasks) and nodes to represent resulting events (deliverables)
- AoN = node boxes represent activities and key project data
layout of drawing a AoA diagram
-arrow = activity that is being represented
- top quadrant of node = EET
- bottom quadrant of node = LET
- at event 1, EET= 0
- arrows leading in are the tasks/ activities needed to be complete for that event to occur
EET calculation
EET = proceeding EET + TE of connecting activity arrow
- if there is one or more arrows going to the node, the EET would be largest total
LET calculations
preceding event LET - TE of connected acitivty
-final LET = final event EET
-if there is one or more arrows going to the node, LET will be the smallest total
-latest an event can occur without delaying project completion
slack/ float
a task has slack if its completion can be delayed
2 types of slack
- free slack = without delaying subsequent task completion
- total slack = without delaying overall project completion
slack calculation
=LET - EET
-tasks that have a difference between LET and EET ( in the node diagram) has slack
critical path
sequence of project network activities which add up to the longest overall duration
- Determines the shortest time possible to complete the project.( longest time to complete the project= shortest time for the whole thing)
– Contains all the tasks / activities with no slack
– A project can have several critical paths.
Any delay of an activity on the critical path directly impacts the planned project
completion date
• Other paths through the network with the total durations shorter than the critical path are called a sub-critical or non-critical path
critical time
total time to complete the critical path
how can you shorten the project time
By shortening the critical path (in 3 ways):
- pruning critical path activities
– by "fast tracking" (i.e., performing more activities in parallel),
– by "crashing the critical path" (i.e., shortening the durations of critical path activities by increasing resources applied)
crashing
to crash a project or a task is to complete it in less time by deploying more resources to complete it
-Careful planning is vital if we are to crash a project most efficiently
(by deploying resources where they will make most difference)
- Crashing will almost always involve an increase in cost
- We need to know the cost per day of crashing a project
- Then we can judge the cost / benefit ratio and decide if and where to crash
crash cost per day calculation
(crash - normal)COST / (normal-crash)TIME