1/126
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
Project risk
uncertain event or condition in the future, if it occurs, will have a positive or negative impact on one or more project objectives (scope, schedule, cost, quality, etc.)
Positive risks (opportunities)
the risks with positive effects or favorable situation in the organizational environment.
Arrival of new technology,
Removal of an international trade barrier
Negative risks (threats)
external elements in the environment that arise from political, economic, social, and technological forces and can cause problems for the business.
v New regulation, an increased trade barrier, or emergence of substitute products.
v Technological developments may make your offerings obsolete.
v Market changes may result from the changes in competitions or demographic shifts.
v The political situation determines governmental policies.
Internal risks
refers to risks that we face from our own company or within our own organization.
Examples of Internal Risks
v The project costs being exceeded because of inaccurate estimates or due to scope creep
v The project schedule is taking longer than expected
v The project performance or quality fail to deliver as planned.
v Personnel and resource management issues
v Labor shortages or poor morale
v Outdated technology or infrastructure
External risks
refers to risks that are outside the control of the project team which are difficult to predict.
v The project governance related to business management, changes in leadership
v The strategic approach related to using a wrong and unsuitable technology
v The market changes related to competition, currency fluctuation
v The legal issues related to changes in regulatory requirements, contract or patent
v The environmental issues related to earthquakes, storms, strikes
v Events that directly impact the project's effectiveness and are completely out of our control
Project risk management
art and science of identifying, analyzing, and responding to risk throughout the project lifecycle for meeting project objectives.
Plan risk management
refers to the process of defining how to conduct risk management activities for a project
Risk management objectives
v Increase the probability and impact of positive events
v Decrease the probability and impact of adverse events
Project manager’s responsibilities
v Develop a systematic approach to risk management
v Develop an open and honest communication for risk identification
v Address risks proactively throughout the project
v Focus on preventative instead of reactive problem solving
Risk Management Processes
Risk Identification
• Brainstorm, check previous projects, talk to experts • Risk register
Risk Assessment (quantification),
Risk Mitigation (response development),
Risk monitoring and control
What is the output of the Risk Management Processes
Risk Management Plan (RMP)
Tools and Techniques: Information Gathering
Brainstorming
Diagramming tech
Interviewing stakeholders
SWOT analysis
Root cause analysis
analytical technique used to determine the basic underlying reason that causes a variance/defect/risk. may underlie more than one variance/defect/risk
Risk trigger
indication that a risk is about to occur or has occurred
Trigger Condition
event or a situation that indicated a risk is about to occur
Diagramming technique
useful during the risk identification process and is a system or process flow chart
helps you recognize risks and find new risks int the process flow,
geographically shows the logical sequence of steps in a process from start to finish
Risk Categories
group of potential causes to risk, which can be grouped into categories such as:
Technical
Organizational - v Lack of prioritization of projects v Inadequate funding v Inadequate resource assignment
Project Management - v Poor allocation of the resources v Inexperienced resources
External - v Legal or regulatory requirements v Supplier and contractor risks
Risk register
tool project managers use to track and monitor any risks that might impact thier projects
list of identifies risk with potential responses, root causes, categories, and probability and impact
“a document in which the results of risk analysis and risk response planning are recorded.
a living document with a list of risks along with their status, impact and other key details.
v Risk categories v Identified risks v Potential causes v Potential responses
Plan risk responses
the process of figuring out options and actions needed to reduce threats and enhance opportunities to project objectives
Risk response
document that address risks by their priority and includes identification and assignment of a owner for each risk
Risk strategies
Acceptance, Transfer, Mitigation (Control), Avoidance
Acceptance Risk Strategy
Adopting a wait-and-see attitude to take action when triggers are met
Do noth, cure is expensive than risk consequences
Mitigation (Control)
reduce probability/impact through active measure
bring down risk probability by proactive apporaches (training, buy vs build, etc)
Transfer
reduce probability/impact through change of ownership (outsource or buy insurance)
Avoidance
v Eliminate risk by accepting another alternative (e.g., changing the design)
v Elect to not do part of the project associated with the risk (do risk/return analysis; revisit scope)
Qualitative Risk Analysis
process of prioritizing risks by assessing and combining their probability of occurrence and impact to the project.
Risk has two primary dimensions
probability and impact
= f(probability, impact)
a probability of occurence of an event and impact/consequence off the event occurring (amount at stake)
Probability
The probability of risk occurring can range from 0% to 100 %
how likely each risk is going to happen
impact
how bad it would be for the project if each risk did happen, The size varies in terms of cost
Expected Monetary Value (EMV)
a tool to quantify the project risk in term of cost, helps PMs to evaluate the potential costs of project risks
calculated by p x i
multiplying the probability of a risk event occurring with the impact of that risk on cost
Positive EMV
indicated that the risk has a positive impact or benefit if it occurs (+)
negative EMV
indicates that the risk has a negative cost if it occurs (-)
Project schedule
a timetable that, at minimus shows
what needs to be done, start and end dates for all activities, who the resources are and the project due date.
project schedule
developed by a pm by analyzing all task durations, sequences, and resources needed
How to develop a project schedule
identify all activities and determine logical order
assign resources to each activity
estimate time required for that activity
consider project budget, quality, and risk factors
Project schedule baseline
when the project schedule is approved by the client, and after this approval the change control process should be used to modify the project schedule baseline.
Activity
distinct, scheduled portion of work performed during the course of a project
manageable chunk of work in a project
typically starts with an actionable verb
Duration
the total number of work periods required to complete a schedule activity, usually expressed as workdays
A project network consists of…
a set of circles or boxes called nodes (which represent activities), and arrows called arcs (which define the precedence relationship between activities)
the main idea for both networks is to determine the critical path
Activity on Node
also called precedence diagraming method (pdm), where nodes designate activities
Activity-on-arrow
also called Arrow Diagramming Method (ADM), arrows designate activities
Network Analysis
used the forward pass and backward pass routine to analyze the project network
Milestones
a significant event in the project schedule with zero duration, shows major deliverables and their specific completion dates and are difficult to change (require sponsor approval)
Path
sequence of connected activities in a project network
Sequencing project activities
process that involves taking the activities and milestones and sequences them in the logical order in which the work will be performed, results in a project schedule network diagram
Network diagram
graphical representation of the logical relationships/dependencies between project tasks
Successor activity
a dependent activity that logically comes after another activity in a schedule
Predecessor activity
an activity that logically comes before a dependent activity in a schedule
Precedence Diagramming Method (PDM)
a method for developing a project schedule in which tasks are linked by logical relationships (dependencies) to show the tasks’ sequences.
How many dependencies does precedence diagramming method (PDM) have?
Finish to Start, Finish to Finish, Start to Start, Start to Finish
Lead
the amount of time a successor activity can be advanced with respect to a predecessor activity
the overlap between the first and second activity.
Lag
the amount of time a successor activity will be delayed with respect to a predecessor activity. It is a waiting time between activities. the delay between the first and second activity
Estimate Activity Durations process
utilizes scope and resource information such as who will be doing the work, resource availability, and number of resources assigned to estimate durations for the activities of the project.
key benefit - it provides the amount of time each activity will take to complete, which is very helpful in developing the project’s schedule.
Analogous estimating
refers to a method for estimating the duration or cost of a task using data from similar projects.
❖ It is less accurate, less costly and takes less time to estimate
❖ It uses historical information and expert judgement
Parametric estimating
refers to a method that uses an algorithm to calculate duration or cost of a task using data from project parameters.
❖ Activity duration = quantity of work to be performed x labor hours
One-Point estimation or Bottom-Up estimating
refers to a method for estimating the duration or cost of a task based on expert judgement, historical information, educated guess, etc.
❖ It is the most accurate estimate and the most time-consuming exercise
❖ Sometimes forces people to add padding to their estimates (not recommended)
3-Point or PERT (Program Evaluation and Review Technique) estimation
refers to a technique that uses a weighted average of three numbers (optimistically, most likely, pessimistically) to develop a final estimate.
Optimistic time estimate (O):
Shortest possible time to complete an activity under perfect circumstances
Most likely time estimate (M):
Most likely time to complete an activity under normal circumstances.
Pessimistic time estimate (P):
Longest possible time to complete an activity under a worst-case scenario.
PERT: Program Evaluation and Review Technique
a project management planning tool used to calculate the time it will take to finish a project.
a visual method for identifying task sequencing and dependencies and for finding the critical path of a project
Estimates the most likely time needed to complete a project
Critical Path Method (CPM)
a method to estimate the project duration.
❖ Used to plan very large projects
❖ Used single time estimates for each activity
❖ Focus on longest sequence of activities
❖ Used to determine how to complete a project early
Critical path
the longest sequence of activities that must be finished on time to complete a project, any delays in critical tasks will delay the whole project
sequence of activities that represents the longest path through the project, which determines the shortest possible duration
Forward pass and backward pass methods are used to determine the critical path. The critical path is indicated by the activities with zero slack.
Forward pass
Finds Early Start and Early Finish, critical path method tech for calculating the early start and early finish dates
Earliest start time (ES)
the earliest time an activity can start.
Early finish (EF)
the earliest time an activity can finish, This would be ES + activity duration
backward pass
critical path method technique for calculating the late start and late finish dates.
Late start (LS)
the latest time an activity can start and not delay the project, This would be LF - activity duration.
Late finish (LF)
the latest time an activity can finish and not delay the project
Slack/float
the amount of time a project activity that is not on the critical path can be delayed without delaying the early start of the next activity or the entire project.
indicates how flexible the project schedule can be. More slack time means that project scheduling is more flexible.
❖ LS – ES (LS minus ES) = Slack ❖ LF – EF (LF minus EF) = Slack
Formulas for calculating the expected duration (PERT value)
❖ Beta distribution formula: E = (O + 4M + P) / 6 (most commonly used). The three estimates are normally provided or given based on previous experience, knowledge, or expert judgement.
❖ The expected duration of a path is equal to the sum of the expected times of activities on that path.
❖ The standard deviation (SD) of each activity’s time is estimated as one-sixth of the difference between the pessimistic and optimistic time estimates.
❖ The variance is the square of the standard deviation
Cost
common cause of project failure.
a resource to achieve specific objective in managing projects. It usually measured in monetary units like dollar
Project managers need to consider time, resources and scope to determine overall ____
Project cost management
includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.
Project Cost Management Challenges
Lack of resources: The project manager will have a significant difficulty to secure the necessary resources (people, materials, or technology) to complete the project successfully on-time.
Poor cost estimation: This is the most common issue in failing projects. Poor estimation/forecasting occur when a project manager is not experienced enough (e.g., cost, scope, schedule). Poor cost estimation often leads to cost overruns
A well-defined, bottom-up approach
very helpful in estimating costs and creating a budget for the project.
Why should PMs take cost estimates seriously?
if they want to complete projects on a budget
Fixed cost (1 of 4 main types of cost)
This type of cost does not change as production change throughout the life of a project.
Variable Cost:
This type of cost varies with the amount of work/production and changes month to month.
Direct Cost
This type of cost is directly attributable to the project work. It occurs only because of the project.
Indirect Cost
an overhead cost or cost that is incurred for the benefit of more than one project. It is not associated with one specific project.
Project Cost Management
concerned with the cost of all the resources needed to complete project activities.
Cost management plan can establish:
units of measure, level of precision, level of accuracy
Level of precision:
the degree to which cost estimates will be rounded up or down. For example, rounding up $695.96 to $697.
Level of accuracy:
The acceptable range (e.g., ±10%) used in determining realistic cost estimates
Estimate Costs
the process of developing an approximation of the cost of resources needed to complete project work.
using these inputs to estimate costs: v Cost management plan v Quality management plan v Scope baseline and project schedule v Resource requirements v Risk register v Previous projects
Activity-based estimates
• Cost for an activity is based on the costs for labor and materials (preferred)
Detailed estimates from all sources are reorganized
An activity can have costs from more than one vendor
Reserve
refers to the extra money in project budget to be used if necessary,
money is budgeted for dealing with unplanned but predictable cost increases.
contingency reserve
the money held to pay for predictable but unspecified extra costs.
Project manager performs risk management process to determine this through a method such as expected Monetary value (EMV).
Management reserve
refers to the money assigned to the project for unknown possible costs and money that senior management controls
ex) if something happens during the project that changes the scope, so basically the money primarily available for changing project scope.
Estimated cost
refers to the total project cost estimates that the project manager makes. Then the management prepares the overall project budget.
Budgeted cost
refers to a budget that the management has prepared and allocated to the project. It shows how the money will be spent
Estimated cost should not ______ budgeted cost
exceed
Determine Budget
the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Cost Baseline
a time-phased budget used to monitor, measure, and control cost performance during the project.
It includes contingency reserves but not the management reserves.
Control account
a management control point where scope, cost and schedule are integrated and compared to the earned value (EV) for performance measurement.
comprises of the amount allocated for the completion of the work in the work packages. Since the work packages are linked to the organizational units, organizational unit wise budget consumption also can be monitored effectively. This is the cost aggregation
Cost Baseline Formula
Cost Estimate + Contingency Reserve
Project Budget Formula
= Cost Baseline + Management Reserve
Control Costs
the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline
Earned Value Management (EVM)
common method of project performance and progress measurement throughout the project lifecycle in terms of the cost and schedule control.
integrates project schedule, costs, and scope to measure the overall project performance
compares the budgeted and actual costs of a project
helps project managers with project forecasting (future performance)
used when there is a risk to on-time and on-budget project delivery and cost and schedule needs to be managed
answers - “ Are we ahead of or behind schedule?”