it evaluates the structural strength of coarse aggregate. It gives an indication of quality as determined by resistance to impact and wear. It also determines whether the aggregates will have degradation during traffic or rolling.
What is Significance of abrasion test is that?
No. 12 (1.70 mm)
What is the sieve used in sieving materials for abrasion test?
14 days
At what age should a concrete beam sample be tested for flexural test?
R = PL/bd2
How to compute the flexural strength of concrete beam sample tested at third point?
R = 3PL2/bd2
How to compute the flexural strength of concrete beam sample tested at center point?
16 mm Ø and 610 mm long with the tamping end rounded to a hemispherical tip of the same Ø as the rod.
What is the size of the tamping rod used is sampling concrete?
6 pcs per 10,000 units (12 pcs if more than 10,000 units)
Concrete masonry (hollow blocks) if subject to test, how many samples are required?
Individual = 5.5 MPa (800 psi) minimum
Average (for 3 samples) = 6.9 MPa (1000 psi) minimum
What is the strength requirement for load bearing concrete masonry units?
Individual = 3.45 MPa (500 psi) minimum
Average (for 3 samples) = 4.5 MPa (600 psi) minimum
What is the strength requirement for non – load bearing concrete masonry units?
to determine the yield and tensile strength of the bar as well as its elongation and is used to classify the bars into grade.
What is the significance of testing reinforcing steel bars?
To evaluate the ductile properties of RSB
What is the significance of bending test for RSB?
1 can (gal or pail)/ 100 cans (gal or pail)
What is the required testing requirement for paints?
slow - setting emulsified asphalt
SS – l or SS – lh is what kind of asphalt?
24 hours
For how many hours or how long shall a bituminous prime coat be left undisturbed?
cut – back asphalt
What kind of asphalt is used as tack coat?
25 pcs
One (1) set of concrete cylinder sample shall be taken for every how many pieces of RCCP?
thickness and density
What is being determined in a core sample from asphalt pavement?
materials logbook
All records regarding quality control such as accomplishment, daily activities, weather, etc. are recorded in a _____
depth of soil layer
The Standard Penetration Test (SPT) is an in – situ test that measures what?
segregation
The main problem associated with wrong practice of conveying concrete is called _____
three (3) layers over the full width of 4.5 m
A one – lane road with a pavement width of 3.5 m and shoulder width of 0.5 m on each side of the pavement was designed to have subbase and base courses with a combined thickness of 300 mm. If the thickness of the subbase is 125 mm, the spreading and compaction of the base and subbase courses shall be carried out in _____?
higher
During the application of the first half of the anticipated load a _____ rate of loading shall be permitted?
Test of concrete pipe samples
Quality of factory – produced RCCP may be best established through what?
geotextiles
Soft and unstable soils were encountered during the course of subgrade preparation. If you were the ME assigned to the project, what is the most effective and cheaper method that you would recommend to stabilize the soil prior to the construction of the subbase course?
63 blows per layer
How many times per layer should a concrete specimen molded in a 6” x 6” x 21” beam mold be rodded?
pulverizing of the aggregate, displacement of the mixture
Rolling of bituminous mix shall be discontinued whenever it begins to produce excessive _______ or _______.
29ºC
In placing concrete, the required temperature should be less than ____
12 sets
How many concrete cylinder samples is required for a 300 pcs RCCP?
6 pcs RCCP
If concrete cylinder is not available for a 300 pcs RCCP, how many pipes shall be subjected to test?
not exceeding 45 minutes and that water – cement ratio is not exceeded.
If there is a necessity to add water to the concrete mix in order to increase its workability (provided concrete does not exceed specified slump), how many minutes after the initial time of mixing does adding water be permitted?
TAR – is a viscous liquid obtained from the distillation of coal or wood.
PETROLEUM ASPHALT – are the products of the distillation of crude oil.
What are the two (2) types of bitumen that are commonly used in the bituminous mixture?
Asphalt cement, cut – back asphalt, emulsified asphalt
What are the three (3) major petroleum asphalts?
GASOLINE – for rapid curing type
KEROSENE – for medium curing type
DIESEL – for slow curing type
What are the solvents of cut – back asphalts?
CATIONIC EMULSION – works better with wet aggregates and in cold weather. It is a positively charge electron.
ANIONIC EMULSION - adheres better to aggregates which have positive charge. It is a negatively charge electron.
Emulsified asphalts are either _____ or _____.
asphalt cement
What is the bituminous material used in Item 310?
grade and quantity of asphalt
What greatly affects the service of asphalt cement?
climatic condition
What influences primarily the grade of asphalt selected?
three (3) weeks
How many weeks do the producer of asphalt mix or the contractor shall submit the job – mix formula?
DPWH PE and ME
Who will approve the job – mix formula?
a. grading of aggregates
b. percentage and type of asphalt
c. temperature of aggregates and asphalt
d. temperature of mixture upon delivery or time of compaction
The job – mix formula contains provisions the following:
66ºC to 107ºC
When tar is used, what is the temperature that the mixture shall be placed?
when the mixture is still hot and workable
When is the right time to compact in order to attain the required density?
trial section
What is to be done in order to determine the number of passes that would attain the required density?
temperature
What needs to be controlled during the mixing and compaction and is of great significance in the strength of the resulting pavement?
It should begin from the sides and proceed longitudinally parallel towards the center line, each trip overlapping one half the roller’s width.
In Item 310, how is rolling be done?
degree of compaction
After the final rolling, what will be checked?
95% of the laboratory compacted density
The compacted pavement shall have a density equal to or greater than _____
when the pavement has cooled to atmospheric temperature
When will the traffic be permitted to utilize the pavement?
by the use of core drill or saw
How do we take sample from the finish pavement?
40 mm – 75 mm
What is the allowable slump of a workable concrete if not vibrated?
10 mm – 40 mm
What is the allowable slump of a workable concrete if vibrated?
not less than 50 seconds or more than 90 seconds
When concrete is mixed in a central mixing plant, what is the time of mixing?
It shall not exceed 45 minutes if hauled in non – agitating trucks and 90 minutes if hauled in truck mixers or agitators.
In transporting concrete, what is the time elapsed from the time water is added to the mix until the concrete is deposited in – place at the site?
by the use of vibrator inserted in the concrete vertically
How is concrete consolidated?
longitudinal construction joint
If the lanes are concreted separately, what kind of joint in a form of a keyway is used?
deformed steel tie bars
What kind of bar is placed perpendicular to the joint stated in the preceding problem?
not less than 50 mm
What is the depth of the weaken plane joint when sawed with a concrete saw?
not less than 6 mm
The width of the weaken plane joint is _____
sawing shall be omitted
What shall be done if cracks appear at or near the joint prior to the time of sawing?
asphalt or other materials
Tie bars shall not be coated or painted with _____
dowel
What is the material that is used as a load transfer device held in a position parallel to the surface and center line of the slab of pavement?
a thin film of bitumen
To protect dowels from corrosion and to facilitate sliding in concrete, it shall be coated with _____
brooming
The surface of the pavement shall be roughened by means of _____
1.5 mm
What is the depth of corrugation produced by brooming in the surface of the pavement?
72 hours
The surface of a newly put concrete when has sufficiently set shall be cured for a period of _____
a. by covering the concrete with mats saturated with water
b. by thoroughly wetting the pavement
c. by ponding
d. by applying curing compound immediately after finishing of the surface
The curing of the pavement is done by means of the following:
after the curing period or before it is opened to traffic
When is the right time to seal the joints?
the placement of stone or boulders and the ratio of cement and fine sand
What is the difference between Item 504 and Item 505 (bluebook ’95)?
Materials Engineer of the DPWH
The ME of the contractor is directly under the supervision of the _____?
well packed in durable containers to avoid damages in transit, accompanied by a sample card filled up in detail and duly signed by the ME
The requisites in transporting samples of the laboratory is _____
Materials Engineer of the DPWH
Who has the power to recommend the acceptance or rejection of construction materials for use in the project based on test results?
asphaltene
It is a chemical composition of asphalt that gives color and hardness.
No. 200
The mineral filler which is used in the bituminous mix is passing sieve?
pothole patching
Cold mix asphalt is used in _____
Voids in Mineral Aggregates
VMA means
124ºC
The compaction temperature in molding the bituminous mixture specimen
163ºC
The mixing temperature of bituminous mix is
121ºC - 188ºC
The heating temperature of bituminous mix is
177ºC - 191ºC
The heating temperature of aggregates ranges from
240 kg per m3
The maximum absorption content of CHB
45%
The maximum moisture content of CHB
Standard Penetration Test
SPT means
Shelby tube
A tube sampler is used in sampling undisturbed sample
wax
Used in sealing undisturbed sample
Split spoon sampler
A tube sampler is used in sampling disturbed sample
Standard Penetration Test
It is a dynamic test used in the field to obtain rapid empirical results which can be used to estimate shear strength and bearing capacity
diamond bit
A type of coring bit used in rock coring
Certificate of Quality Control Assurance (submitted weekly)
CQCA means
1.01-1.04
The specific gravity of asphalt ranges from
cationic
The type of electron present in rapid curing emulsified asphalt?
fifteen (15)
How many group of three in – situ densities are required if the compacted volume of embankment laid was estimated to be 1,500 cu. m with a thickness of 200 mm per layer?
6% maximum under nominal stress
The allowable % variation in mass of deformed reinforcing steel is
0.06%
The maximum allowable % phosphorous content of a deformed and plain billet steel bar is
TENSILE STRENGTH YIELD POINT
GRADE 40 483 MPa 276 MPa
GRADE 60 621 MPa 414 MPa
GRADE 75 689 MPa 517 MPa
Tensile and yield strengths of steel bars?
clay content
Plasticity index is an indication of percent
air – dried condition
The condition of the soil to be tested in the laboratory compaction test is
Sand cone method
The method in the determination of density of soil in – place
sieve No. 10 retained No. 200
Air –dry sand used in the density apparatus is passing
surfacing materials
Which of the following items does not need CBR?
GRADING A – 12 spheres
GRADING B – 11 spheres
GRADING C – 8 spheres
GRADING D – 6 spheres
In abrasion test, the abrasive charge shall consist of cast – iron spheres or steel spheres.