Predictive Process

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/136

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 8:00 PM on 7/11/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

137 Terms

1
New cards

100% Rule,

States that the Work Breakdown Structure (WBS) must include 100% of the work defined in the project scope

2
New cards

Acceleration

The use of methods to complete work in a shorter time than previously planned or required

3
New cards

Accepted Deliverables

Deliverables that have been formally accepted by the client through formal sign-off

4
New cards

Activity

A task or set of tasks carried out to create a deliverable

5
New cards

Activity Attributes

The elements associated with each scheduled activity including codes, predecessors, successors, relationships, leads, lags, resource requirements, constraints, assumptions, and imposed dates

6
New cards

Activity Duration Estimates

Quantitative assessments of the likely time required to complete an activity

7
New cards

Activity List

A detailed list of all planned project activities

8
New cards

Actual Cost (AC)

The amount of money actually spent to date on the project

9
New cards

Actual Duration

The actual amount of time a task has taken from start to completion or to the current point if still in progress

10
New cards

Backward Pass

A technique used to calculate Late Start and Late Finish dates by working backward through the network diagram

11
New cards

Baseline

The final approved version of the project scope, schedule, and cost

12
New cards

Basis of Estimates

A document explaining how estimates were developed and the supporting information used

13
New cards

Benefits Management Plan

A document describing how project benefits will be realized and managed

14
New cards

Beta Distribution (PERT)

A weighted average estimate giving the most weight to the most likely estimate to improve accuracy

15
New cards

Bottom-up Estimation

Estimating individual activities and combining them to determine the total project cost and duration

16
New cards

Budget at Completion (BAC)

The planned total budget for the entire project

17
New cards

Buffer

Extra time allocated to account for uncertainty, constraints, or delays

18
New cards

Change

A proposed modification to any project document, plan, deliverable, or work product

19
New cards

Change Control

A structured process for reviewing, analyzing, approving, implementing, and documenting change requests

20
New cards

Change Control Board (CCB)

The group responsible for approving or rejecting change requests

21
New cards

Change Control Plan

A document describing how project changes will be identified, evaluated, approved, communicated, and implemented

22
New cards

Change Log

A record used to track project changes and their status

23
New cards

Change Request

A formal proposal to modify any aspect of the project baseline

24
New cards

Closing Process Group

The process group used to formally complete the project, phase, or contract and obtain customer acceptance;

25
New cards

Code of Accounts

A numbering or lettering system that uniquely identifies each WBS component

26
New cards

Conceptual Estimate

An early estimate developed using prototypes, designs, mockups, or similar concepts to reduce uncertainty

27
New cards

Configuration Management Plan

A document describing how configuration items will be identified, tracked, controlled, and audited

28
New cards

Control

Activities used to monitor, measure, and adjust project performance

29
New cards

Control Accounts

Management control points where scope, schedule, and cost are integrated and measured

30
New cards

Cost Aggregation

The process of combining individual cost estimates into a total project cost

31
New cards

Cost Baseline

The approved project budget excluding management reserves

32
New cards

Cost Management Plan

A document describing how project costs will be planned, managed, and controlled

33
New cards

Cost Performance Index (CPI)

A measure of cost efficiency calculated as Earned Value divided by Actual Cost

34
New cards

Cost Variance (CV)

The difference between Earned Value and Actual Cost

35
New cards

Crashing

A schedule compression technique that adds resources to shorten project duration

36
New cards

Critical Chain

The longest chain of dependent activities considering both task dependencies and resource availability

37
New cards

Critical Path

The sequence of activities that determines the shortest possible project duration

38
New cards

Critical Path Method (CPM)

a project management technique for determining the project schedule using the network diagram

39
New cards

Deadline

the latest date or time by which a task or project should be completed

40
New cards

Decomposition

breaking down project deliverables into smaller, more detailed, and manageable work packages.

41
New cards

Definitive estimate

determined at the end of the planning phase, hence providing the most accurate cost estimation

42
New cards

Dependencies, Logical relationships:

relationships between tasks that determine their order in a project

43
New cards

Discretionary dependency, Soft, preferred, or preferential logic:

created based on the preference of the project team and the order of

activities they find more suitable or the nature of work.

44
New cards

Dropped Baton

refers to the impact of poor coordination when an activity is completed early and the resources or the new dependent activity are not ready, thus the time gained by completing the activity early is lost.

45
New cards

Early Finish (EF)

refers to the earliest possible date that a task or activity can be completed

46
New cards

Early Start (ES)

refers to the earliest possible date that a task can begin

47
New cards

Earned Value (EV)

Measures the budgeted value of work realized to date. It’s calculated to determine whether the project is on track, behind or ahead of schedule, and over or under budget.

48
New cards

Earned Value Management (EVM)

The process of performance measurement by monitoring project progress and comparing its actual performance to its planned performance.

49
New cards

Estimate at Completion (EAC)

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

50
New cards

Estimate to Complete (ETC)

The expected cost to finish all the remaining project work.

51
New cards

Estimating methods

Methods used to develop an approximation of work, time, or cost on a project.

52
New cards

Executing process group

Performed to implement the work defined and detailed in the planning process group. This group involves carrying out all planned activities to produce the project deliverables according to requirements.

53
New cards

Expert judgment estimating

making estimations based on the skill, expertise, or specialized knowledge of the project team, independent consultants, or subject-matter agencies.

54
New cards

External dependency

the type of dependency between project activities and non-project activities that is outside of the direct influence or control of the project team, but must nonetheless be accounted or when planning or managing a project schedule

55
New cards
Fast Tracking
a schedule compression technique that consists o concurrently completing tasks that would normally be completed sequentially
56
New cards
Finish-to-Finish (FF) dependency
when one task can only be completed after the other task has been completed
57
New cards
Finish-to-Start (FS) dependency
when the start of the successor activity depends on the completion o the predecessor activity
58
New cards

Float, Total Float, Slack

the amount of time that a task can be delayed without affecting the completion date of the project. Total Float can be calculated either by subtracting the Early Start date of the activity from its Late Start date or its Early Finish date from its Late Finish date. Critical path activities have zero float.

59
New cards
Forecasting

the process of making predictions, guesses, or assumptions of the possible outcomes of a project.

60
New cards
Forward Pass

moving forward through a network diagram to calculate the early start and early finish values, meaning the earliest day each project task can begin and wrap up

61
New cards
Free Float

the amount of time that an activity can be delayed without delaying the Early Start date of its successor activity

62
New cards

Gantt chart, Bar chart

A bar chart created to depict the scheduled activities’ duration and sequence; activities are listed on vertical bars, their start and finish dates are displayed across the top of the chart, and their durations are shown as horizontal bars.

63
New cards
Gold plating

Performing work that was neither requested nor approved by the client, aiming to deliver added value.

64
New cards
Historical information
information that was created and documented in earlier projects and developments, including documents such as project manuals, requirement specifications, reports, etc.
65
New cards
Initiating process group
This is the process group or launching the project. It’s performed to identify the project's objectives, scope, purpose, and key stakeholders.
66
New cards
Internal dependency
dependencies between two project activities that generally the project team has complete control over.
67
New cards
ITTOs
stands for Inputs, Tools & Techniques, and Outputs, a method used to understand how a process can be performed.
68
New cards
Kill point

a phase-end review that allows the organization to evaluate the project's performance and take immediate action to correct any problems or even cancel the project, hence the name kill point.

69
New cards
Lag time

the amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.

70
New cards
Late Finish (LF)
The latest date that the activity can finish without causing a delay to the project completion date.
71
New cards
Late Start (LS)
The latest date that the activity can start without causing a delay to the project completion date.
72
New cards
Lead
the amount of time in which a predecessor activity can run in parallel with a successor activity.
73
New cards
Mandatory dependency, Hard logic

is a negotiable dependency that means that the next task can't be started until the previous one has been completed.

74
New cards
Master schedule
a detailed plan that includes all aspects o multiple projects or operations, providing a broad overview of various project schedules, such as milestone schedules.
75
New cards
Milestone schedule
A type of schedule that presents milestones with planned dates.
76
New cards
Monitoring and Controlling process group
where the project's performance is tracked, reviewed, and adjusted to ensure that it stays on track and meets the planned objectives and requirements.
77
New cards
Murder board
a committee of experts, senior managers, and stakeholders that attends stage gate meetings to review and evaluate the phase performance, and accordingly, decide whether the project should continue or should be canceled.
78
New cards
Network diagram, Precedence Diagramming Method (PDM)
a graphical representation o the project schedule, depicting and mapping out all the tasks in a project.
79
New cards
Node
a key element within a project network diagram that represents a specific activity that needs to be accomplished.
80
New cards

Parametric estimating

uses statistical relationships and historical data to estimate the cost, duration, or resource requirements of a project or activity based on specific measurable parameters.

81
New cards
Parkinson’s law
States that work expands to fill the time available or its completion.
82
New cards
Performance Measurement Baseline
Integrated scope, schedule, and cost baselines used or comparison to manage, measure, and control project execution.
83
New cards

Performance review

a technique used to gauge, compare, and analyze the performance of work in progress against the baseline of the project.

84
New cards
Phase review, Stage gate, Phase gate, Phase entrance, Phase exit
a formal meeting to check that the desired outcomes or exit criteria or the phase have been achieved before proceeding to the next phase.
85
New cards
Planned Value (PV)
The authorized budget or accomplishing the planned work.
86
New cards
Planning package
A Work Breakdown Structure component under control accounts, used to plan and track activities that are not yet fully defined.
87
New cards

Planning process group

Involves developing the project management plans including its budget, schedule, assignments, and responsibilities.

88
New cards
Precedence relationship

defines the logical sequence between tasks, indicating the order in which activities must be performed. There are our types of dependencies: finish-to-start, start-to-start, finish-to-finish, and start-to-finish.

89
New cards

Predictive approach, Plan driven approach, Traditional approach, Waterfall

A development approach in which the project scope, time,

and cost are determined in the early phases o the life cycle.

90
New cards
Preliminary estimate, Rough estimate, Screening estimate, Approximate estimate

carried out at the beginning of the project based on historical data of other projects to provide a high-level estimate of the cost and time required or completing the project.

91
New cards
Process group
A logical grouping o project management processes to achieve specific project objectives.
92
New cards
Project calendar
A calendar that identifies workin days and shits that are available or scheduled activities.
93
New cards
Project Management Plan
is a document that describes how the project will be executed, monitored and controlled, and closed.
94
New cards
Project schedule
a detailed plan that outlines the duration o project activities, milestones, and deliverables to ensure the project is completed on time.
95
New cards

Ranged estimating

The process of estimating a minimum and maximum value or cost or schedule.

96
New cards

Requirements Management Plan

describes how project requirements will be analyzed, documented, and managed.

97
New cards

Requirements Traceability Matrix (RTM)

A grid that links product requirements from their origin to the deliverables that satisfy them.

98
New cards
Reserve Analysis

A method used to evaluate the amount of risk on the project and the amount of schedule and budget reserve to determine whether the reserve is sufficient or the remaining risk.

99
New cards
Resource leveling

Consists of altering the duration or the sequence of activities according to resources’ availability to avoid any overallocation. This can lead to changes in schedule.

100
New cards
Resource optimization technique
Used to adjust resource allocation before the schedule is approved or baselined.