Part 5

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/27

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 10:35 PM on 7/21/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

28 Terms

1
New cards

What is monitoring and control?

The continuous comparison of actual project performance against the approved plan, followed by corrective action when needed.

2
New cards

What is the difference between monitoring and control?

Monitoring collects information; control uses that information to make decisions and take action.

3
New cards

What are the five stages shown in the monitoring cycle?

Plan, execute, monitor, control and report.

4
New cards

What is a baseline?

The approved scope, schedule and cost plan against which actual performance is measured.

5
New cards

What options are available during control?

Correct the problem, escalate it, accept the variance or replan.

6
New cards

Why must performance be reported differently to different stakeholders?

Different stakeholders require different levels of detail, frequency and technical information.

7
New cards

What does EVM stand for?

Earned Value Management.

8
New cards

What two major questions does EVM answer?

Are we on schedule, and are we on budget?

9
New cards

What is Planned Value, or PV?

The budgeted value of the work that should have been completed by now.

10
New cards

What is Earned Value, or EV?

The budgeted value of the work that has actually been completed.

11
New cards

What is Actual Cost, or AC?

The amount actually spent on the completed work.

12
New cards

What is the Cost Variance formula?

CV = EV − AC

13
New cards

What does a negative CV mean?

The project is over budget.

14
New cards

What is the Schedule Variance formula?

SV = EV − PV

15
New cards

What does a negative SV mean?

The project is behind schedule.

16
New cards

What is the Cost Performance Index formula?

CPI = EV ÷ AC

17
New cards

What does a CPI below 1 mean?

The project is costing more than planned for the value of work completed.

18
New cards

What is the Schedule Performance Index formula?

SPI = EV ÷ PV

19
New cards

What does an SPI below 1 mean?

The project is progressing more slowly than planned.

20
New cards

What are the five stages of formal change control?

Identify the change, raise a change request, assess its impact, obtain a CCB decision, and update and communicate.

21
New cards

What happens when a change is identified?

It should be recorded immediately rather than handled informally.

22
New cards

What should a formal change request describe?

What is changing, why it is changing and the effects on scope, schedule, cost, quality and risk.

23
New cards

Why must the change’s impact be assessed across several areas?

A change in one area normally causes second-order effects elsewhere.

24
New cards

What is the CCB?

The Change Control Board, which has authority to approve, reject or defer a change

25
New cards

Can the project manager always approve a change alone?

No. Significant changes must be approved by the people with the appropriate authority.

26
New cards

What happens after a change is approved?

The baseline, project plan and affected documents are updated, and stakeholders are informed.

27
New cards

Why is communication particularly important after an international change?

Distributed stakeholders may be working with different documents, languages, time zones and assumptions.

28
New cards

What is scope creep?

Uncontrolled expansion of project scope without formal approval or corresponding adjustments to time, cost and resources.