Proving, Commissioning, and Troubleshooting a Loop (12410-16)

0.0(0)
studied byStudied by 0 people
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/19

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

20 Terms

1
New cards

Testing the components of a loop for functionality without using live process is known as

proving

2
New cards

Mechanical inspection, which includes checking for damage and improper components, is done

by visual inspection

3
New cards

If slightly damaged signal wiring or broken conduit is not repaired, the result can be

intermittent behavior

4
New cards

In a continuity test, a loop should not show excessive leakage or excessive

resistance

5
New cards

Generally, to test an electrical loop, the test instrument should be able to supply

Power

6
New cards

A pneumatic tester may have a built-in pressure source or it may require a

hand pump

7
New cards

During loop proving, the process must be

simulated

8
New cards

A device that is capable of both supplying a loop's power and reading the output signals of each of the instruments in the loop is a

multifunction calibrator

9
New cards

A process loop cannot be tuned until it has been

Calibrated

10
New cards

A normal calibration involves setting the zero and

Span

11
New cards

A database and communications system that help manage a plant's instruments, maintenance, calibration, and other resources is known as a(n)

IAMS

12
New cards

Commissioning cannot be considered complete without full

documentation

13
New cards

The drawing that shows all of the connection details of the control system components arrange into a loop is the

Loop diagram

14
New cards

A list of instrument tag numbers may be found on the

instrument index

15
New cards

In the final stages of commissioning, the loop control is run in

automatic

16
New cards

Although this is usually done at the factory or during proving, a typical commissioning procedure includes verifying that the instruments have been

Calibrated

17
New cards

When identifying a problem ina loop, a useful place to look is the loop's

maintenance records

18
New cards

In order to effectively troubleshoot a loop, it is crucial to

understand the loop's operation

19
New cards

A process that reacts to a disturbance and never stabilizes in a reasonable time period is said to be

oscillating

20
New cards

A useful way of exploring whether the controller is at fault in a loop problem is switching it to

manual mode