which of the following is the least likely to be a CE
a) minor land acquisition for adding signs and pavement markings on Rock Quarry Rd.
b) elderly and disabled accessible alterations to the Wabash bus station
c) acquisition of scenic easements along I-70
d) CoMo Shortline track and railbed maintenance and improvement with additional right of way
d) CoMo Shortline track and railbed maintenance and improvement with additional right of way
what is not a potential outcome of EA?
a) EIS
b) categorical exclusion environmental study
c) FONSI
b) categorical exclusion environmental study
what is the typical sequence of an EIS?
a) circulate draft EIS, NOI, public comments, ROD
b) NOI, circulate draft EIS, public comments, ROD
c) NOI, public comments, circulate draft EIS, ROD
d) Notice of Intent, Final EIS, public comments, ROD
b) NOI, circulate draft EIS, public comments, ROD
which of the following is untrue about resource-specific environmental laws?
a) they are not tied to federal funding unlike NEPA
b) they involve resources such as wildlife, waters of the US, and air
c) they could involve permitting, such as obtaining a Section 404 permit from the Corps
d) they are all satisfied via the NEPA planning process
d) they are all satisfied via the NEPA planning process
which of the following is not a resource-specific environmental law covered in the lecture video?
a) environmental justice in the fair treatment of all peoples regardless of race, color, or income
b) superfund law
c) environmental planning and zoning law
d) clean Air Act which even governs noise pollution
c) environmental planning and zoning law