The process improvement technique that sorts the vital few from the trivial many is
Pareto Analysis
A fishbone chart is also known as a
Cause and Effect Diagram
When sample measurements fall inside the control limits, it means that
If there is no other patterns in the sample, the process is in control
Pareto charts are used to
Organize errors, problems, or defects
If x-bar = 23 ounces, sigma = 0.4 ounces and n = 16, what will be the +-3sigma control limits for the x-bar chart?
22.70 to 23.30
To set x-bar chart upper and lower control limits, one must know the process central line which is the
Average of the sample means
Which of the following is true regarding the process capability index Cpk?
The larger the Cpk, the more units meet specifications
A manager wishes to build a 3-sigma range chart for a process. The sample size is five, the mean of the sample is 16.01 and the average range is 5.3 from table s6.1, the appropriate value of D3 is 0, and D4 is 2.115. What is the UCL and LCL, respectively for this range court?
11.2 and 0
Assignable Variations
Is to be identified and investigated
A product-focused process is commonly used to produce
High volume, low variety products
Break-even is the number of units at which
Total revenue equals total cost
Fabricators, inc. wants to increase capacity by adding a new machine. The fixed costs machine A are $90,000 and its variable costs is $15 per unit. The revenue is $21 per unit. What is the break-even point for machine A?
15,000 units
A work system has five stations that have process times of 5+9+4+9+8. What is the bottleneck time?
9
For a 3-sigma x-bar chart where the process standard deviation is known, the upper control limit
Is 3sigmasqrtn above the means of a 3sigma control chart
The c-chart signals whether there has been a
Change in the number of defects per unit
Professional services typically require low levels of labor intensity
False
Effective Capacity is the
Capacity a firm expects to achieve given the current operating constraints
Utilization will always be lower than design capacity
Effective capacity is less than design capacity
Which of the following statements regarding fixed costs is true?
While fixed costs are ordinarily constant with respect to volume, they can “step” upward if volume increases result in additional fixed costs
Which of the following costs would be incurred even if no units were produced?
Building rental costs