WEEK THREE OPERATIONS CONTENT

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/18

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 10:54 PM on 9/24/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

19 Terms

1
New cards

Demand vs Capacity Mismatch

When incoming demand rate exceeds system capacity rate, causing inventory to continuously build up in queues or buffers.

2
New cards

Inventory Buildup Rate

The rate at which backlog accumulates per unit of time, calculated as Demand Rate minus Capacity Rate.

3
New cards

Inventory Buildup Rate Formula

Buildup Rate = Demand Rate - Capacity Rate

4
New cards

Peak Inventory

The maximum inventory or backlog accumulated in a system, occurring at the exact moment incoming deliveries or arrivals stop.

5
New cards

Peak Inventory Formula

Peak Inventory = Inventory Buildup Rate x Duration of Inflow (hours).

6
New cards

Clearing Time

The time required to process the remaining accumulated backlog after new arrivals have stopped.

7
New cards

Clearing Time Formula

Clearing Time = Peak Inventory / Processing Capacity Rate.

8
New cards

Makespan

The total elapsed time from when a facility opens for incoming jobs to when all processing finishes and inventory reaches zero.

9
New cards

Makespan Formula

Makespan = Inflow Duration + Clearing Time.

10
New cards

Holding Bin Capacity Limit

The fixed maximum storage capacity of an internal buffer; once full, inventory shifts to external waiting lines (like truck queues).

11
New cards

Truck Queue Start Time

The point in time when internal storage becomes 100% full, forcing arriving vehicles to wait outside in line.

12
New cards

Average Queue Length (Triangle Rule)

For a linearly growing line that builds from 0 to a maximum (Peak Queue), the average queue length is equal to 1/2 of the peak queue height.

13
New cards

Total Wait Time (Vehicle-Hours)

The cumulative waiting time experienced by all vehicles, calculated as Average Queue Length x Duration of Queue.

14
New cards

Longest Waiting Vehicle

The vehicle that arrives at the exact moment inflow stops, sitting at the end of the maximum queue and waiting for the full clearing time.

15
New cards

Elevating a Bottleneck

Taking targeted operational actions to increase the processing capacity of the system's slowest constraint.

16
New cards

Bottleneck Elevation Tactics

Adding parallel processors, reducing step processing time, staggering operator breaks, ensuring preventive maintenance, and keeping spare parts ready.

17
New cards

Non Bottleneck Capital Trap

Spending money or adding machinery upstream or downstream of a bottleneck, which fails to increase system throughput and only increases WIP.

18
New cards

Quality Check Placement Rule

Locating quality inspections immediately before a bottleneck so the constrained resource never wastes time on defective parts.

19
New cards

Mixed Product Flow Rule

Tracing distinct product flows separately through shared and unique steps to isolate individual product bottlenecks.