Levelling
A surveying technique used to determine the elevation of points on the ground.
Closed Level Traverse
A series of level runs from a known Datum or Reduced Level (RL) back to a known Datum.
Misclosure
The difference between the measured height difference and the known height difference.
Collimation Error
An error due to the line of sight not being perfectly horizontal.
Two-Peg Test
A field calibration procedure to determine and reduce collimation error in level instruments.
Back Sight (BS)
The first reading taken after setting the instrument, taken at a point of known elevation.
Fore Sight (FS)
The last reading taken before moving the instrument, taken at a point of unknown elevation.
Temporary Benchmark (TBM)
A self-made point which has a transferred value of reduced level (RL).
Height of Collimation (HOC)
An alternative method for calculating using the height of the collimation.