1/85
A comprehensive set of flashcards covering project finance structures, life cycles, tax equity, credit mechanics, contracting (EPC/O&M), and regulatory frameworks in the renewable energy sector.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai | Chat |
|---|
No analytics yet
Send a link to your students to track their progress
Project finance
Lending against the cash flows of a discrete, ring-fenced project rather than against the balance sheet of the sponsor, with recourse limited to the project company and its assets.
Non-recourse vs limited recourse
Non-recourse means lenders look only to project assets and cash flows. Limited recourse means the sponsor provides defined credit support but is not on the hook for the loan generally.
Ring-fencing
Isolating the project in a special purpose entity so its assets and liabilities are separated from the sponsor's other businesses and from other projects.
Special purpose vehicle (SPV)
The bankruptcy-remote project company that owns the project, holds the contracts and permits, and borrows the debt.
Bankruptcy remoteness
Structural features designed to reduce the risk that the project company is drawn into a sponsor bankruptcy, such as separateness covenants and independent managers.
Independent manager or independent director
A person on the project company's governing body whose consent is required for a bankruptcy filing, designed to protect lenders from a voluntary filing driven by the sponsor.
Sponsor
The developer or owner that originates the project, contributes equity, and typically provides development-stage credit support.
Development stage
The period covering site control, resource assessment, permitting, interconnection, and offtake procurement, funded by sponsor equity or development capital.
Site control
Legal rights to the project land, held as fee ownership, lease, easement, or option, required in a form that lenders can take security over.
Interconnection queue position
The project's place in the transmission provider's study queue, determining when it can connect to the grid; often the most valuable early-stage asset.
Notice to proceed (NTP)
The instruction from the owner to the EPC contractor to begin work, normally requiring financing, permits, interconnection, and offtake to be in place.
Limited notice to proceed (LNTP)
A narrower authorization to begin defined early works, such as procurement of long lead items or site preparation, before full NTP.
Construction period
The phase from NTP to substantial completion where the primary risk is completion risk, funded by construction debt and equity.
Commercial operation date (COD)
The date the project meets contractual performance requirements and begins delivering under the offtake agreement, triggering obligations under the PPA and EPC.
Substantial completion vs final completion
Substantial completion means the project can operate and be handed over; final completion means the punch list is cleared and all obligations are satisfied.
Punch list
The schedule of minor outstanding items at substantial completion, typically backed by retainage or a holdback.
Term conversion
The point at which the construction loan converts to a term loan, conditioned on completion tests and consultant certification.
Operations phase
The post-COD phase where risk shifts to availability, resource variability, offtaker credit, and O&M cost while the project services debt.
Greenfield vs brownfield
Greenfield is a new project built from nothing; brownfield is an existing operating asset being expanded, repowered, or refinanced.
Repowering
Replacing or upgrading major equipment on an existing project to improve output or requalify for tax credits.
Merchant project
A project without a long-term contracted offtake, exposed to market power prices and typically financing at lower leverage and higher cost.
Contracted project
A project with a long-term offtake, supporting higher leverage due to predictable cash flows.
Capital stack
The full set of funding sources ordered by priority: project debt, tax equity, back leverage, sponsor equity, and mezzanine or preferred equity.
Back leverage
Debt at the holdco level above the tax equity partnership, secured by the sponsor's equity interests rather than project assets.
Structural subordination
The result of back leverage where holdco lenders are paid only from distributions reaching the holdco, sitting behind project-level obligations.
Mezzanine debt
Subordinated debt sitting between senior debt and equity, priced higher and sometimes including equity features.
Portfolio financing
Financing several projects together in one facility to diversify resource and offtaker risk.
Warehouse facility
A revolving facility used to fund a pipeline of projects during development and construction, later replaced by permanent financing.
Bankability
Whether a contract's terms will be accepted by lenders as supporting debt by allocating risk away from the project company to creditworthy counterparties.
Power purchase agreement (PPA)
The long-term contract under which an offtaker buys energy, capacity, and environmental attributes from a project at an agreed price.
Physical PPA
A contract where the offtaker takes physical delivery of power at a defined delivery point.
Virtual PPA (VPPA)
A financial contract for differences where the project sells into the market and settles the difference against a strike price with the offtaker.
Contract for differences (CfD)
A settlement mechanism where parties exchange the difference between a market reference price and a fixed strike price.
Basis risk
In a VPPA, the risk that the price at the project's delivery node differs from the price at the settlement hub.
Shape risk
The risk that generation does not occur during the hours when prices or contract terms are most favorable.
Hedge or revenue put
A financial arrangement setting a floor or fixed price on revenue to make merchant projects financeable.
Tolling agreement
An arrangement where the offtaker supplies fuel and pays a capacity charge, leaving the project with availability risk but not commodity risk.
Capacity payment
A payment for making capacity available regardless of energy delivered, which is not volume dependent.
Renewable energy certificate (REC)
A tradable instrument representing the environmental attributes of one megawatt hour (1MWh) of renewable generation.
Curtailment
Reduction of output at the direction of the grid operator or offtaker.
Deemed generation
A contractual construct where the project is paid for curtailed output as if it had been delivered.
Offtaker credit
The creditworthiness of the PPA counterparty, which effectively caps the credit quality of the project.
Corporate PPA
A PPA with a corporate buyer rather than a utility, often involving shorter terms and different credit considerations.
Change in law provisions
Clauses allocating the risk that new laws change project economics, which is highly relevant to tax credit volatility.
Large generator interconnection agreement (LGIA)
The FERC pro forma interconnection agreement for larger generators forming the basis of most US utility-scale interconnections.
Step-in rights
Lender rights to assume or direct performance under project contracts following a default so the project can continue.
Base case model
The financial model agreed at closing used to size debt and test the project against expectations.
Debt sizing
The process of deriving the maximum loan amount from projected cash flows based on a required debt service coverage ratio.
Debt service coverage ratio (DSCR)
DSCR=Scheduled Debt ServiceCFADS. The core credit metric in project finance.
Cash flow available for debt service (CFADS)
Project revenue less operating expenses, taxes, and required reserve funding, calculated before debt service.
Sculpted amortization
Repayment sized so each period's debt service produces a target DSCR against that period's projected cash flow.
Loan life coverage ratio (LLCR)
Net present value of CFADS over the remaining loan term divided by outstanding debt; a forward-looking solvency measure.
Tail
The period of project life extending beyond debt maturity, providing comfort that value remains if refinancing is needed.
P50
The energy production estimate with a 50% probability of being exceeded, representing the central expectation.
P90 and P99
Conservative production estimates exceeded with 90% and 99% probability, used by lenders to size debt.
Independent engineer (IE)
The lender's technical consultant who reviews design, budget, and production estimates and certifies milestones.
Conditions precedent (CP)
Documentary and factual conditions that must be satisfied before funding can occur.
Lien waivers
Contractor releases confirming payment to keep project title clear of mechanics liens.
Mechanics lien
A statutory lien claimed by contractors for unpaid work that can prime or disrupt lender security.
Cash sweep
A mandatory prepayment mechanism applying a percentage of excess cash flow to debt reduction, often used for merchant exposure.
Cash waterfall
The ordered application of project revenue, typically starting with operating expenses and ending with distributions to equity.
Debt service reserve account (DSRA)
A reserve holding approximately six months of forward debt service to be used if cash flow falls short.
Deposit account control agreement (DACA)
The agreement giving a secured party control over deposit accounts for perfection purposes.
Equity cure
The right of the sponsor to contribute cash to remedy a financial covenant breach.
Sacred rights
Amendments requiring every affected lender's consent, such as changes to principal, interest, or maturity.
Pledge of equity interests
A pledge allowing lenders to take ownership of the project entity whole, usually the preferred enforcement route.
Tax equity
Investment made to monetize tax benefits (credits, depreciation, losses) that a sponsor cannot efficiently use.
Partnership flip
A structure where a tax equity investor receives the majority of tax items and a small share of cash until a yield or time-based flip point.
Deficit restoration obligation (DRO)
A partner's obligation to contribute cash on liquidation to restore a negative capital account, allowing the allocation of losses beyond capital balance.
Hypothetical liquidation at book value (HLBV)
The accounting method used in tax equity to determine each partner's share of income based on a theoretical liquidation.
Investment tax credit (ITC)
A credit calculated as a percentage of eligible basis in the project, claimed when the project is placed in service.
Production tax credit (PTC)
A credit calculated per unit of electricity generated and sold over a defined credit period.
Eligible basis
The portion of project cost qualifying for the ITC, excluding land and certain transmission or soft costs.
MACRS
The accelerated depreciation schedule (historically five years) applicable to most renewable energy property.
Beginning of construction (BOC)
The test determining which credit rule vintage applies, satisfied by the physical work test or the five percent safe harbor.
Five percent safe harbor
Meeting BOC requirements by paying or incurring at least 5% of total project cost.
Recapture
The clawback of ITC by the IRS if a property is disposed of or fails to qualify during the five-year vesting period.
Prevailing wage and apprenticeship (PWA)
Labor requirements that, if satisfied, substantially increase the tax credit amount.
Section 6418 transferability
The mechanism permitting an eligible taxpayer to sell certain tax credits for cash to an unrelated party.
Full wrap EPC
A single contractor takes responsibility for the entire scope, providing a single point of accountability to the owner.
Interface risk
The risk that responsibility for a failure falls between the scopes of two different contractors in a split-scope arrangement.
Liquidated damages (LDs)
Pre-agreed damages for delay or performance shortfalls that avoid the need to prove actual loss.
FERC
The Federal Energy Regulatory Commission, which regulates wholesale power sales and transmission.
Exempt wholesale generator (EWG)
A status under PUHCA for entities exclusively in wholesale generation providing relief from certain regulations.
CFIUS
An interagency committee reviewing foreign investment in US businesses on national security grounds.
Membership interest purchase agreement (MIPA)
The standard vehicle for project M&A, transferring equity in the project holdco rather than individual assets.