Compiled Set

5.0(1)
studied byStudied by 1 person
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/187

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

188 Terms

1
New cards
Construction plans
are drawings that show the location, dimensions, and details of the work to be performed.
2
New cards
Construction technical specifications
provide the detailed requirements for the materials, equipment, and workmanship to be incorporated into the project.
3
New cards
Shop drawings
are drawings, charts, and other data prepared by a contractor or supplier which describe the detailed characteristics of equipment or show how specific structural elements or items of equipment are to be fabricated and installed.
4
New cards
Punch list
is the list of deficiencies to be corrected which is prepared at the final inspection.
5
New cards
Claim
is a request by the contractor for a time extension or for additional payment based on the occurrence of an event beyond the contractor’s control that has not been covered by a change order.
6
New cards
Disputes
are disagreements between the contractor and owner over some aspect of contract performance.
7
New cards
Drawings
are construction documents that “show in graphic and quantitative form the extent, design location, relationships, and dimensions of the work to be done.
8
New cards
Project manual
is a single volume that contains all written requirements for a building construction project.
9
New cards
Specifications
constitute that portion of the written requirements for a building construction project that are contained in the divisions of a project manual.
10
New cards
Building Information Modeling (BIM)
presents a database that includes design data, drawings, specifications, materials and systems parameters, and life cycle data, for all the various disciplines involved in a project and relates those data to each other and to the project as a whole to present an overall view of the project.
11
New cards
Financial planning
for a construction project includes cost estimating prior to bidding or negotiating a contract, forecasting project income and expenditure (or cash flow), and determining the amount of work that a construction firm can safely undertake at one time.
12
New cards
Cost estimating
involves estimating the total cost to carry out a construction project in accordance with the plans and specifications.
13
New cards
Project cost control
involves the measurement and recording of project costs and progress and a comparison between actual and planned performance.
14
New cards
Qualification of a contractor
the determination that the contractor possesses both the technical and financial ability to perform the work required by the contract.
15
New cards
Prequalification
under this procedure only those contractors determined to be capable of performing are invited to submit bids for the project.
16
New cards
Bid bond
guarantees that a contractor will provide the required performance and payment bonds if awarded the contract.
17
New cards
Performance bond
guarantees completion of the project as described in the contract documents.
18
New cards
Payment bond
guarantees the payment of subcontractors, laborers, and suppliers by the contractor.
19
New cards
Bidding
a process whereby a prime design professional engaged by an owner, and the design professional's consultants, prepare bidding documents and issue them to a group of constructors.
20
New cards
Negotiation
a process whereby an architect engaged by an owner, and the architect's consultants, prepare negotiation document
21
New cards
Owning costs
fixed costs that are incurred each year whether the equipment is operated or not. Owning costs are made up of the following principal elements: Depreciation, investment (or interest) cost, insurance cost, taxes, and storage cost.
22
New cards
Operating costs
costs that are incurred only when the equipment is used. Service cost represents the cost of oil, hydraulic fluids, grease, and filters as well as the labor required to perform routine maintenance service. Repair cost represents the cost of all equipment repair and maintenance.
23
New cards
Progress payments
payments made at the interval specified in the contract, usually monthly or upon completion of certain milestones.
24
New cards
Retainage
a percentage of the value of work completed that is withheld as a guarantee against defective work and to ensure that the remaining work can be completed within the unpaid amount of the contract.
25
New cards
Change order
a document authorizing changes to the project within the general scope of the contract.
26
New cards
Consequential costs
additional project costs that result from changes or delay in one activity that necessitate changes in resource allocation or progress on other activities.
27
New cards
Delays
interruptions in the orderly progress of a construction project, which may result from a multitude of causes. The three general categories of delay include: those beyond the control of either the contractor or the owner (“acts of God”), those under the control of the owner, and those under the control of the contractor.
28
New cards
Construction Management
refers to the contractual arrangement under which a firm supplies construction management services to an owner.
29
New cards
Quality management
includes such activities as specification development, process control, product acceptance, laboratory and technician certification, training, and communication.
30
New cards
Quality control (QC)
primarily concerned with the process control function.
31
New cards
Bar graph or bar chart schedule
a graphical schedule relating progress of items of work to a time schedule.
32
New cards
CPM
assigns each activity a single fixed duration.
33
New cards
PERT
utilizes probability concepts to deal with the uncertainty associated with activity time estimates.
34
New cards
Activity-on-arrow format
each activity is represented by an arrow that has an associated description and expected duration.
35
New cards
Dummy Activity
does not represent any work and, hence, always has a duration of zero.
36
New cards
Early event time
the earliest time at which each event may occur based on an arbitrary starting time of zero.
37
New cards
Critical path
that path through the network which establishes the minimum project duration.
38
New cards
Float
(slack in PERT terminology) - the amount of scheduling leeway available to an activity.
39
New cards
Activity on-node diagram
a simple form of the activity on-node diagram is the circle diagram or circle notation, in which each activity is represented by a circle containing the activity description, an identifying number, and the activity duration.
40
New cards
Precedence diagram
an extension of the activity-on node format that provides for incorporation of lag-time factors as well as permitting additional precedence relationships.
41
New cards
Early start schedule
when all activities are scheduled to start at the earliest allowable time.
42
New cards
Late start schedule
when all activities are started at their latest allowable starting time.
43
New cards
Value engineering
the analysis of a design with the objective of accomplishing the required function at a lower cost.
44
New cards
Subcontracts
are contracts between a prime contractor and secondary contractors or suppliers.
45
New cards
Negotiated contract
is one negotiated between an owner and a construction firm.
46
New cards
Lump-sum contract
provides a specified payment for completion of the work described in the contract documents.
47
New cards
Unit-price contracts
specify the amount to be paid for each unit of work but not the total contract amount.
48
New cards
Fixed price with escalation contracts
contain a provision whereby the contract value is adjusted according to a specified price index.
49
New cards
Cost plus percentage of cost contract
pays the contractor a fee that is a percentage of the project’s actual cost.
50
New cards
Construction contract
consists of the following documents: Agreement, Conditions of the Contract (usually General Conditions and Special Conditions), Plans, Specifications.
51
New cards
Agreement
describes the work to be performed, the required completion time, contract sum, provisions for progress payments and final payment, and lists the other documents making up the complete contract.
52
New cards
General Conditions
contain those contract provisions applicable to most construction contracts written by the owner.
53
New cards
Special Conditions
contain any additional contract provisions applicable to the specific project.
54
New cards
Contract Time
is the time allowed (expressed as either days allowed or as a required completion date) for completion of a construction project that is normally specified in the contract along with the phrase “time is of the essence.”
55
New cards
Liquidated damages
clause in the contract may be used to simplify the process of establishing the amount of damages resulting from late completion.
56
New cards
foundation
The part of a structure that supports its weight and the weight of applied loads.
57
New cards
spread footing
The simplest and most common type of building foundation that includes individual footings, combined footings, and mat foundations.
58
New cards
mat or raft foundation
A heavily reinforced concrete slab extending under the entire structure, used to spread the structure's load over a large area.
59
New cards
floating foundation
A type of mat foundation in which the weight of the soil excavated approximately equals the weight of the structure being erected.
60
New cards
ground modification
The process of improving soils in place, also known as soil stabilization.
61
New cards
pile
A column driven into the soil to support a structure by transferring building loads to a deeper and stronger layer of soil or rock.
62
New cards
precast concrete piles
Piles that may be manufactured in almost any desired size or shape.
63
New cards
cast-in-place concrete piles
Piles constructed by driving a steel shell into the ground and then filling it with concrete.
64
New cards
steel piles
Piles made of steel that are capable of supporting heavy loads, can be driven to great depth without damage, and are easily cut and spliced.
65
New cards
composite piles
Piles made up of two or more different materials.
66
New cards
bulb piles
A special form of cast-in-place concrete pile in which an enlarged base (or bulb) is formed during driving.
67
New cards
pier
A column, usually of reinforced concrete, constructed below the ground surface.
68
New cards
caisson
A structure used to provide all-around lateral support to an excavation. Caissons may be either open or pneumatic.
69
New cards
liquefaction
A condition in which the water pressure exactly equals soil weight, causing the soil to behave like a liquid.
70
New cards
boiling or piping
A condition in which the water pressure is strong enough to move subsurface soil up through the bottom of a cut.
71
New cards
shoring
A method of providing lateral support for the sides of an excavation.
72
New cards
lagging
Sheet placed horizontally for shoring.
73
New cards
sheet piling
Sheeting of concrete, steel, or timber that is designed to be driven by a pile driver.
74
New cards
trench shields or trench boxes
Used in place of shoring to protect workers during trenching operations.
75
New cards
dewatering
The process of removing water from an excavation.
76
New cards
soil permeability
The ease with which water flows through soil, primarily a function of the soil's grain size distribution.
77
New cards
wellpoint
The perforated assembly placed on the bottom of the inlet pipe for a well.
78
New cards
vacuum wells
Wellpoints that are sealed at the surface by placing a ring of bentonite or clay around the well casing.
79
New cards
electroosmosis
The process of accelerating the flow of water through soil by the application of a direct current.
80
New cards
grouting or pressure grouting
The process of injecting a grouting agent into soil or rock to increase its strength or stability, protect foundations, or reduce groundwater flow.
81
New cards
Running bond
a pattern bond that uses only stretcher courses with head joints centered over stretchers in the course below.
82
New cards
Common bond
a pattern bond that uses a header course repeated at regular intervals; usually every fifth, sixth, or seventh course.
83
New cards
Flemish bond
a pattern bond that alternates stretchers and headers in each course with headers centered over stretchers in the course below.
84
New cards
English bond
a pattern bond made up of alternate courses of headers and stretchers, with headers centered on stretchers.
85
New cards
Stack bond
a pattern bond that provides no interlocking between adjacent masonry units and is used for its architectural effect.
86
New cards
Bond beam
a continuously reinforced horizontal beam of concrete or masonry designed to provide additional strength and to prevent cracking in a masonry wall.
87
New cards
Expansion or control joints
joints in masonry walls used to permit differential movement of wall sections caused by shrinkage of concrete foundations and floor slabs, temperature and moisture changes, and foundation settlement.
88
New cards
Flashing
layers of impervious material used to seal out moisture or to direct any moisture that does penetrate back to the outside.
89
New cards
Fuel-resistant asphalt
often based on a polymer-modified asphalt (PMA), is available and has demonstrated high resistance to rutting and cracking as well as to petroleum fuels.
90
New cards
Asphalt cutback
is liquid at room temperature and is created when petroleum distillates are mixed with asphalt cement.
91
New cards
Asphalt emulsions
contain particles of asphalt dispersed in water by means of emulsifying agents.
92
New cards
Flash point
of a liquid is the temperature at which it produces sufficient vapor to ignite in the presence of air and an open flame.
93
New cards
Slipform paver
is capable of spreading, consolidating, and finishing a concrete slab without the use of conventional forms.
94
New cards
Tack coat
is a thin coating of light bituminous material applied to a previously paved surface to act as a bonding agent.
95
New cards
Dust palliative
is a substance applied to an unpaved surface to reduce the amount of dust produced by vehicular traffic and wind.
96
New cards
Fog seal
is a light application of a slow-setting asphalt emulsion diluted by one to three parts of water.
97
New cards
Emulsion slurry seal
is composed of a mixture of slow-setting asphalt emulsion, fine aggregate, mineral filler, and water.
98
New cards
Sand seal
is composed of a light application of a medium-viscosity liquid asphalt covered with fine aggregates.
99
New cards
Single-pass and multiple-pass surface treatments
sometimes called aggregate surface treatments, are made up of alternate applications of asphalt and aggregate.
100
New cards
Single-pass surface treatment
is constructed by spraying on a layer of asphalt and covering it with a layer of aggregate approximately one stone in depth.