Chapter 7: Managing Project Costs

0.0(0)
studied byStudied by 0 people
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/41

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

42 Terms

1
New cards

actual cost (AC)

The actual amount of monies the project has spent to date.

2
New cards

analogous estimating

An approach that relies on historical information the cost of the current project. It is also known as top-down estimating and is the least reliable of all the cost-estimating approaches.

3
New cards

bottom-up estimating

An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs.

4
New cards

budget estimate

An estimate that is somewhat broad and is used early in the planning processes as well as in top-down estimates. The range of variance for the estimate can be from -10 percent to +25 percent.

5
New cards

commercial database

A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.

6
New cards

contingency reserve

A contingency allowance to account for overruns in costs. Contingency reserves are used at the project manager's discretion and with management's approval to counteract cost overruns for scheduled activities and risk events.

7
New cards

cost aggregation

Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.

8
New cards

cost budgeting

Applies the cost estimates over time.

9
New cards

cost baseline

A time-lapse exposure of when the project monies are to be spent in each of the scheduled activities or, more likely, for each of the work packages in the WBS.

10
New cards

cost budgeting

The cost aggregation achieved by assigning specific dollar amounts for.

11
New cards

cost change control system

A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.

12
New cards

cost management plan

A plan that dictates how cost variances will be managed.

13
New cards

cost of poor quality

The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.

14
New cards

cost of quality

The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.

15
New cards

cost performance index (CPI)

Measures the project based on its financial performance. The formula is CPI = EV/AC.

16
New cards

cost variance (CV)

The difference of the earned value amount and the cumulative actual costs of the project. The formula is CV = EV – AC.

17
New cards

definitive estimate

One of the most accurate estimate types. It's used late in the planning processes and is associated with bottom-up estimating. You need the WBS to create the definitive estimate. The range of variance for the estimate can be from -5 percent to +10 percent.

18
New cards

direct costs

Costs are attributed directly to the project work and cannot be shared among projects (for example, airfare, hotels, long-distance phone charges, and so on).

19
New cards

earned value (EV)

The physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.

20
New cards

estimate at completion (EAC)

Forecasting formulas that predict the likely completed costs of the project based on current scenarios within the project.

21
New cards

estimate to complete (ETC)

An earned value management formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.

22
New cards

fixed costs

Costs that remain constant throughout the life of the project (such as of rented equipment for the project, the cost of a consultant brought on to the project, and so on).

23
New cards

funding limit reconciliation

An organization's approach to managing cash flow at the project deliverables based on a schedule, milestone accomplishment, or data constraints.

24
New cards

known unknown

An event that will likely happen within the project, but when it will happen and to what degree is unknown. These events, such as delays, are usually risk-related.

25
New cards

learning curve

An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.

26
New cards

oligopoly

A market condition in which the market is so tight that the actions of one vendor affect the actions of all the others.

27
New cards

opportunity cost

The total cost of the opportunity that is refused to realize an opposing opportunity.

28
New cards

parametric estimating

An approach using a parametric model to extrapolate what costs will be needed for a project (for example, cost per hour and cost per unit). It can include variables and points based on conditions.

29
New cards

planned value (PV)

The work scheduled and the budget authorized to accomplish that work. It is the percentage of the BAC that reflects where the project should be at this point in time.

30
New cards

project variance

The final variance, which is discovered only at the project's completion. The formula is VAR = BAC - AC.

31
New cards

regression analysis

A statistical approach to predicting what future values may be, based on historical values. Regression analysis creates quantitative predictions based on variables within one value to predict variables in another.

32
New cards

reserve analysis

Cost reserves are for unknown unknowns within a project. The management reserve is not part of the project cost baseline, but it is included as part of the project budget.

33
New cards

rough order of magnitude

A rough estimate used during the initiating processes and in top-down estimates. The range of variance for the estimate can be from -25 percent to +75 percent.

34
New cards

schedule performance index (SPI)

Measures the project based on its schedule performance. The formula is SPI = EV/PV.

35
New cards

schedule variance (SV)

The difference between the earned value and the planned value. The formula is SV = EV - PV.

36
New cards

single source

When many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor.

37
New cards

sole source

Only one vendor can provide what your project needs to purchase. Examples include a specific consultant, specialized service, or unique type of material.

38
New cards

sunk costs

Monies that have already been invested in a project.

39
New cards

to-complete performance index (TCPI)

A formula to forecast the likelihood of a project to achieve its goals based on what's happening in the project currently. Two formulas: TCPI = (BAC - EV)/(BAC - AC) or TCPI = (BAC - EV)/(EAC - AC).

40
New cards

variable costs

Costs that change based on the conditions applied in the project (the number of meeting participants, the supply of and demand for materials, and so on).

41
New cards

variance

The difference between what was expected and what was experienced.

42
New cards

variance at completion (VAC)

A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. The formula is VAC = BAC - EAC.