York Fire Station No. 2 - Capstone Defense Flashcards

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/52

flashcard set

Earn XP

Description and Tags

Vocabulary practice cards for the York Fire Station No. 2 Capstone project, covering financials, team, schedule, and contract details.

Last updated 5:35 PM on 7/22/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

53 Terms

1
New cards

Stipulated Contract Sum

2,328,284.752,328,284.75

2
New cards

Cost per square foot

269.07269.07 per SF

3
New cards

Total building size

8,635SF8,635\,SF (4,400SF4,400\,SF living quarters + 4,253SF4,253\,SF apparatus bay)

4
New cards

Site location and size

2.2acres2.2\,acres on the Old York Road corridor, off SC-5 / SC-161, York, SC

5
New cards

Direct cost subtotal

2,014,6732,014,673

6
New cards

Labor burden amount

247,726247,726

7
New cards

Sales tax amount

35,66535,665

8
New cards

P&P bond cost

30,22030,220 (1.5%1.5\% of contract price)

9
New cards

Project duration

252workingdays252\,working\,days / 362calendardays362\,calendar\,days (NTP to turnover)

10
New cards

Notice to Proceed date

July 27, 2026

11
New cards

Dry-in milestone date

March 11, 2027

12
New cards

Turnover date

July 23, 2027

13
New cards

Retainage percentage

5%5\% on completed work AND stored materials

14
New cards

Liquidated damages

500500 per calendar day late

15
New cards

Extended General Conditions cost

Approximately $2,300\$2,300 per workday delay

16
New cards

Total Value Engineering savings

119,236119,236 (107,743107,743 CMU + 11,49311,493 sealer)

17
New cards

Contract backloading

Approximately 76%76\% of the contract value is backloaded into the final 8 months

18
New cards

Project Owner

City of York, South Carolina

19
New cards

Architect

Palmetto Architecture Group, LLC - J. Randall Pruitt, AIA, Principal

20
New cards

Apparatus bay oil/water separator capacity

1,000gallons1,000\,gallons

21
New cards

Roof structural components

59 open-web steel joists with a maximum span up to 46feet46\,feet and 8,433SF8,433\,SF of metal roof deck

22
New cards

Maximum wall height

20feet8inches20\,feet\,8\,inches

23
New cards

Delivery method

Single prime contractor

24
New cards

Burks Construction Company

Founded 2002, headquartered in Atlanta; self-performs concrete, masonry, metals, finishes, and sitework

25
New cards

Brenan Burks (Project Manager)

7 years experience, B.S. Construction Management from Kennesaw State, OSHA 30, PMP

26
New cards

Tim Wattley (Superintendent)

18 years experience, B.S. CM Georgia Southern, OSHA 30, NPDES 1A, STS-C; designated competent person for excavation, scaffolds, and fall protection

27
New cards

Lesley Chow (Field Engineer)

3 years experience, B.S. Building Science from Auburn; serves as SSHO (Site Safety & Health Officer) and is CHST-certified

28
New cards

Division 01 General Conditions

550,800550,800 (63.65/SF63.65/SF); comprises 23.7%23.7\% of the contract

29
New cards

Division 09 Finishes

321,334321,334 (37.14/SF37.14/SF)

30
New cards

Division 32 Site Improvements

192,233192,233 (22.22/SF22.22/SF)

31
New cards

Division 05 Metals

190,070190,070 (21.97/SF21.97/SF)

32
New cards

Division 04 Masonry

158,918158,918 (18.37/SF18.37/SF)

33
New cards

Estimating pricing sources

Quantity takeoffs priced with RSMeans, company historical cost records, and current market prices

34
New cards

Plumbing scope distribution

45K45K subcontracted plus $14.9K\$14.9K self-performed

35
New cards

VE Item 1

12-inch reinforced CMU replaced 12-inch cast-in-place concrete (28.50/SF28.50/SF over 7,793SF7,793\,SF), saving 107,743107,743

36
New cards

VE Item 2

SpecChem All Shield WB liquid densifier/sealer replaced multi-coat epoxy, saving 11,49311,493

37
New cards

VE Item 3

5.0mm5.0\,mm commercial-grade LVT with 20mil20-mil wear layer (Mohawk Hot & Heavy II) replaced engineered hardwood

38
New cards

Schedule WBS Phases

9 phases: Preconstruction, Sitework, Foundations, Structure, Building Envelope, MEP Rough-In, Interior Finishes, Site Improvements, Closeout

39
New cards

Critical path chain

42 workdays of masonry -> single crane mobilization for steel -> dry-in (overhead doors and storefront glazing) -> finish phase

40
New cards

Masonry logic tie

SS+6SS+6 (Start-to-Start plus 6 days) for bond beams/grout lifts relative to CMU

41
New cards

Long-lead items

Roof joists, roof deck, and apparatus bay overhead doors

42
New cards

Primary Contract Forms

AIA A101 (Agreement) and AIA A201-2007 (General Conditions)

43
New cards

Substantial Completion requirement

Within 340calendardays340\,calendar\,days of commencement (July 2, 2027)

44
New cards

Dispute resolution path

Mediation first, then litigation

45
New cards

Insurance Limits (CGL)

1M1M each occurrence / 2M2M general aggregate / 2M2M products-completed operations

46
New cards

Subcontractor Contract Form

AIA A401 (flow-down obligations, pay-when-paid, matching 5%5\% retainage)

47
New cards

Monthly billing forms

G702/G703 AIA pay-application forms

48
New cards

Pay App 4 (Nov 2026) status

114,591114,591 billed, 24.0%24.0\% cumulative complete; concrete 100%100\% done, CMU at 8%8\%

49
New cards

S-curve spending peaks

February 2027 (~$357K\$357K) and June 2027 (~$342K\$342K)

50
New cards

Risk scoring formula

Probability×ImpactProbability \times Impact on 151-5 scales (max score 2525)

51
New cards

Risk #1

Winter weather halting critical-path masonry (score 16)

52
New cards

OSHA regulations

29 CFR Parts 190429\text{ CFR Parts } 1904 (recordkeeping), 19101910 (general industry), and 19261926 (construction)

53
New cards

Activity Hazard Analysis (AHA)

Required for structural steel erection, designated the highest-risk operation