Vocabulary practice cards for the York Fire Station No. 2 Capstone project, covering financials, team, schedule, and contract details.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai | Chat |
|---|
No analytics yet
Send a link to your students to track their progress
Stipulated Contract Sum
2,328,284.75
Cost per square foot
269.07 per SF
Total building size
8,635SF (4,400SF living quarters + 4,253SF apparatus bay)
Site location and size
2.2acres on the Old York Road corridor, off SC-5 / SC-161, York, SC
Direct cost subtotal
2,014,673
Labor burden amount
247,726
Sales tax amount
35,665
P&P bond cost
30,220 (1.5% of contract price)
Project duration
252workingdays / 362calendardays (NTP to turnover)
Notice to Proceed date
July 27, 2026
Dry-in milestone date
March 11, 2027
Turnover date
July 23, 2027
Retainage percentage
5% on completed work AND stored materials
Liquidated damages
500 per calendar day late
Extended General Conditions cost
Approximately $2,300 per workday delay
Total Value Engineering savings
119,236 (107,743 CMU + 11,493 sealer)
Contract backloading
Approximately 76% of the contract value is backloaded into the final 8 months
Project Owner
City of York, South Carolina
Architect
Palmetto Architecture Group, LLC - J. Randall Pruitt, AIA, Principal
Apparatus bay oil/water separator capacity
1,000gallons
Roof structural components
59 open-web steel joists with a maximum span up to 46feet and 8,433SF of metal roof deck
Maximum wall height
20feet8inches
Delivery method
Single prime contractor
Burks Construction Company
Founded 2002, headquartered in Atlanta; self-performs concrete, masonry, metals, finishes, and sitework
Brenan Burks (Project Manager)
7 years experience, B.S. Construction Management from Kennesaw State, OSHA 30, PMP
Tim Wattley (Superintendent)
18 years experience, B.S. CM Georgia Southern, OSHA 30, NPDES 1A, STS-C; designated competent person for excavation, scaffolds, and fall protection
Lesley Chow (Field Engineer)
3 years experience, B.S. Building Science from Auburn; serves as SSHO (Site Safety & Health Officer) and is CHST-certified
Division 01 General Conditions
550,800 (63.65/SF); comprises 23.7% of the contract
Division 09 Finishes
321,334 (37.14/SF)
Division 32 Site Improvements
192,233 (22.22/SF)
Division 05 Metals
190,070 (21.97/SF)
Division 04 Masonry
158,918 (18.37/SF)
Estimating pricing sources
Quantity takeoffs priced with RSMeans, company historical cost records, and current market prices
Plumbing scope distribution
45K subcontracted plus $14.9K self-performed
VE Item 1
12-inch reinforced CMU replaced 12-inch cast-in-place concrete (28.50/SF over 7,793SF), saving 107,743
VE Item 2
SpecChem All Shield WB liquid densifier/sealer replaced multi-coat epoxy, saving 11,493
VE Item 3
5.0mm commercial-grade LVT with 20−mil wear layer (Mohawk Hot & Heavy II) replaced engineered hardwood
Schedule WBS Phases
9 phases: Preconstruction, Sitework, Foundations, Structure, Building Envelope, MEP Rough-In, Interior Finishes, Site Improvements, Closeout
Critical path chain
42 workdays of masonry -> single crane mobilization for steel -> dry-in (overhead doors and storefront glazing) -> finish phase
Masonry logic tie
SS+6 (Start-to-Start plus 6 days) for bond beams/grout lifts relative to CMU
Long-lead items
Roof joists, roof deck, and apparatus bay overhead doors
Primary Contract Forms
AIA A101 (Agreement) and AIA A201-2007 (General Conditions)
Substantial Completion requirement
Within 340calendardays of commencement (July 2, 2027)
Dispute resolution path
Mediation first, then litigation
Insurance Limits (CGL)
1M each occurrence / 2M general aggregate / 2M products-completed operations
Subcontractor Contract Form
AIA A401 (flow-down obligations, pay-when-paid, matching 5% retainage)
Monthly billing forms
G702/G703 AIA pay-application forms
Pay App 4 (Nov 2026) status
114,591 billed, 24.0% cumulative complete; concrete 100% done, CMU at 8%
S-curve spending peaks
February 2027 (~$357K) and June 2027 (~$342K)
Risk scoring formula
Probability×Impact on 1−5 scales (max score 25)
Risk #1
Winter weather halting critical-path masonry (score 16)
OSHA regulations
29 CFR Parts 1904 (recordkeeping), 1910 (general industry), and 1926 (construction)
Activity Hazard Analysis (AHA)
Required for structural steel erection, designated the highest-risk operation